Elmbridge Borough Council
East Surrey Shadow Authority Executive, Monday 9 November 2026 at 10.00am

Risk Management Approach for East Surrey Council

Decided Executive 7 papers

AI summaryEast Surrey Shadow Authority Executive's report recommends Option 1. [P6] [P7] [P40] It would oversee corporate risks from Day 1, retain legacy service arrangements until later harmonisation, and have no direct financial implications. [P18] [P19] [P26] [P81]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCorporate oversight from Day 1, then harmonisation. [P14] [P18] [P26]
MoneyNo direct financial implications [P81] [P86]Option 1 can use existing resources. [P81]
What happens nextCorporate risk register development [P22]Senior Leadership Team starts in January 2027. [P22]
Who it affectsCouncil corporate risk oversight [P2]Members and officers gain risk oversight. [P13] [P21]

What was decided

The report recommends approval of Option 1, having regard to comments from the Audit and Governance Committee. Option 1 provides corporate oversight from Day 1 and allows later harmonisation. Report P7, P14, P18, P26, P74

The report recommends that legacy councils continue their current service risk policies and frameworks below corporate level. This would continue until a comprehensive, harmonised framework is developed after vesting day. Report P6, P8, P10, P19, P26

Why

A phased approach is proportionate and deliverable during reorganisation. It supports robust oversight and accountability from vesting day. Report P12

It provides oversight of corporate risks, awareness of inherited risks, assurance over legacy service risks and a route for escalation. Report P2, P58, P61

It supports a safe and legal transition and the statutory Best Value standards. Report P11, P13, P88

What happens next

Members will take part in risk sessions during the Member Induction Programme in December 2026. One online session and one in person session will be offered. Report P21, P66, P75

The Senior Leadership Team will begin developing the corporate risk register in January 2027. Newly appointed Executive Directors are expected to own relevant risks between January and March 2027. The Chief Executive will own the register, with the Senior Leadership Team managing it. Report P22, P23, P62

After vesting day, East Surrey Council will develop a comprehensive framework, agree risk appetite and tolerance, and harmonise systems and risks. It will also provide training and confirm the coordinating team. Report P64, P65, P66, P67

Options considered

  • Chosen: Option 1: phased approach from vesting day, then comprehensive harmonisation. The report identifies it as preferred. It provides oversight from Day 1 while recognising current organisational and resource constraints. Report P14, P40, P41, P42
  • Rejected: Option 2: postpone risk management development until after vesting day. East Surrey Council would lack oversight of corporate risks, assurance over legacy service risks and escalation for significant new risks. Report P32, P33, P34, P35
  • Rejected: Option 3: develop a comprehensive harmonised framework by March 2027. It would require substantial work and officer resources while recruitment and governance were still developing. Any framework would be likely to need revision soon after implementation. Report P36, P37, P38, P39

Implications

  • Financial: Option 1 can be delivered with existing resources. The proposal has no direct financial implications. East Surrey Council still faces significant budget pressures, rising demand and costs, limited resources and reducing government funding. Report P81, P85, P86
  • Legal: The phased framework supports a safe and legal transition. It also provides mitigation for risks to strategic objectives. Report P11, P88
  • Risk: From Day 1, East Surrey Council would have corporate risk oversight, inherited risk awareness, service risk assurance and an escalation route. Internal and external committee reporting arrangements are still to be confirmed. Report P2, P18, P58, P61
  • Risk: Misalignment with strategy, reorganisation, budgeting and service planning could reduce clarity on the emerging risk profile. Regular coordination and governance milestones are intended to manage this. Report P77, P79
  • Staffing: The approach does not itself change staffing structures, roles or terms and conditions. Delivery depends on officer capacity, clear accountability, guidance, communication and training. Report P91
  • Staffing: Later changes affecting roles, responsibilities, working methods or systems must use the Council's people and change arrangements. Staff and recognised trade union engagement would occur where appropriate. Report P92
  • Equalities: No direct impact is expected on residents or staff with different protected characteristics. Report P94
  • Climate: No direct climate change or sustainability impacts are expected. Controls would be put in place if either were included as risks. Report P83

Who and where

  • East Surrey Council Report P2, P48
  • legacy councils Report P19, P63
  • Council Members Report P13, P21
  • Chief Executive Report P62
  • Senior Leadership Team Report P22, P62
  • newly appointed Executive Directors Report P23
  • officers Report P91
  • staff Report P92, P94

Timeline

  • July 2026: A risk management sub workstream was established. Report P52
  • September and October 2026: The Vesting Day Readiness Board and Officer Board endorsed the proposal. Report P73
  • 2 November 2026: The Audit and Governance Committee received the proposal and submitted its comments to the Executive. Report P74
  • December 2026: Member induction engagement is planned, and Vesting Day Blueprints are due during the month. Report P21, P25, P66, P75
  • January 2027: The Senior Leadership Team will begin developing the corporate risk register. Report P22
  • Between January and March 2027: Newly appointed Executive Directors are expected to own relevant corporate risk areas. Report P23
  • Day 1: Corporate risk oversight and escalation arrangements are intended to operate. Report P18, P48
  • post vesting day: A comprehensive risk framework and harmonised arrangements will be developed. Report P26, P64, P65

Plain English for the jargon

  • Vesting day: The point from which East Surrey Council's new arrangements operate. [P48] [P61]
  • Corporate risk: The most significant risks to the organisation in delivering its Council Strategy and priorities. [P2]
  • Corporate Risk Register: The register where corporate risks are identified and assessed for impact and likelihood. [P55]
  • Service risk: Risk below corporate level, managed under each legacy council's arrangements until harmonisation. [P19] [P63]
  • Risk appetite and risk tolerance: Framework elements that East Surrey Council will develop and agree after vesting day. [P26] [P65]
  • Risk assessment matrix: The scoring system used to assess a risk's impact and likelihood. [P55] [P56]
  • Escalation: The route for discussing legacy service risks and considering possible inclusion on the corporate risk register. [P58]
  • Harmonisation: Later work to bring legacy risks, systems and methods into one common approach. [P63] [P65]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item82/E

Resolved

View the decision text for item 82/E
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to East Surrey Shadow Authority Executive

Purpose of the report

The purpose of this report is to set out the proposed approach to Risk Management for East Surrey Council (ESC) approval.

This report sets out the minimum viable arrangements that enable ESC to have oversight of corporate risk (the most significant risks to the organisation in the delivery of its Council Strategy and priorities), to have awareness of corporate risks inherited from legacy councils, assurance that legacy council service risks are being managed effectively, and that risk escalation arrangements are in place. A suite of draft tools is provided that would enable the development of a Corporate Risk Register, as organisational and governance arrangements develop.

Apart from the management of corporate risk and escalation arrangements, legacy councils would continue to operate according to their current risk management policies and frameworks post-vesting day.

Harmonisation of service risks, risk matrices, systems and other arrangements would take place post-vesting day as services and organisational structures stabilise. A comprehensive Risk Management Framework would be developed, including elements such as risk appetite and risk tolerance.

The recommendations in this report provide a proportionate and deliverable approach to risk management, ahead of vesting day.

Recommendations

It is recommended that the East Surrey Shadow Executive resolves to:

1. Approve the recommended approach to risk management (Option 1) for East Surrey Council, having regard to any comments and observations from the Audit & Governance Committee; and

2. Endorse the proposal that legacy councils continue to operate according to their current risk management policies and frameworks, below corporate risk

OFFICIAL OFFICIAL

level, pending the development and approval of a comprehensive and harmonised risk management framework post-vesting day.

Reason for recommendations

The recommended approach would provide a proportionate and deliverable approach to risk management and would ensure that ESC operates on a safe and legal basis from vesting day.

It recognises the practical constraints of Local Government Reorganisation and focuses on establishing the minimum viable arrangements required for transition to the new authority. Implementation of a mature and harmonised risk management framework would be developed post vesting day in alignment with emerging organisational arrangements and structures. A phased approach provides ESC with the ability to establish robust oversight and accountability arrangements from Vesting Day while allowing the development of a harmonised framework and associated arrangements to evolve alongside service integration and organisational maturity.

The approach supports the statutory Best Value standards and strengthens organisational accountability. It establishes the foundations for future risk management arrangements that provide officers and elected Members with clear mechanisms for managing risk as the Council begins its delivery of the Council's strategic priorities.

Options

Option 1 – Adoption of phased approach to Risk Management to be in place by vesting day, with development of a comprehensive Framework and associated harmonised arrangements post-vesting day. Recommended.

This option has been developed based on the critical milestones set out in the Surrey Devolution and Local Government Reorganisation (D&LGR) Implementation Plan, endorsed by the Chief Executive and the Interim Statutory Officers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
High level of summary of key existing risks from current councils’ corporate risk registers /EAppendix A 559 KB Download
PDF
List of existing corporate risks from current councils /EAppendix B 259 KB Download
PDF
Draft Corporate Risk Register template and worked example /EAppendix C 18 KB Download
PDF
Draft corporate risk assurance evidence template and worked example /EAppendix D 305 KB Download
PDF
Draft corporate risk assessment matrix and scoring guidelines /EAppendix E 245 KB Download
PDF
Draft Day 1 escalation process for consideration of risks at corporate risk levelAppendix F 200 KB Download
PDF
Risk Management Approach for East Surrey CouncilReport 357 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
ES
East Surrey Councillor Steve WottonLeader, expected
ES
East Surrey Councillor Kirsty HewensDeputy Leader, expected
ES
East Surrey Councillor Andy BurtonCommittee Member, expected
ES
East Surrey Councillor David BuxtonCommittee Member, expected
ES
East Surrey Councillor Julian FreemanCommittee Member, expected
ES
East Surrey Councillor Abhiram MageshCommittee Member, expected
ES
East Surrey Councillor Claire MalcomsonCommittee Member, expected
ES
East Surrey Councillor Andrew MatthewsCommittee Member, expected
ES
East Surrey Councillor Bradley NelsonCommittee Member, expected
ES
East Surrey Councillor Ashley TillingCommittee Member, expected

On this subject at Elmbridge

Search all
  1. Risk Management Approach for East Surrey CouncilThis decision
  2. Tree Risk Management StrategyDecided
  3. Risk Management Strategy & Strategic Risk Register and the RMP report on Community Support ServicesDecided
  4. Surrey Local Flood Risk Management Strategy 2017-2032Decided

More from Elmbridge East Surrey Shadow Authority Executive

All decisions
MeetingDecisionOutcome
19 Nov 2026 Consenting to the Formation of a Foundation Strategic Authority for SurreyView the decision text for item 3. Decided Open
19 Nov 2026 Appointment of Electoral Appointee for East SurreyView the decision text for item 4. Decided Open
9 Nov 2026 Implementation Programme UpdateView the decision text for item 77/E Decided Open
9 Nov 2026 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 78/E Decided Open
9 Nov 2026 Strategic PartnershipsView the decision text for item 79/E Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies