CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Elmbridge Borough Council
East Surrey Shadow Authority Executive, Monday 9 November 2026 at 10.00am

Implementation Programme Update

Decided Executive 3 papers

AI summaryThe East Surrey Shadow Authority Executive noted critical milestone progress, rising risk and the Implementation Fund position. [D] [P4] [P5] [P6] Committed funding is £35.658 million, with continued milestone, risk and financial oversight. [P44] [P80] [P81] [P82]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided68 of 201 critical milestones completed; delivery remained red. [P22] [P33]
Money£35.658 million committed [P44]Further £3.100 million approved; just under £2m uncommitted. [P44]
What happens nextFurther programme updates [P83]Milestones, oversight, risks and funding continue. [P80] [P81] [P82] [P83]
Who it affectsNew councils’ service continuity [P24] [P73]Recruitment and capacity risks may affect organisational readiness. [P73]

What was decided

The Executive noted continued progress against critical milestones. Report P4, P22

It noted the increasing programme risk profile and the highest scoring risks. Report P5, P42

It noted the latest Implementation Fund position. Report P6, P44

Why

Under the Constitution, the Shadow Executive oversees transition, maintains the Implementation Plan and takes key executive decisions needed to establish the new council. Agreeing the recommendations supports these duties. Report P7, P11

The Surrey (Structural Changes) Order 2026 requires the Implementation Plan to be kept under review. Declining the recommendations could hinder the Executive's functions and lead to inconsistent reporting and reduced public confidence. Report P14, P69, P71

Progress continues, but programme pace and complexity, the SEND inspection assessment and Tier 2 and statutory officer appointment challenges are affecting risk and require close management. Report P15, P17, P35

What happens next

Continue assessing the potential impact of the Surrey Local Area SEND inspection while awaiting its report. Report P34, P79

Continue delivery against critical milestones. Report P80

Continue monitoring through the Vesting Day Readiness Board, actively manage risks and financial pressures, and provide further updates to Shadow Executive meetings. Report P81, P82, P83

The money

  • £35.658 million Total committed programme funding Report P44
  • £3.100 million Further Implementation Fund approved since the previous meeting Report P44
  • just under £2m Implementation Fund remaining uncommitted Report P44
  • £6.950 million Spent in 2026/27 at the end of September Report P48
  • £2.2m Severance costs profiled for March 2027 Report P50, P53
  • £0.900m MHCLG grant provided to East Surrey Council Report P56
  • £0.194m Uncommitted within the East Surrey Council grant Report P62
  • £0.293 million Available after forecast variances within the grant budget Report P62

Options considered

  • Chosen: Note progress, risks and the Implementation Fund. This supports the Executive's programme monitoring and assurance functions. Report P7, P11, P12
  • Rejected: Do not accept the recommendations. This could hinder the Executive's functions and risk inconsistent reporting and reduced public confidence. Report P14

Implications

  • Financial: Spend is expected to accelerate, with £2.2m of severance costs profiled for March 2027. The funding envelope remains within the approved limit, with sufficient headroom expected for critical requirements. Report P50, P54
  • Financial: East Surrey Council faces significant budget pressure from rising demand, costs and reduced government funding. The new council is expected to rely more on Council Tax, and spending must remain within available resources. Report P64, P65
  • Legal: Article 23 of the Surrey (Structural Changes) Order 2026 requires the Shadow Authority for East Surrey to review and revise the Implementation Plan as necessary. Report P69, P71
  • Equalities: There are no direct equality implications from the recommendations. Equality Impact Assessments will be undertaken for future decisions that require them. Report P75
  • Climate: There are no direct climate change and sustainability implications from the recommendations. Report P77
  • Risk: The Children’s Theme and overall programme remain red. The highest scoring risks are system readiness, programme capacity, Executive decision making capacity and statutory officer appointment delays, each scoring 20. Report P17, P33, P42
  • Staffing: There are no direct staffing implications from the recommendations. Recruitment and capacity risks could affect organisational readiness and service continuity. Report P73
  • Other: The SEND inspection’s short term impact is manageable, but longer term uncertainty remains until the report is received and assessed. Report P34

Who and where

  • New councils’ service continuity Report P24, P73
  • Children’s and Adults’ services Report P35, P41
  • The Implementation Team and predecessor councils Report P38, P73
  • East and West Surrey Shadow Authorities Report P2, P22
  • Senior leadership and statutory officer roles Report P41, P73

Timeline

  • 9 June 2026: The programme monitoring and assurance approach was agreed. Report P1
  • 21 September: The Surrey Local Area Partnership SEND inspection began. Report P17
  • end of September: £6.950 million had been spent in 2026/27. Report P48
  • Friday 9 October 2026: The Surrey Local Area Partnership SEND inspection ended. Report P17
  • 22 October: Shadow Executive Members discussed progress and programme developments. Report P39
  • 31 December 2026: Tier 2 and statutory officer roles are required to be in place. Report P35
  • March 2027: Severance costs are profiled. Report P50, P53
  • future Shadow Executive meetings: Further programme updates will be provided. Report P83

Plain English for the jargon

  • LGR: Local Government Reorganisation. [P1]
  • SCO: Surrey (Structural Changes) Order 2026. [P14]
  • SEND: Special Educational Needs and Disabilities. [P17]
  • PMO: Programme Management Office. [P22]
  • IPB: Implementation Programme Board. [P24]
  • CQC: Care Quality Commission. [P17]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item77/E

Resolved

View the decision text for item 77/E
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to East Surrey Shadow Authority Executive

Purpose of the report

The East Surrey Shadow Authority Executive agreed an approach to Local Government Reorganisation (LGR) programme monitoring and assurance on 9 June 2026. This report sets out the latest position in line with that approach. Also included are the updates on programme risks against critical milestones, top programme risks and the latest position related to the implementation fund.

The Shadow Executive is, jointly with the West Shadow Executive, responsible for keeping under review, and revising as necessary, the Implementation Plan for local government reorganisation in Surrey1 and managing the overall Transition Programme. Recommendations are made to the Shadow Executive for arrangements to support these functions.

Recommendations

It is recommended that the East Surrey Shadow Executive resolves to:

1. Note continued progress against critical milestones;

2. Note the increasing programme risk profile and highest scoring risks; and

3. Note the latest Implementation Fund position.

Reason for recommendations

1. Under the Shadow Authority’s Constitution, the Shadow Executive is responsible for overseeing and managing the transition programme, including maintaining the Implementation Plan and taking the key executive decisions needed to

1 Future Surrey - Implementation Plan -

https://www.surreylgrhub.gov.uk/downloads/file/18/implementation-plan-05-26

OFFICIAL OFFICIAL

establish the new council. Agreeing the recommendations in this report will support the Shadow Executive to discharge these functions.

2. The Shadow Executive will receive regular programme updates providing assurance on overall delivery and highlighting areas requiring direction or decision.

Options, including alternatives (if any)

3. The Surrey (Structural Changes) Order 2026 (SCO) requires the Shadow Authority to keep the Implementation Plan under review and, as set out above, the Constitution confirms the role the Shadow Executive has in this. Whilst the Shadow Executive could choose not to accept the recommendations this could hinder their ability to discharge these functions and risks inconsistency in reporting and reduced public confidence in the transition process.

4. Overall, the programme continues to make progress against key milestones set out in the Implementation Plan. However, the pace and complexity of the programme, together with ongoing assessment of impacts related to the Surrey Local Area Partnership SEND inspection, and challenges with appointments to Tier 2 and statutory roles are impacting the risk profile and will require close management over the coming weeks and months.

Summary

Progress and Programme Assurance

5. The Children’s Theme and overall programme both remain rated red. Between 21 September and Friday 9 October 2026 Ofsted and the Care Quality Commission (CQC) carried out a Special Educational Needs and Disabilities (SEND) Local Area Partnership Inspection in Surrey. The inspection impacted staff capacity to deliver LGR programme activity across multiple themes, including IT&D activity, Day One readiness preparations and workforce disaggregation. This programme- level issue remains under active management and Executive Members have been kept updated through established governance arrangements. Further information about the overall assurance position is provided in paragraph 16.

6. Although the programme is still rated red, progress continues at pace and further milestones have been achieved, however significant risks remain related to programme delivery, and delivery confidence will be dependent on the ongoing management and mitigation of these risks.

OFFICIAL OFFICIAL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Programme Progress & Assurance Update /EAppendix 1 2.1 MB Download
PDF
Risk Update /EAppendix 2 409 KB Download
PDF
Implementation Programme UpdateReport 915 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
ES
East Surrey Councillor Steve WottonLeader, expected
ES
East Surrey Councillor Kirsty HewensDeputy Leader, expected
ES
East Surrey Councillor Andy BurtonCommittee Member, expected
ES
East Surrey Councillor David BuxtonCommittee Member, expected
ES
East Surrey Councillor Julian FreemanCommittee Member, expected
ES
East Surrey Councillor Abhiram MageshCommittee Member, expected
ES
East Surrey Councillor Claire MalcomsonCommittee Member, expected
ES
East Surrey Councillor Andrew MatthewsCommittee Member, expected
ES
East Surrey Councillor Bradley NelsonCommittee Member, expected
ES
East Surrey Councillor Ashley TillingCommittee Member, expected

On this subject at Elmbridge

Search all
  1. Implementation Programme UpdateThis decision
  2. Implementation Programme UpdateDecided
  3. Implementation Programme UpdateDecided
  4. Implementation Programme Assurance UpdateDecided

More from Elmbridge East Surrey Shadow Authority Executive

All decisions
MeetingDecisionOutcome
19 Nov 2026 Consenting to the Formation of a Foundation Strategic Authority for SurreyView the decision text for item 3. Decided Open
19 Nov 2026 Appointment of Electoral Appointee for East SurreyView the decision text for item 4. Decided Open
9 Nov 2026 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 78/E Decided Open
9 Nov 2026 Strategic PartnershipsView the decision text for item 79/E Decided Open
9 Nov 2026 Equality Diversity and Inclusion ApproachView the decision text for item 80/E Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies