Resolved
View the decision text for item 77/E
AI summaryThe East Surrey Shadow Authority Executive noted critical milestone progress, rising risk and the Implementation Fund position. [D] [P4] [P5] [P6] Committed funding is £35.658 million, with continued milestone, risk and financial oversight. [P44] [P80] [P81] [P82]
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 77/E
The East Surrey Shadow Authority Executive agreed an approach to Local Government Reorganisation (LGR) programme monitoring and assurance on 9 June 2026. This report sets out the latest position in line with that approach. Also included are the updates on programme risks against critical milestones, top programme risks and the latest position related to the implementation fund.
The Shadow Executive is, jointly with the West Shadow Executive, responsible for keeping under review, and revising as necessary, the Implementation Plan for local government reorganisation in Surrey1 and managing the overall Transition Programme. Recommendations are made to the Shadow Executive for arrangements to support these functions.
It is recommended that the East Surrey Shadow Executive resolves to:
1. Note continued progress against critical milestones;
2. Note the increasing programme risk profile and highest scoring risks; and
3. Note the latest Implementation Fund position.
1. Under the Shadow Authority’s Constitution, the Shadow Executive is responsible for overseeing and managing the transition programme, including maintaining the Implementation Plan and taking the key executive decisions needed to
1 Future Surrey - Implementation Plan -
https://www.surreylgrhub.gov.uk/downloads/file/18/implementation-plan-05-26
OFFICIAL OFFICIAL
establish the new council. Agreeing the recommendations in this report will support the Shadow Executive to discharge these functions.
2. The Shadow Executive will receive regular programme updates providing assurance on overall delivery and highlighting areas requiring direction or decision.
Options, including alternatives (if any)
3. The Surrey (Structural Changes) Order 2026 (SCO) requires the Shadow Authority to keep the Implementation Plan under review and, as set out above, the Constitution confirms the role the Shadow Executive has in this. Whilst the Shadow Executive could choose not to accept the recommendations this could hinder their ability to discharge these functions and risks inconsistency in reporting and reduced public confidence in the transition process.
4. Overall, the programme continues to make progress against key milestones set out in the Implementation Plan. However, the pace and complexity of the programme, together with ongoing assessment of impacts related to the Surrey Local Area Partnership SEND inspection, and challenges with appointments to Tier 2 and statutory roles are impacting the risk profile and will require close management over the coming weeks and months.
Progress and Programme Assurance
5. The Children’s Theme and overall programme both remain rated red. Between 21 September and Friday 9 October 2026 Ofsted and the Care Quality Commission (CQC) carried out a Special Educational Needs and Disabilities (SEND) Local Area Partnership Inspection in Surrey. The inspection impacted staff capacity to deliver LGR programme activity across multiple themes, including IT&D activity, Day One readiness preparations and workforce disaggregation. This programme- level issue remains under active management and Executive Members have been kept updated through established governance arrangements. Further information about the overall assurance position is provided in paragraph 16.
6. Although the programme is still rated red, progress continues at pace and further milestones have been achieved, however significant risks remain related to programme delivery, and delivery confidence will be dependent on the ongoing management and mitigation of these risks.
OFFICIAL OFFICIAL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Programme Progress & Assurance Update /EAppendix 1 | 2.1 MB | Download |
PDF |
Risk Update /EAppendix 2 | 409 KB | Download |
PDF |
Implementation Programme UpdateReport | 915 KB | DownloadRead as text |
Follow East Surrey Shadow Authority Executive at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Nov 2026 | Consenting to the Formation of a Foundation Strategic Authority for SurreyView the decision text for item 3. | Decided | Open |
| 19 Nov 2026 | Appointment of Electoral Appointee for East SurreyView the decision text for item 4. | Decided | Open |
| 9 Nov 2026 | 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 78/E | Decided | Open |
| 9 Nov 2026 | Strategic PartnershipsView the decision text for item 79/E | Decided | Open |
| 9 Nov 2026 | Equality Diversity and Inclusion ApproachView the decision text for item 80/E | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.