The Committee: (1) Noted progress on the 2018/19 planned maintenance programme; (2) Authorised changes to the programme set out in section 3 of the report, including £41,500 additional expenditure to be funded from the property maintenance reserve.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1At its meeting on 17 April 2018, the Strategy and Resources Committee approved the list of works in Annex 1. Strategy and Resources Committee 27 November 2018 2.2 These works totalled £280k, with £210k funded from the planned maintenance budget and £70k funded from property maintenance reserve.
3 Proposals
3.1Authorisation for additional works is now requested for the following items:
3.1.1 Horton Country Park - relay new water main as the existing water main to cluster of buildings is leaking at a cost of £300 a week. The proposed works have been tendered and will cost £26k.
3.1.2 The Town Hall has an internal lighting management system that is out of date and requires new software and repairs and alterations to ensure lights go off when required, this will save energy and update to current technologies. This is ongoing maintenance to an existing lighting system, to rectify defects where lighting is on continuously. The cost will be approximately £7k.
3.1.3 Following legionella risk assessments it is anticipated that removal of dead leg pipework and alterations to various buildings will be required. The cost will be approximately £20k.
3.1.4 The proposed change of control panel to the heating system at the Community and Wellbeing centre can be removed from this year’s programme. After investigations there may be a requirement for a larger project in the future.
3.2The combined estimated cost of these additional works is £53k, which can be partially funded by a projected underspend of £11.5k on the approved works programme, as detailed at Annex 2. It is proposed to fund the £41.5k balance from the property maintenance reserve.
3.3Committee is asked to note the progress on the 2018/19 planned maintenance programme set out in Annex 2.
3.4Committee is also asked to authorise the proposed changes to the programme, including £41,500 additional expenditure to be funded from the property maintenance reserve.
4 Financial and Manpower Implications
4.1The current projected balance of the property maintenance reserve at 31 March 2019 is £348,820.
4.2Approving the additional £41,500 expenditure for new works would reduce the projected balance to £307,320.
4.3Chief Finance Officer’s comments: Financial implications are set out in the body of the report. Strategy and Resources Committee 27 November 2018 5 Legal Implications (including implications for matters relating to equality)
5.1There are no legal arising from the contents of this report
5.2Monitoring Officer’s comments: There are no comments on the contents of this report.
6 Sustainability Policy and Community Safety Implications
6.1The scope of works within the planned maintenance programme for 2017/18 contribute to the achievement of council’s objectives for sustainability.
7 Partnerships
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.