Resolved
The Committee approved: (1) Additional budget of £30,350 to enable the scheme to proceed; (2) The use of £30,350 of S106 monies to fund the additional budget.
Strategy and Resources Committee approved this item on Tuesday 27 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee approved: (1) Additional budget of £30,350 to enable the scheme to proceed; (2) The use of £30,350 of S106 monies to fund the additional budget.
2.1The Poole Road Pavilion is 20 years old and the heating & hot water plant is past the end of its life.
2.2The budget of £50,000 was allocated within the Capital programme to replace the plant in the boiler room.
2.3The works are specialist mechanical and electrical works of which a specialist consultant was appointed to produce specification and drawings.
2.4The consultant fee tendered at a cost of £9,000 to produce documents drawings, carry out tender analysis and manage the project. Strategy and Resources Committee 27 November 2018 2.5 The works consists of replacement of boilers, pumps, expansion vessels, electronic fill devise, control panel, labelling and drawings
2.6The project was tendered in August 2018 to five contractors. Only 4 parties submitted a tender and there was a wide price range across the tenders; the lowest tender was £66,350.
2.7There has been no contingency allowance within the specification, this is common place for Mechanical and Electrical consultants preparation of documents.
2.8After careful analysis and discussion with our consultant, a range of options have been identified to reduce the costs of the scheme to meet the budgeted costs figure.
2.9These options include omitting thermal insulation, removal of a control panel, removal of a modern magnetic water conditioner, omitting performance testing of plant, remove new modern inverter pumps and 6 months commissioning audit.
2.10It is felt that the risk from reducing the scope of works to this extent and removing all energy efficiency measures, would undermine the current scheme. There would be no guarantee that these items would not continue to fail on a regular basis, increasing the pressure of the maintenance budget and more requests occurring for additional funding
2.11Although reducing the scheme is an option, it is not recommended.
3 Proposals
3.1It is proposed to proceed with the lowest tender price for the full scope of works and to include a contingency sum of £5,000 for any unforeseen works.
3.2The revised estimated project cost is as follows:
Contract sum £66,350
Contingency sum £5,000
Consultants fee £9,000
Total cost £80,350
Approved budget £50,000
Budget shortfall £30,350
3.3Members are asked to approve additional funding of £30,350 from S106 funds to meet the budget shortfall. Strategy and Resources Committee 27 November 2018 4 Financial and Manpower Implications
4.1It is proposed that the budget shortfall of £30,350 be funded from S106 funding within the Outdoor Sports Facilities category. There is currently a balance of £172,300 of S106 funds within this category.
4.2Approving £30,350 for the Poole Road Pavilion scheme will reduce the balance of S106 Outdoor Sports Facilities funds to £141,950, therefore reducing the funds available for other projects in future.
4.3Seven S106 agreements have been identified that can be utilised to fund the £30,350 required.
4.4Chief Finance Officer’s comments: All financial implications are set out in the body of the report.
5 Legal Implications (including implications for matters relating to equality)
5.1Legal implications have been incorporated within the body of the report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Poole road pavilion enhancements Capital ProjectReport | 92 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... | Noted | Open |
| 10 Nov 2026 | Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report | Noted | Open |
| 10 Nov 2026 | Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... | Agreed | Open |
| 10 Nov 2026 | Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... | Agreed | Open |
| 10 Nov 2026 | Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.