Following consideration, it was resolved that the Committee: (1) Agreed to the allocation of £50,000 to support the development of a pipeline of future investment opportunities for Epsom and Ewell to be financed from the Council’s corporate projects reserve; (2) Agreed that development proposals arising from this work be brought back to Strategy & Resources Committee for consideration.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
1.1There is expected to be future funding available to support the recovery of the economy in the aftermath of COVID-19, particularly for capital investment schemes that can be progressed in a reasonable timeframe. Strategy and Resources Committee 27 October 2020 1.2 To ensure that the Council and the borough is well placed to access these future inward investment opportunities, it is important that the Council begins work on developing a pipeline of future investment opportunities, by undertaking some initial project feasibility and prospectus work.
Background
2.1Capital and construction related projects usually have a significant lead in time, and depending on their size and complexity this can stretch into several years. This can be a cause of frustration, as when priorities shift and/or new external funding opportunities become available, project ideas are seldom far enough advanced to be capable of being implemented in the timescales required.
2.2A well developed project pipeline provides a menu of choices for investment, with a range of ideas and schemes at different stages of development. The project pipeline can be adjusted over time to take into account shifting priorities, staff capacity and the availability of financial resources. These financial resources may be Council funding - including CIL funding, Government funding, Local Enterprise Partnership funding, Surrey County Council funding, or developer funding. Sometimes it is possible to piggy back a project on to a wider scheme which then also picks up the cost. For example a public realm landscaping idea for an area, being funded by a developer as part of them bringing forward their adjacent development.
2.3There is greater value in having a large and diverse project pipeline, as when third-party funds do become available, they can be specific about the type and size of project, and the timescales in which they have to be delivered.
2.4Stages in a project pipeline
2.4.1 While the stages of a project can vary considerably depending on its size and nature, in general terms projects pass through the following stages. As bringing forward a project is an iterative process, there is an opportunity at every stage to decide whether to stop, pause or proceed to the next stage.
2.4.2 Concept preparation
Generation of initial ideas, scoping and concepts. Taking soundings eg regarding alignment with local priorities and the priorities of external funding agencies. Development of potential options for delivery. Preparation of initial concept designs, outline master planning and prospectus preparations. Strategy and Resources Committee 27 October 2020 2.4.3 Initial feasibility
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.