Following consideration, it was resolved that the Committee: (1) Noted the provisions in the Electronic Communications Code (with effect from December 2017) with its significant changes favouring the presumption of approval for telecommunications masts and limiting the grounds for objection by land owners and occupiers of land. (2) Agreed the siting of a telecommunication mast on Council owned land at Wells Road, Epsom; and (3) Agreed to permit the instruction of an independent surveyor to act on behalf of EEBC to negotiate and agree Heads of Terms with the cost to be met by the operator; and (4) Agreed to enter a lease for a term of 10 years, with authority to agree terms and conditions delegated to the Chief Legal Officer.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
A request for siting of telecommunication equipment has been received on Council owned land at Wells Road. Permission for its siting is sought and agreement to a ten year lease on terms to be negotiated.
Recommendation (s) The Committee is asked to:
(1) Note the provisions in the Electronic Communications Code (with effect from December 2017) with its significant changes favouring the presumption of approval for telecommunications masts and limiting the grounds for objection by land owners and occupiers of land.
(2) To agree the siting of a telecommunication mast on Council owned land at Wells Road, Epsom; and
(3) To permit the instruction of an independent surveyor to act on behalf of EEBC to negotiate and agree Heads of Terms with the cost to be met by the operator; and
(4) To enter a lease for a term of 10 years, with authority to agree terms and conditions delegated to the Chief Legal Officer. Strategy and Resources Committee 27 October 2020 1 Reason for Recommendation
1.1The new Electronic Communications Code (the Code), which came into force in December 2017, constituted a significant change to the law in this area. It is widely interpreted as having been a positive change for telecommunications network operators and a negative one for owners and occupiers of land.
1.2By way of context, a letter from central government (specifically Department for Digital, Culture, Media & Sport and Ministry of Housing, Communities & Local Government) to Council Chief Executives dated 7 March 2019 stated as follows:
“We need to create the market and policy conditions necessary to support the large-scale commercial investment required to extend and future-proof digital connectivity. A key part of this is making it easier for operators to deploy infrastructure. To help to achieve this, the Government recently reformed the Electronic Communications Code - the statutory framework which underpins agreements between communications network providers and those in both the private and public sector who can provide sites for the installation of network equipment. The purpose of the reforms was to make it easier and more cost effective for communications network providers to deploy and maintain digital infrastructure.
Local authorities have an essential role to play as site providers.”
and
“We would, therefore, ask you: … to ensure your teams are granting access to your assets and infrastructure effectively to support the rollout of full fibre and mobile networks.”
1.3Any occupier of land will need to carefully consider any approach from an operator, rather than either dismissing the approach out of hand, or agreeing to everything that is asked of it without any scrutiny. It is worth considering what tests the Code imposes in the event that a dispute arises which has to be determined by the Upper Tribunal.
1.4The Code is drafted so as to make it very difficult for an occupier of land to resist having an agreement imposed on it by the Upper Tribunal, in the event that it does not agree voluntarily to enter into an agreement for the siting of Electronic Communications Apparatus.
1.5In a case where the land occupier is not intending to redevelop the relevant land, the “operator” (i.e. the telecoms network provider) has to satisfy paras 21(2) and (3) of the Code. Strategy and Resources Committee 27 October 2020 1.6 The test at para 21(2) is as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.