Following consideration, the Committee resolved unanimously: (1) To agree to an independent Planning Officers Society review of the Development Management Service; (2) To agree to procure consultancy support to clear the backlog of planning applications; (3) To agree to retain existing senior agency staff pending permanent recruitment to roles; (4) To agree to appoint an enforcement trainer to work with and train planning officers in planning enforcement; (5) To approve the allocation of up to £190,000 to the Development Management Service budget to enable the additional resource and for the review to be undertaken; (6) A Member Task and Finish Group to oversee the review and progress against implementation of an action plan.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
The report seeks approval for additional resources to enable the Planning Development Management Service to procure consultancy support to clear the current backlog in planning and related applications. In addition, to employ an officer to train staff in compliance and to undertake an independent review of the service by the Planning Officer’s Society.
Recommendation (s) The Committee is asked to:
(1) To agree to an independent Planning Officers Society review of the Development Management Service.
(2) To agree to procure consultancy support to clear the backlog of planning applications
(3) To agree to retain existing senior agency staff pending permanent recruitment to roles
(4) To agree to appoint an enforcement trainer to work with and train planning officers in planning enforcement
(5) To approve the allocation of up to £190,000 to the Development Management Service budget to enable the additional resource and for the review to be undertaken.
(6) Member Task and Finish Group to oversee the review and progress against implementation of an action plan. Strategy and Resources Committee 27 July 2021
Reason for recommendation
1.1With significant increases in workload (25% increase in applications and 20% increase in enforcement complaints) in recent months combined with resourcing a number of major appeals, demand for the development management service has exceeded beyond capacity.
1.2To reduce the current backlog and ensure the council provides the service that our residents expect, this report seeks approval for additional resources of up to £190,000 to assist with clearing the current backlog and providing specialist enforcement training.
1.3The report also seeks approval for an independent review and training to enable the planning service to adapt processes and allocate its resources as efficiently as possible to meet workload challenges going forward.
1.4The proposal is to undertake a review of planning processes after the backlog is cleared in order to ensure that the service is as efficient as possible and that it allocates its resources effectively.
Background
2.1The development management service for the borough deals with all applications for planning permission, advertisement consent, listed building and conservation area consent, the felling of trees protected by tree preservation orders and prior notifications for telecommunication masts, and changes of use under the permitted development regime as well as the enforcement of breaches of planning control.
2.2It is a statutory function operating under primary and secondary legislation and guided by government guidance, case law and the locally adopted statutory Development Plan.
2.3It is one of the key public-facing services provided by the Borough Council.
3. Capacity issues
3.1There have been capacity issues in the service over recent months due to a significant increase in workload (25% increase in applications and a 20% increase in enforcement complaints). In addition, there have been a number of officer recommendations overturned at planning committee, which has resulted in planning appeals with the associated resource requirements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.