Following consideration, the Committee resolved unanimously to: (1) Receive the report on provisional financial outturn for 2020/21; (2) Note the carry forward £2.471m budget for capital schemes to be added to the 2021/22 capital programme. (3) Note that the external audit of the 2020/21 Statement of Accounts is underway and is expected to complete in the Autumn . Should any material changes to outturn arise from the audit, these will be reported to this Committee in Autumn .
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report summarises the Council’s provisional financial performance for 2020/21 and details the capital budgets to be carried forward for schemes where costs will be incurred in 2021/22.
Recommendation (s) The Committee is asked to:
(1) Receive the report on provisional financial outturn for 2020/21;
(2) Note the carry forward £2.471m budget for capital schemes to be added to the 2021/22 capital programme.
(3) Note that the external audit of the 2020/21 Statement of Accounts is underway and is expected to complete in the Autumn. Should any material changes to outturn arise from the audit, these will be reported to this Committee in Autumn.
Reason for recommendation
1.1The Council’s Financial Regulations require that the financial outturn performance and capital programme be reported to Strategy & Resources Committee.
2 Background Strategy and Resources Committee 27 July 2021 2.1 The Council’s financial performance is reported to members quarterly through the budget monitoring process, and at year-end through this report. Provisional outturn has already been circulated via Members’ Update on 18 June 2021, this report formally presents the position to Strategy & Resources Committee.
2.2The external audit of the Council’s accounts is progressing and is expected to be completed and reported to this Committee by the statutory deadline of 30 November 2021.
2.3There have been no changes to the provisional revenue outturn position reported on 18 June 2021 arising from the external audit thus far.
2.4However, there has been one significant change to the reported balance on the Business Rates Equalisation Reserve, which has increased by £6.7m from £2.6m to £9.3m. The increase is principally because a net £6.6m in grants – awarded by MHCLG to compensate the Council for a £6.6m deficit on the business rates collection fund – have been set-aside in the business rates equalisation reserve to fund the £6.6m collection fund deficit by 2022/23, in accordance with collection fund regulations. The deficit on the collection fund is principally due to mandatory business rates reliefs awarded to eligible businesses during 2020/21, as instructed by central government. The change was identified during completion of collection fund accounting returns to MHCLG, and prior to the external audit starting.
2.5The provisional outturn figures in this report are not expected to change, however, should there be any amendments following completion of the external audit, these will be reported back to S&R Committee.
General Fund Summary Position
2.6In summary the outturn position for 2020/21 is:- Current Original Table 1 - General Fund Approved Actual Variance Budget Summary Budget* £’000 £’000 £’000 £’000 Strategy and Resources 3,819 2,916 -494 -3,410 Environment & Safe 2,154 2,320 4,925 2,605 Communities Community & Wellbeing 6,439 6,754 7,602 848 Capital charges -2,669 -2,247 -2,247 0 Total Net Expenditure 9,743 9,743 9,787 43 Funded by: Collection fund precept 6,713 6,713 6,713 0 Revenue Support Grant 0 0 0 0 Share of Business Rates 1,617 1,617 1,617 0 Strategy and Resources Committee 27 July 2021 Transfer from Collection 1,413 1,413 1,413 0 Fund Total Funding (Budget 9,743 9,743 9,743 0 Requirement) Deficit for the year 0 0 43 43
* includes changes to employee and support services allocations, capital charges and IAS 19 pension adjustments from the original budget and reflects required changes in accounting practice.
2.7Net expenditure for the year is just £43,000 over the original budget, however, the outturn position includes £5.56m of government financial support, which is detailed within the following table:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.