Strategy and Resources Committee agreed this item on Thursday 21 September 2023. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee unanimously resolved to: (1) Agree the , and the associated plan to invest in a programme of works as set out in the IT Roadmap. (2) To note that the works to include; a refresh of end user devices for officers, a programme of works to update infrastructure and move to a hosted data centre and transformational projects to improve and increase online services to residents. (3) Approve the indicative funding implications for delivering the defined IT Roadmap in 2023-2027, as set out in section 5 of the report, which will feed into the Medium-Term Financial Strategy to be approved at Full Council in February 2024. (4) Agree that a further report on the IT Roadmap will be submitted to committee in September 2024. This will provide an update on the implementation of the roadmap and details of funding actuals to date and forecast.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report provides details of the Epsom & Ewell Borough Council Information Technology Strategy for 2023 and beyond. The IT Strategy defines the principles, governance, standards and methodology by which the council will source, procure, implement, maintain and deliver IT services both internally (to staff and partners) and externally (to residents). This report details also the accompanying IT Roadmap for 2023-2027.
Delivery of the IT Roadmap will provide residents with an enhanced user experience of the Council’s website. Officers and members will benefit from up-to-date systems and improved ways of working which facilitate collaboration and support hybrid working.
To support the developing Town Hall/70 East Street reviews, the roadmap defines the path to move the council to a state where it requires only minimal on-premise IT infrastructure, with services delivered from hosted data centres and the Cloud.
The IT Strategy and IT Roadmap will be subject to annual review to ensure they continue to align with the council’s business requirements, reflect changing technology opportunities and threats and detail the technical solutions required to meet them.
Recommendation (s) The Committee is asked to:
(1) Agree the IT Strategy, and the associated plan to invest in a programme of works as set out in the IT Roadmap.
(2) To note that the works to include; a refresh of end user devices for officers, a programme of works to update infrastructure and move to a hosted data centre and transformational projects to improve and increase online services to residents. Strategy and Resources Committee 21 September 2023
(3) Approve the indicative funding implications for delivering the defined IT Roadmap in 2023-2027, as set out in section 5 of this report, which will feed into the Medium-Term Financial Strategy to be approved at Full Council in February 2024.
(4) Agree that a further report on the IT Roadmap will be submitted to committee in September 2024. This will provide an update on the implementation of the roadmap and details of funding actuals to date and forecast.
Reason for recommendation
1.1Strategy and Resources Committee approved the draft IT Strategy and current ICT Programme of Works capital funding for 2023-2024 on 28th March 2023. Subsequently, there has been significant work to add detail to the IT Roadmap required to deliver the strategy.
1.2The IT Strategy and accompanying IT Roadmap are the first steps in defining the path from our current “as is” to our proposed “future state”.
1.3Key aspects of the IT Strategy include deployment of corporate laptops, the discontinuation of Citrix and increased use of hosted and Cloud services. The latter will result in a significant shift from capital funding to revenue.
1.4Whilst the core projects within the IT Roadmap are broadly defined, they require further work before exact costs will be known. Further work will be required also to review and agree future treatment plans for many of the minor (sub £5,000/year) department applications.
1.5The IT Roadmap supports the mitigation and remediation actions defined in the IT risk register, in particular the removal of legacy applications and infrastructure. It supports also the Town Hall/70 East Street reviews and the council’s carbon reduction target.
Background
2.1In March 2023 a draft IT strategy and roadmap prepared by the then new Head of Information Technology was agreed by Strategy & Resources Committee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.