Strategy and Resources Committee approved this item on Thursday 21 September 2023. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee unanimously resolved to: (1) Approve additional funding of £105,000 from the Capital Receipts Reserve, to enable the Poole Road Pavilion Re-Roofing project to proceed at an estimated cost of £255,000. (2) Request that internal audit look at this particular procurement to allay any Members’ concerns around it.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
Report requesting additional capital funding to carry out the replacement of the roof covering to the pavilion and provide additional insulation.
Recommendation (s) The Committee is asked to:
(1) Approve additional funding of £105,000 from the Capital Receipts Reserve, to enable the Poole Road Pavilion Re-Roofing project to proceed at an estimated cost of £255,000.
Reason for recommendation
1.1The Poole Road pavilion is used by the Harriers Athletic Club, the boxing club, a children’s play area and various private hirers.
1.2The works are essential in the prevention of future roof leaks. The building has had water ingress in various areas including the boiler room, the main hall, and the corridor area. If the leaks continue, we may have to close the building which will in turn prevent the hirers activities and could lead to potential claims in loss of income.
1.3The works will provide a quality vandal resistant roof covering for an expected 25 years and increase the thermal efficiency of the roof and reduce carbon footprint.
2 Background Strategy and Resources Committee 21 September 2023 2.1 The replacement roofing was approved in the Capital budget for 2023/24 at the manufacturer’s estimated cost of £150,000.
2.2The roofing project was tendered, and prices returned in April 2023, three suppliers returned prices with a close spread of costs as follows:
2.2.1 Supplier 1 - £211,388
2.2.2 Supplier 2 - £208,780
2.2.3 Supplier 3 – £203,217
2.3Officers believe the increased costs are a result of a low estimate given by the manufacturer, and a combination of increased material and labour costs, inflation, and management and legal fees.
2.4The existing aluminium roofing sheets are 25 years old and have come to the end of their life. We have experienced roof leaks over the boiler room and vandalism over the years where the roofing tiles have been bent and lifted to gain access or just to be purely vandalised. Works are required to strip and remove existing roof covering and replace with a product called, ‘Britmet granulated light weight roofing sheets’, including providing and installing additional thermal insulation.
2.5This product is a direct replacement of the original ‘decra’ roofing sheets which are heavy duty vandal resistant specifically designed for these types of roofs in exposed locations such as parks etc.
2.6We currently have problems with repairing the air handling system as the roofing is damaged around the roof cowls which is letting in water over the mechanical and electrical plant. This is preventing repair works to the system and parts of the building are not currently ventilated of achieving correct air change volumes.
2.7The recommendation is to award the contract to the lowest supplier at a cost of £203,000. A contingency sum of £20,000 will be added for unforeseen works. Legal costs provisional sum of £5,000 will be added and management costs of 12% will be required to deliver the works at £27,000.
2.8The total requested budget for the project has therefore increased by £105,000, from the original £150,000 to £255,000.
3 Risk Assessment
Legal or other duties
3.1Equality Impact Assessment Strategy and Resources Committee 21 September 2023 3.1.1 This will be addressed in the Risk Assessments and method statements to ensure the track is available to access by the disabled groups that frequently use it whilst works are underway.
3.2Crime & Disorder
3.2.1 The roofing works will secure a new fixed vandal resistant roof that will prevent future vandalism.
3.3Safeguarding
3.3.1 N/A
3.4Dependencies
3.4.1 N/A
3.5Other
3.5.1 N/A
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.