Executive, Monday 7 October 2013 at 6.00pm

Daedalus Investment Opportunity - Update

Agreed Executive 1 paper

Executive agreed this item on Monday 7 October 2013. Below is the council's own wording, with the papers it was decided on.

Item12(3)

Resolved

RESOLVED that the Executive agrees: (a) the revised funding arrangements for the project as set out in the report; (b) in the event that the Growing Places loan conditions cannot be satisfied within the project timescales, the Executive supports an alternative approach backed by prudential borrowing; and (c) the Executive includes the project in the Council’s capital programme at its next review.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 07 October 2013 Portfolio: Policy and Resources Subject: Daedalus Investment Opportunity - Update Report of: Director of Finance and Resources Strategy/Policy: Corporate To promote the economic success of the borough Objective:

Purpose: To update members on progress made in securing the funding for the Daedalus Investment Opportunity project.

Executive summary: In July 2013, the Executive supported a proposal to provide improvements to the airfield, provision of new hangar space and an Innovation Centre for small businesses, at the Solent Enterprise Zone, Daedalus.

Good progress has been made in the preliminary stages of preparing the project, but the main focus over the preceding months has been to establish the funding mechanisms for the project. Funding for the proposal has now been secured but with certain preconditions which must be satisfied. The conditions are such that there will be a need to refinance part of the project cost during the business plan 25- year life and as such, reduce the availability of resources available for future reinvestment.

The implications have been incorporated into the 25-year business plan and still demonstrate that a positive return can be achieved, either by accepting the loan offer from the Growing Places Fund, or alternatively using prudential borrowing from the outset to meet the balance of funding.

Recommendations: That: (a) the Executive agrees the revised funding arrangements for the project as set out in the report; (b) in the event that the Growing Places loan conditions cannot be satisfied within the project timescales, the Executive supports an alternative approach backed by prudential borrowing; and (c) the Executive includes the project in the Council’s capital programme at its next review. Reason: To enable the project to proceed in line with the proposed timescales.

Cost of proposals: The proposed budget for the project is £8.35m, funded from a capital grant payable to the Council, and a Growing Places Fund loan, fully serviced from net rents derived from the project.

Background papers: Deloittes Due Diligence report, August 2013. Executive Briefing Paper Date: 07 October 2013

Subject: Daedalus Investment Opportunity - Update

Briefing by: Director of Finance and Resources Job Title

Portfolio: Policy and Resources

INTRODUCTION

1. In July 2013, the Executive considered an opportunity to provide investment in infrastructure and facilities at the Solent Enterprise Zone, Daedalus. The proposal to provide improvements to the airfield, provision of new hangar space and an Innovation Centre for small businesses, together totalling £8.3m, was supported by the Executive, who gave authority to the Director of Finance and Resources to submit a funding application to the Solent Growing Places Fund and conclude negotiations with the other parties to facilitate the construction works.

2. Good progress has been made in the preliminary stages of preparing the project, but the main focus over the preceding months has been to establish the funding mechanisms for the project. This report provides an update of the progress made on the project, and invites the Executive to consider the most appropriate way forward.

FUNDING ARRANGEMENTS

3. The arrangements for funding the package of works comprised of two elements; a capital grant which would be supported by a loan obtained from the Solent Growing Places Fund.

4. Over the summer period, due diligence work was carried out to satisfy officers that the proposal was viable and that there was sufficient market demand to support the assumptions made in the 25-years business plan. This work was principally taken by Deloitte, and was used as the basis for the funding applications that were subsequently made.

5. The Council has now received written confirmation of the capital grant offer. The grant amounts to £5.3m, and is conditional upon:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Daedalus Investment Opportunity: UpdateReport 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 14 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor CartwrightCommittee Member, present
BB
Councillor Brian BayfordCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, apologies
LK
Councillor Leslie KeebleCommittee Member, present
LU
Leigh UsherCommittee Officer, in attendance
JB
Councillor John BryantGuest, in attendance
PB
Councillor Pamela BryantGuest, in attendance
PD
Councillor Peter DaviesGuest, in attendance
TH
Councillor Tiffany HarperGuest, in attendance
AM
Councillor Arthur MandryGuest, in attendance

All 14 on the meeting page

On this subject at Fareham

Search all
  1. Daedalus Investment Opportunity - UpdateThis decision
  2. Investment Programme for Solent Airport, DaedalusAgreed
  3. Investment Programme for Solent Airport, DaedalusNoted
  4. Covid 19 Impact on Daedalus Faraday Business Park Investment ProjectAgreed
  5. Daedalus Investment Project - Progress ReportDecided
  6. Daedalus Investment Project - Progress UpdateDecided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies