Resolved
RESOLVED that the Executive notes the progress made to date on the Daedalus Investment Project.
Executive decided this item on Monday 7 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Executive notes the progress made to date on the Daedalus Investment Project.
Report to the Executive for Decision 07 July 2014 Portfolio: Policy and Resources Subject: Daedalus Investment Project - Progress Report Report of: Director of Finance and Resources Strategy/Policy:
Corporate To promote the economic success of the Borough Objective:
Purpose: The purpose of this report is to update Members on progress with the Daedalus Investment project.
Executive summary: In July 2013, the Executive supported a proposal to develop an Innovation Centre for new start up businesses at the Solent Enterprise Zone, undertake improvements to the airfield and develop new hangar space. In October 2013, the Executive agreed revised funding arrangements for the project and in November 2013 agreed a governance and decision-making structure and the establishment of a Member Working Group to oversee the project.
The project contained some very challenging timescales, principally the requirement to complete the Innovation Centre by the end of March 2015. This aspect of the project is progressing extremely well. Planning consent was granted on 26 March 2014 and site preparation works commenced on 12 May. Construction work on the site commenced on 2 June and the completion date is programmed for early March 2015. A procurement process is currently under way with a view to appointing an operator for the centre during the summer of 2014.
The work to improve the runway is still planned to commence during September 2014 and be complete by the end of November 2014. This will minimise disruption to planned airfield activities during the summer months. The specification for the works is intended to enable the airfield operator to obtain a CAA licence which will enhance its commercial potential.
Work has been ongoing with the Homes and Communities Agency (HCA) to identify a suitable location on the airfield for the development of new hangar space. This is dependent on agreement of an overall strategy for the airfield between the HCA, FBC and other interested parties including Hampshire County Council (HCC), the Solent Local Enterprise Partnership (SLEP) and the airfield operator. As a result it is now likely that new hangar space will be delivered during the latter half of 2015. Recommendation: That the Executive notes the progress made to date on the Daedalus Investment Project.
Reason: To keep the Executive abreast of the progress on the Daedalus Investment project.
Cost of proposals: The cost of the proposals can be met within the resources previously agreed by the Executive for the project.
Background papers: Executive Briefing Paper Date: 07 July 2014
Subject: Daedalus Investment Project - Progress Report
Briefing by: Director of Finance and Resources
Portfolio: Policy and Resources
INTRODUCTION
1. The Daedalus Investment Project comprises three distinct but inter-related projects. A new Innovation Centre will provide office and workshop space for emerging small businesses and is being funded by a grant of £5.3m from the HCA. The other elements of the investment project are the provision of improvements to the airfield at an estimated cost of £1.5m and the provision of new hangar space, also costing an estimated £1.5m, both of which will be funded via borrowing by the Borough Council.
2. The following sections update Members on the progress of each individual element of the project.
INNOVATION CENTRE
3. Of the three elements, the Innovation Centre has the most challenging timescale as it is a condition of the funding agreement that it is completed by March 2015. Originally, businesses locating within an Enterprise Zone also needed to be in occupation by that date in order to qualify for Business Rate Relief for a period of 5 years. However, due to changes announced in the Budget in March 2014, this deadline has been extended until March 2018, thus increasing the attractiveness of the Centre.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Daedalus Investment Project: Progress UpdateReport | 106 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.