CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Fareham Borough Council
Executive, Monday 3 March 2014 at 6.00pm

Daedalus Investment Project - Progress Report

Decided Executive 1 paper

Executive decided this item on Monday 3 March 2014. Below is the council's own wording, with the papers it was decided on.

Item10(2)

Resolved

RESOLVED that the Executive notes the progress made to date on the Daedalus Investment Project.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 03 March 2014 Portfolio: Policy and Resources Subject: Daedalus Investment Project - Progress Report Report of: Director of Finance and Resources Strategy/Policy: Corporate To promote the economic success of the Borough Objective:

Purpose: The purpose of this report is to update Members on progress with the Daedalus Investment project.

Executive summary: In July 2013, the Executive supported a proposal to develop an Innovation Centre for new start up businesses at the Solent Enterprise Zone, undertake improvements to the airfield and develop new hangar space. In October 2013, the Executive agreed revised funding arrangements for the project and in November 2013 agreed a governance and decision making structure and the establishment of a Member Working Group to oversee the project.

The project contained some very challenging timescales, principally the requirement to complete the Innovation Centre by the end of March 2015. This aspect of the project is progressing extremely well. A final design has been agreed and a planning application has been submitted. It is proposed to make a start on site on 27 May 2014 with a view to completion during March 2015.

In order to minimise disruption to planned airfield activities during the summer months it is now proposed to commence the improvements to the runway during September 2014 and complete them by the end of November 2014. The specification for the works is intended to achieve a CAA licence for the airfield, enabling it to enhance its commercial potential.

Work has been ongoing with the Homes and Communities Agency (HCA) to identify a suitable location within Hangars West for the new hangar space. The exact nature of the design of the hangar and the procurement process is currently under discussion with a view to completing the project during the early summer of 2015. Recommendation: That the Executive notes the progress made to date on the Daedalus Investment Project

Reason: To keep the Executive abreast of the progress on the Daedalus Investment project.

Cost of proposals: The cost of the proposals can be met within the resources previously agreed by the Executive for the project.

Appendices: A: Images of the Proposed Innovation Centre Executive Briefing Paper Date: 03 March 2014

Subject: Daedalus Investment Project - Progress Report

Briefing by: Director of Finance and Resources

Portfolio: Policy and Resources

INTRODUCTION

1. The Daedalus Investment Project comprises three distinct but inter-related projects. A new Innovation Centre will provide office and workshop space for emerging small businesses and will be funded by a grant of £5.3m from the HCA. The other elements of the investment project are the provision of improvements to the airfield at an estimated cost of £1.5m and the provision of new hangar space, also costing an estimated £1.5m, both of which will be funded via borrowing by the Borough Council.

2. The following sections update Members on the progress of each individual element of the project.

INNOVATION CENTRE

3. Of the three elements, the Innovation Centre has the most challenging timescale as it is a condition of the funding agreement that it is completed by March 2015. In addition, for new businesses to qualify for Business Rate Relief within an Enterprise Zone, they need to be in occupation by that date.

4. Since the last report to the Executive, very good progress has been made. A Design and Build contractor, Leadbitter, was appointed at the beginning of December 2013. Leadbitter have taken the initial design concept forward very quickly and developed a more detailed design in less than two months. This design was signed off by the Members Working Group at its meeting on 28 January and a planning application was submitted on 31 January. The application is due to be considered on 26 March. This will enable a start on site by the end of May 2014, with completion due by the planned date of March 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Daedalus Investment Project: Progress ReportReport 380 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 15 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
BB
Councillor Brian BayfordCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
LK
Councillor Leslie KeebleCommittee Member, present
LU
Leigh UsherCommittee Officer, in attendance
RI
Richard IvoryLead Officer, in attendance
JB
Councillor John BryantGuest, in attendance
PB
Councillor Pamela BryantGuest, in attendance
PD
Councillor Peter DaviesGuest, in attendance
ME
Councillor Marian EllertonGuest, in attendance

All 15 on the meeting page

On this subject at Fareham

Search all
  1. Daedalus Investment Project - Progress ReportThis decision
  2. Investment Programme for Solent Airport, DaedalusAgreed
  3. Investment Programme for Solent Airport, DaedalusNoted
  4. Covid 19 Impact on Daedalus Faraday Business Park Investment ProjectAgreed
  5. Daedalus Investment Project - Progress ReportDecided
  6. Daedalus Investment Project - Progress UpdateDecided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies