CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Fareham Borough Council
Audit and Governance Committee, Monday 21 September 2015 at 6.00pm

Head of Audit's Annual Opinion

Noted Finance 1 paper

Audit and Governance Committee noted this item on Monday 21 September 2015. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that the Committee note the content of the report as a source of evidence for the 2014/15 Annual Governance Statement.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

This report sets out the Internal Audit coverage, findings and performance for 2014/15 and gives an overall assurance opinion on the adequacy and effectiveness of the Council’s framework of governance, risk management and control.

It also covers the results of the Quality Assurance and Improvement Plan for the internal audit service for the year.

Recommendation

That the contents of the report are noted as a source of evidence for the 2014/15 Annual Governance Statement. INTRODUCTION

1. This report covers the assurances that are available through the work of the Internal Audit service on the adequacy and effectiveness of the Council’s framework of governance, risk management and control.

2. It is one of the key documents which inform this year’s Annual Governance Statement.

ASSURANCES AVAILABLE TO SUPPORT THE OPINION

Completion of Planned Assignments

3. The audit plan for 2014/15 included 21 audit assignments of different types to give a good spread across the audit universe. This is fewer compared to previous years as we have changed our focus from 2014/15 to carry out fewer but longer audits which give a deeper understanding of weaknesses found before any actions are agreed with the Sponsor.

4. At the time of giving this annual opinion all 21 assignments had been undertaken and sufficient conclusions drawn to be useable as a source of assurance. 12 had been fully completed and actions agreed with the Audit Sponsor. Appendix A gives the latest status of the assignments and the key assurance measures arising from the work.

Spread of Individual Assignment Opinions

5. The majority of assignments result in an individual assurance opinion which reflects the level of internal control found within the system for those areas tested. The table below provides a summary of this information compared to previous years:

Table 1 - Spread of Assignment Assurance Opinions Given Year Strong Reasonable Limited Minimal Total 2014/15 6 (40%) 8 1 0 15 2013/14 13 (41%) 18 1 0 32 2012/13 8 (30%) 16 3 0 27 2011/12 13 (46%) 14 1 0 28

6. No opinions of ‘Minimal Assurance’ were issued in the year. There is 1 ‘Limited Assurance opinion’ likely to be awarded in the year for the Contract Completion audit. Issues were found in relation to the clarity of policy and levels of compliance covering the Contracts Payment Register, pricing variation orders and reporting overspends. These will be need to be addressed as part of the major rewrite of the Financial Regulation on Procurement which is planned following a Systems Thinking review of the process.

7. Work has been carried out in the last couple of years to address issues arising from the Data Protection audits. In particular a computer training package (Skillgate) is being developed for roll out to all employees. This is a significant action in terms of governance. 8. It should be noted that the major audit of a service (Benefits) in the year which had undergone a “Systems Thinking” intervention is likely to be given a Strong assurance opinion.

Income or Expenditure Errors found

9. The following two errors were identified in the year from the testing carried out in planned assignments:

 An invoice was incorrectly raised giving a customer a 50% discount (£400) on the annual beach hut fee when he was not a resident of the borough.  A variation order had been made to a contract reducing the work that needed to be carried out by £700. However, it had been included in the Final Account and paid.

Essential Recommendations

10. As at the end of 2013 survey there were 4 essential recommendations awaiting implementation. A further 4 were added after the survey. The 2014 survey confirmed that all 8 were now implemented or could be cancelled and have been closed down by internal audit.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Head of Audit's Annual OpinionReport 437 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
GF
Councillor Geoff FazackarleyVice-Chairman, present
TK
Councillor Tim KnightChairman, present
PD
Councillor Peter DaviesCommittee Member, apologies, sent representative
TH
Councillor Tiffany HarperCommittee Member, present
DS
Councillor Dennis SteadmanCommittee Member, present
PW
Councillor Paul Whittle, JPCommittee Member, apologies, sent representative
CW
Councillor Christopher WoodCommittee Member, present
LK
Councillor Leslie KeebleReserve, present as substitute
DN
Councillor David NorrisReserve, present as substitute
MB
Melanie BettleyCommittee Officer, expected
PD
Paul DoranOfficer, expected
EH
Elaine HammellOfficer, expected

All 14 on the meeting page

On this subject at Fareham

Search all
  1. Head of Audit's Annual OpinionThis decision
  2. Head of Internal Audits Quarterly Report and Annual PlanApproved
  3. Head of Internal Audits Quarterly ReportDecided
  4. Head of Audits Quarterly ReportDecided
  5. Head of Internal Audits Quarterly ReportDecided
  6. Head of Internal Audits Annual OpinionNoted

More from Fareham Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. Noted Open
8 Sep 2026 Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... Noted Open
8 Sep 2026 Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. Decided Open
8 Sep 2026 Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... Approved Open
27 Jul 2026 External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies