CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Fareham Borough Council
Planning Committee, Wednesday 16 January 2019 at 2.30pm

Five Year Housing Land Supply Position

Decided Planning 1 paper

Planning Committee decided this item on Wednesday 16 January 2019. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that the Committee note:- (i). the content of the report and the current 5-Year Housing Land Supply position; (ii). that the 5-Year Housing Land Supply Position set out in the attached report (which will be updated regularly as appropriate) is a material consideration in the determination of planning applications for residential development; (iii). when the Government publishes the Housing Delivery Test results, Officers believe that this Council will be required to apply a 20% buffer to the 5-Year Housing Land Supply position, and Members should make decisions on planning applications on that basis; and (iv). that the Government are consulting on adjustments to the new standard method used to calculate Local Housing Need, following publication of the new household growth projections on 20 th September 2018. If implemented these adjustments will further increase the Council’s housing requirements, above those arising from the Housing Delivery Test.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

Summary

At their meeting on the 9th October 2017, the Executive resolved that Officers present a report to the Planning Committee on the Council’s current 5-Year Housing Supply (5YHLS) position on a regular basis.

The following report provides the latest update, and supersedes the update previously provided to the Planning Committee on 12th December 2018.

Recommendation

That the Committee note: -

(i) the content of the report and the current 5-Year Housing Land Supply position; (ii) that the 5-Year Housing Land Supply Position set out in the attached report (which will be updated regularly as appropriate) is a material consideration in the determination of planning applications for residential development; (iii) when the Government publishes the Housing Delivery Test results, Officers believe that this Council will be required to apply a 20% buffer to the 5-Year Housing Land Supply position, and Members should make decisions on planning applications on that basis; and (iv) that the Government are consulting on adjustments to the new standard method used to calculate Local Housing Need, following publication of the new household growth projections on 20th September 2018. If implemented these adjustments will further increase the Council’s housing requirements, above that arising from the Housing Delivery Test. INTRODUCTION

1. The following 5YHLS position updates and supersedes those previously provided to the Planning Committee. It will continue to be regularly updated as appropriate and will represent a material consideration in the determination of planning applications. It should be noted that the Council’s housing land supply position can go down as well as up depending on the circumstances relevant at any given time.

NATIONAL PLANNING CHANGES

2. The revised NPPF and PPG changed how Local Planning Authorities must calculate their housing need figure. Prior to publication of the revised Framework and Guidance, housing need was calculated through a process called Objectively Assessed Need (OAN). The requirement of the revised NPPF is for housing need to now be calculated by a new standard method, as set out in the PPG.

3. The standard method uses household growth projections and house-price to earnings affordability data (produced by the Office for National Statistics) to calculate the Local Housing Need figure for a Local Planning Authority.

4. In September, the Office for National Statistics published new household growth projections. The new projections are 2016-based and update the previous 2014- based projections which were used to calculate the annual housing need figure.

5. At the Planning Committee meeting in October, Members were advised that using the new household growth projections within the standard method reduced Fareham’s housing need by 65 dwellings per annum from the figure reported to September Planning Committee. The housing need figure for Fareham, using the standard method, became 479 dwellings per annum.

6. Calculation of the Council’s 5-Year Housing Land Supply Position based on an annual dwelling requirement of 479 gave a projected position of 4.95 years in October 2018.

7. The Housing Delivery Test results which the Ministry of Housing, Communities and Local Government (MHCLG) were due to publish in November had still not been published as at the 8th January. Officers believe that when these results are published they will require this Council to apply a buffer of 20%.

8. At the Planning Committee on the 12th December, Members were advised that as this Council will be required to apply a 20% buffer to its 5-Year Housing Land Supply requirement, Members should determine planning applications on that basis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Five Year Housing Land Supply PositionReport 318 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 26 attended
NW
Councillor Nick WalkerChairman, present
IB
Councillor Ian BastableVice-Chairman, present
FB
Councillor Fred BirkettCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
PD
Councillor Peter DaviesCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
MF
Councillor Michael Ford, JPCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
RP
Councillor Roger Price, JPCommittee Member, present
MS
Councillor Mrs Susan WalkerGuest, in attendance
SC
Councillor Shaun CunninghamGuest, in attendance
MB
Melanie BettleyCommittee Officer, expected

All 26 on the meeting page

On this subject at Fareham

Search all
  1. Five Year Housing Land Supply PositionThis decision
  2. The Council's Five-Year Housing Land Supply Position UpdateDecided
  3. Five-Year Housing Land Supply Position UpdateNoted
  4. Five Year Housing Land Supply PositionNoted
  5. Five Year Housing Land Supply PositionNoted
  6. Five Year Housing Land Supply PositionNoted

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... Agreed Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open
12 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies