RESOLVED that the Executive: (a) approves the General Fund capital programme for 2019/20 to be financed as set out in this report; (b) agrees that the additional expenditure incurred, amounting to £67,363 be financed retrospectively from unallocated capital resources; and (c) notes the treasury management activity for 2019/20.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 03 August 2020 Portfolio: Policy and Resources
Subject: Capital and Treasury Management Outturn 2019/20
Report of: Deputy Chief Executive Officer
Corporate Priorities: A dynamic, prudent and progressive Council
Purpose: This report provides the Executive with details of the capital and treasury management outturn for 2019/20 to comply with the reporting requirements of the Code of Practice for Treasury Management. The report also seeks approval for the proposed methods of financing the General Fund capital programme.
Executive summary: Actual capital expenditure on General Fund schemes in 2019/20 was £16,496,896 (£3.5 million in 2018/19) compared with the revised capital programme of £17,324,000. The overall variance was £827,104 and a detailed analysis of the variations is given in Appendix A to this report.
Total savings of £214,924 were achieved, additional expenditure of £67,363 was incurred and a total of £679,543 will be carried forward into 2020/21. Details of the various methods used to finance this expenditure are set out in this report.
Full details of Treasury Management investment and borrowing activity in 2019/20 are also set out in this report. Treasury activity in 2019/20 is summarised below:
31 March 2019 2019/20 31 March 2020 Actual Movement Actual £’000 £’000 £’000 Total borrowing 45,510 12,149 57,659 Total investments (13,100) (3,200) (16,300) Net borrowing 32,410 8,949 41,359
Net interest received in 2019/20 was £603,316 (£481,480 in 2018/19) and net interest paid was £1,676,656 (£1,728,219 in 2018/19).
During 2019/20, the Council complied with its legislative and regulatory requirements of the Prudential Code. Recommendation: It is recommended that the Executive:
(a) approves the General Fund capital programme for 2019/20 to be financed as set out in this report;
(b) agrees that the additional expenditure incurred, amounting to £67,363 be financed retrospectively from unallocated capital resources; and
(c) notes the treasury management activity for 2019/20.
Reason: To provide the Executive with details of the capital and treasury management outturn in 2019/20 and to comply with the reporting requirements of the Code of Practice for Treasury Management.
Cost of proposals: The necessary resources are available to finance the General Fund capital programme for 2019/20 including the additional expenditure of £67,363.
Appendices: A: Capital Expenditure 2019/20 B: Economic Commentary by Treasury Advisors, Arlingclose C: Prudential and Treasury Indicators 2019/20
Background papers: None
Reference papers: Finance Strategy, Capital Programme, Revenue Budget and Council Tax 2020/21, Executive Committee, 3 February 2020
Treasury Management Strategy and Prudential Indicators 2019/20, Council, 22 February 2019
CIPFA Code of Practice for Treasury Management Executive Briefing Paper Date: 03 August 2020 Subject: Capital and Treasury Management Outturn 2019/20 Briefing by: Deputy Chief Executive Officer Portfolio: Policy and Resources
INTRODUCTION
1. This report provides the Executive with details of the capital and treasury management outturn for 2019/20 to comply with the reporting requirements of the Code of Practice for Treasury Management.
CAPITAL OUTTURN REPORT 2019/20
2. The capital programme for 2019/20, approved in February this year for the General Fund was £17,324,000. The actual capital expenditure, detailed in Appendix A, was £16,496,896 (£3.5 million in 2018/19) giving an overall variation of £827,104. A summary, including savings and additional expenditure, is summarised in the table below.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.