This report sets out for the information of Members details of the actual revenue expenditure for 2019/20 in respect of the services for which this Committee is responsible.
The Committee is asked to note the content of the report. INTRODUCTION
1. The final accounts for the financial year for this Committee shows that the actual expenditure of £953,091 was £286,191 (43%) above the revised budget of £666,900 which was agreed by this Committee in January 2020 and approved by Full Council in February 2020.
2. The actual totals of gross expenditure and income are set out in the table below.
Revised Budget Actual Variance 2019/20 2019/20 2019/20 £ £ £ Employees 792,200 895,856 103,656 Transport 11,600 13,749 2,149 Supplies & Services 142,800 358,096 215,296 Third Party Payments 100,200 97,053 -3,147 Internal Recharges 166,100 161,130 -4,970 GROSS EXPENDITURE 1,212,900 1,525,883 312,983
Other Income -2,600 -20,000 -17,400 Fees & Charges -543,400 -552,792 -9,392 GROSS INCOME -546,000 -572,792 -26,792
NET EXPENDITURE 666,900 953,091 286,191
3. The main reasons for the variance was due increased spend on consultants and legal costs in relation to planning applications and appeals. There was also additional spend on employee costs mainly due to additional pension costs that are removed from the overall council position. Income from fees and charges were lower than anticipated so the income target was reduced by £100,000 in the last quarter.
4. The actual net revenue expenditure for the year analysed over the main services heading is shown in the following table:-
Revised Budget Actual Variance 2019/20 2019/20 2019/20 £ £ £ Planning Applications 249,500 396,601 147,101 Planning Advice 235,700 238,037 2,337 Planning Enforcement 125,400 97,146 -28,254 Planning Appeals 56,300 221,307 165,007 666,900 953,091 286,191 5. A detailed breakdown of the actual cost of the individual services is shown in Appendix A. The main variations which exceed £1,000 from the approved budgets are detailed below.
PLANNING APPLICATIONS
6. The service was overspent by just over £147,000 after a revised budget increase of £100,000 to take account of lower planning fee income. The main reason for variance was a large overspend in the employee budget £117,900, mainly due to additional pension costs of £77,600. A temporary Principal Planner post linked to income was established and not included in the budget £57,000. Offset by various staffing savings during the year of £19,700, which included maternity cover and managing vacancies.
7. There were additional use of consultants for providing specialist advice on Air Quality and the Welborne application. The council did receive a 50% contribution from the developer towards this of £52,400.
8. There was reduction in income from applications of over £52,300 during the year even after the original budget was reduced by £100,000 for the revised budget. The planning applications remain low due to the ongoing issues with nitrates.
9. There was additional income from the Legal Partnership of smaller S106 remittances totalling £23,800 for recovery of staff time.
PLANNING ADVICE
10. The overall overspend for this service was just over £2,000. There were savings from vacanct posts throughout the year although this was offset by an overspend due to pension costs of £23,900.
11. Income was a third less than budgeted, £13,500 as the income was expected for the whole year, but the additional fees weren’t approved until Feb 2020.
PLANNING ENFORCEMENT
12. The overall underspend for this service was just over £28,000. The main reason for this was unexpected £20,000 income for costs awarded from the Woodhams case for breach of a Tree Preservation Order. There were savings from vacancy management throughout the year £20,800 and additional pension costs of £12,200.
PLANNING APPEALS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Actual Revenue ExpenditureReport | 162 KB | DownloadRead as text |
Follow Planning Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... | Decided | Open |
| 9 Sep 2026 | Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... | Agreed | Open |
| 9 Sep 2026 | P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... | Decided | Open |
| 9 Sep 2026 | P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... | Decided | Open |
| 12 Aug 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.