Resolved
RESOLVED that the Committee note the content of the report.
Planning Committee noted this item on Wednesday 19 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Committee note the content of the report.
This report sets out for the information of Members details of the actual revenue expenditure for 2020/21 in respect of the services for which this Committee is responsible.
The Committee is asked to note the content of the report. INTRODUCTION
1. The final accounts for the financial year for this Committee shows that the actual expenditure of £848,628 was £249,628 (42%) above the revised budget of £599,000 which was agreed by the executive in December 2020.
2. The actual totals of gross expenditure and income are set out in the table below.
Revised Budget Actual Variance 2020/21 2020/21 2020/21 £ £ £ Employees 762,200 894,597 132,397 Transport 11,500 9,774 -1,726 Supplies & Services 167,100 334,954 137,854 Third Party Payments 113,300 106,350 -7,370 Internal Recharges 185,900 172,350 -13,550 GROSS EXPENDITURE 1,212,900 1,517,705 277,705
Other Income -2,600 -96 2,504 Fees & Charges -641,000 -669,077 -28,077 GROSS INCOME -641,000 -848,628 -28,077
NET EXPENDITURE 599,000 848,628 249,628
3. The main reasons for the variance was because of additional spend on employee costs due to additional pension costs that are removed from the overall council position. There was also increased spend on consultants and legal costs in relation to planning applications and appeals. Application fee income and work from the legal partnership exceeded the budgeted fees and charges projection, offsetting the overall appeals costs.
4. The actual net revenue expenditure for the year analysed over the main services heading is shown in the following table:-
Revised Budget Actual Variance 2020/21 2020/21 2020/21 £ £ £ Planning Applications 108,200 204,175 95,975 Planning Advice 204,300 224,323 20,023 Planning Enforcement 140,700 156,317 15,617 Planning Appeals 145,800 263,813 118,013 599,000 848,628 249,628
5. A detailed breakdown of the actual cost of the individual services is shown in Appendix A. The main variations which exceed £5,000 from the approved budgets are detailed below. PLANNING APPLICATIONS
6. The service was overspent by just under £96,000, the main reason for variance was a large overspend in the employee budget of £81,500. This was due to additional pension costs of £92,500 which has been offset by various staffing savings during the year of £13,000.
7. There were additional use of consultants for providing specialist advice, such as habitat, ecology and various viability assessments contributing to a £58,900 overspend in this area.
8. There was additional income of £48,700 from the Southampton and Fareham Legal Partnership from costs recovered for work on S106 agreements.
9. Despite a slow start to planning application income during the year, the number of applications has nearly doubled from the previous year. There was increased income of £138,000 compared to the previous financial year, however the overall variance in income from applications was a shortfall of £13,700 during the year.
PLANNING ADVICE
10. The overall overspend for this service was just over £20,000. There were savings from vacant posts throughout the year although this was offset by an overspend due to pension costs of £32,200.
11. Income was slightly less than budgeted by £2,500.
PLANNING ENFORCEMENT
12. The overall overspend for this service was just over £15,000. The main reason for this was additional pension costs of £19,600.
PLANNING APPEALS
13. The overall overspend for this service was just over £118,000. There were a number of high profile planning appeals requiring the use of consultants and legal representation.
14. The largest spend on appeals during the year included Newgate Lane North and South (£170,000), the Tithe Barn (£30,650), Newgate Lane gypsy and traveller appeal (£7,900).
15. There were also two judicial reviews during the yea, Save Warsash (£15,100) and Egmont Nurseries (£3,000) with final costs to be concluded in 2021/22.
RISK ASSESSMENT
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Actual Revenue ExpenditureReport | 199 KB | DownloadRead as text |
Follow Planning Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... | Decided | Open |
| 9 Sep 2026 | Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... | Agreed | Open |
| 9 Sep 2026 | P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... | Decided | Open |
| 9 Sep 2026 | P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... | Decided | Open |
| 12 Aug 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.