Approved Executive 1 paper

Executive approved this item on Monday 15 July 2024. Below is the council's own wording, with the papers it was decided on.

Item9(1)

Resolved

RESOLVED that the Executive: (a) approves the principal of providing an evening route between Fareham Live, through FSC to West Street and Market Quay Car Park; (b) subject to the approval of recommendation (a) above, approves a budget of £10,000 to provide improvements, including wayfinding and lighting (subject to Hampshire County Council), to the existing identified routes and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to agree the final scheme design and delivery timeline and to enter into contracts to secure this, within the agreed budget; (c) subject to the approval of recommendation (a) above, approves a maximum budget of £51,000 to provide security officers at FSC and delegates authority to the Director of Planning and Regeneration to enter into or vary contracts to secure the delivery of this, within agreed budgets; (d) subject to the approval of recommendation (a) above, approves a budget of £76,800 for the provision of interventions, public realm improvements and wayfinding, and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to agree the final scheme design and delivery timeline and to enter into contracts to secure this, within the agreed budget; and (e) subject to the approval of recommendation (a) above, delegates authority to the Director of Planning and Regeneration to draw on the remaining regeneration budget, if necessary, to achieve the delivery of the above.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 15 July 2024 Portfolio: Policy and Resources

Subject: Fareham Town Centre Regeneration – North to South Route Report of: Director of Planning and Regeneration

Fareham Town Centre Regeneration Corporate Priorities: Promote Economic Development

Purpose: To seek approval for the creation of an evening route within Fareham town centre between Fareham Live, through Fareham Shopping Centre to West Street and Market Quay Car Park beyond. This route will include a range of interventions to provide a legible, animated, and engaging route alongside security provision within Fareham Shopping Centre (FSC). This will support the opening of Fareham Live and the wider Fareham Town Centre Regeneration programme.

Executive summary: The Council has a strong ambition to reverse the decline of Fareham Town Centre through regeneration, recognising the wider placemaking, economic regeneration and health benefits a more successful town centre would bring.

Work has already begun to deliver the Council’s significant regeneration ambition with the construction of Fareham Live, the demolition and replacement of Osborn Road multi storey car park and the purchase of FSC in September 2023.

The Council has appointed an asset manager to manage the Shopping Centre, alongside regeneration consultants to develop a deliverable and realistic Regeneration Strategy and Action Plan. A final Regeneration Strategy and Action Plan will be presented to the Executive in Winter 2024.

In advance of the Regeneration Strategy and Action Plan, this report seeks agreement to bring forward the delivery of an evening route between Fareham Live, through Fareham Shopping Centre to West Street and Market Quay Car Park beyond. The principal objectives of opening an evening route are to provide a direct, legible, and secure connection from Fareham Live through FSC to West Street, to provide a high-quality visitor experience and to capture wider economic benefits for town centre businesses.

Recommendation: It is recommended that the Executive:

(a) approves the principal of providing an evening route between Fareham Live, through FSC to West Street and Market Quay Car Park;

(b) subject to the approval of recommendation (a) above, approves a budget of £10,000 to provide improvements, including wayfinding and lighting (subject to Hampshire County Council), to the existing identified routes and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to agree the final scheme design and delivery timeline and to enter into contracts to secure this, within the agreed budget;

(c) subject to the approval of recommendation (a) above, approves a maximum budget of £51,000 to provide security officers at FSC and delegates authority to the Director of Planning and Regeneration to enter into or vary contracts to secure the delivery of this, within the agreed budget;

(d) subject to the approval of recommendation (a) above, approves a budget of £76,800 for the provision of interventions, public realm improvements and wayfinding, and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to agree the final scheme design and delivery timeline and to enter into contracts to secure this, within the agreed budget; and

(e) subject to the approval of recommendation (a) above, delegates authority to the Director of Planning and Regeneration to draw on the remaining regeneration budget, if necessary, to achieve the delivery of the above.

Reason: To support the Council's investment in Fareham Live, ensure the delivery of a strategic town centre regeneration objective and to capture the wider economic benefits this would bring to the town centre.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fareham Town Centre Regeneration: North to South RouteReport 2.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 15 attended
SM
Councillor Simon MartinCommittee Member, present
IB
Councillor Ian BastableCommittee Member, apologies
FB
Councillor Fred BirkettCommittee Member, apologies
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
AW
Andrew WannellOfficer, expected
SR
Sarah RobinsonOfficer, expected
SW
Sarah WardOfficer, expected
LU
Leigh UsherCommittee Officer, expected

All 15 on the meeting page

On this subject at Fareham

Search all
  1. Fareham Town Centre Regeneration - North to South RouteThis decision
  2. Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment - shopping arcade, entrances and associated improvement worksApproved
  3. Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment: Shopping Arcade, Entrances and associated improvement worksNoted
  4. Fareham Town Centre Regeneration Programme and MasterplanApproved
  5. Fareham Town Centre Regeneration - West Street Public RealmApproved
  6. Fareham Town Centre Regeneration - North/South Evening RouteApproved

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies