Chief Internal Auditors Quarterly Report

Agreed Finance 1 paper

Audit and Governance Committee agreed this item on Monday 23 September 2024. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

It was agreed that in future the report will make clear the type of audit assignment completed which would influence if an audit opinion would be expected. It was also agreed that that when concerns are raised from members on the number of recommendations made, that these audits will be followed up and be included in a future report to provide an update to the Committee. RESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

This report is a standard item on the Audit and Governance Committee agenda with the aim of providing Members with the assurances arising from the latest internal audit work. It also gives an update on the progress being made with setting and delivering the audit plans.

Recommendation

It is RECOMMENDED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. INTRODUCTION

1. This report provides the assurances arising from the latest internal audit work and gives an update on the progress being made with setting and delivering the audit plans.

PROGRESS OF THE 2024/25 AUDIT PLAN

2. This Work has commenced on 11 (44%) of the 25 audits in the current internal audit plan, as noted in Appendix One, such that:

• 3 are at Stage 1 (The Audit teams have started drawing up the scope of coverage for the assignment), • 1 is at Stage 2 (A scoping meeting has been held with the Sponsor in the client service. • 4 are at Stage 4 (The Auditor has started to deliver the agreed scope of work), • 1 is at Stage 6 (Any additional testing identified has been completed) and • 2 are at Stage 10 (The final report has been issued) FINALISING PREVIOUS PLANS

3. There is 1 audit outstanding from last year’s plan which will be completed in the coming months. There are 5 outstanding audits from the previous Audit Plans. Resource is currently being targeted to complete the review of all outstanding recommendations.

FINDINGS FROM COMPLETED AUDITS

4. 5 audits have been completed since the last report as highlighted in the table below.

Recommendations Made Assurance Audit New New Outstanding Opinion Previous Essential Essential Important or Important

Fareham Live - 2023/24 Strong - - -

Parking Income - 2023/24 Strong - 1 -

Service charges (Civic Offices) – Limited 1 2 - 2023/24

Anti-Bribery Arrangements 2023/24 N/A 1 4 -

Fixed Assets 2024/25 Strong - - 1

Local Tax Collection 2024/25 Reasonable - 2 1 RISK ASSESSMENT

5. There is a risk consideration in relation to this report, arising from the Service Charges (Civic Offices) audit. Testing highlighted calculation errors in respect of three tenants in the Civic Offices which resulted in an underpayment of their Service Charges. Recommendations have been made to address the recovery of the underpayments and to strengthen the controls over invoicing and reconciliation procedures.

Appendices: Appendix One - Audits in the 2024/25 Plan Appendix Two – Reference Tables

Background Papers: Chief Internal Auditor’s quarterly report to the Audit and Governance Committee on 18th July 2024.

Enquiries: For further information on this report please contact Mark Somerset. (Tel: 023 9284 1443) or Clare Rogers (Tel: 01329 824691). APPENDIX ONE

AUDITS IN THE 2024/25 PLAN

Direction of New Recommendations Previous Recs. (E and I only) Progress Stage reached Days Assurance Travel & Audit Title & Report Number report where Errors of 10* in Plan Opinion Date of last In Not included Found Essential Important Implemented Cancelled audit Progress Implemented ? Y/N

FUNDAMENTAL SYSTEM AUDITS

Accounts Receivable (1303) 1 12

Accounts Payable (1304) 12

September Local Tax Collection (1305) 10 12 Reasonable  21/22 N - 2 4 - 1 - 2024

September Fixed Assets (1306) 10 12 Strong 21/22 2024 N - - - - 1 -

SERVICE AND SYSTEMS – HIGH RISK Property Maintenance & Inspections - Council Buildings 10 (1307)

Planned Property Maintenance 15 (1308)

Housing Communal Services 10 (1309)

Housing Delivery & Enabling 10 (1310)

Street Cleansing (1311) 4 10

Parking Strategy (Capital 4 10 Spend) (1312) Direction of New Recommendations Previous Recs. (E and I only) Progress Stage reached Days Assurance Travel & Audit Title & Report Number report where Errors of 10* in Plan Opinion Date of last In Not included Found Essential Important Implemented Cancelled audit Progress Implemented ? Y/N SERVICES AND SYSTEMS - OTHER

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Chief Internal Auditors Quarterly ReportReport 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
RB
Councillor Roger BirdChairman, present
TH
Councillor Tiffany HarperVice-Chairman, present
FB
Councillor Frair BurgessCommittee Member, present
TE
Councillor Tina EllisCommittee Member, present
DF
Councillor David FootCommittee Member, present
DH
Councillor David HamiltonCommittee Member, present
PW
Councillor Paul WhittleCommittee Member, present
SR
Sarah RobinsonOfficer, expected
EH
Elaine HammellOfficer, expected
AW
Andrew WannellOfficer, expected
AH
Astra HughesCommittee Officer, expected

On this subject at Fareham

Search all
  1. Chief Internal Auditors Quarterly ReportThis decision
  2. Chief Internal Auditor's Quarterly ReportDecided
  3. Chief Internal Auditor's Quarterly ReportDecided
  4. Chief Internal Auditors Annual Opinion 2025/26Noted
  5. Chief Internal Auditor's Quarterly ReportApproved
  6. Chief Internal Auditor's Quarterly ReportDecided

More from Fareham Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. Noted Open
8 Sep 2026 Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... Noted Open
8 Sep 2026 Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. Decided Open
8 Sep 2026 Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... Approved Open