Executive, Monday 2 March 2026 at 5.00pm

Infrastructure Improvements at Faraday Business Park, Daedalus

Approved Executive 2 papers

AI summaryFareham Borough Council's Executive has approved a £410,000 budget for professional fees to progress a £2.2 million link road at Faraday Business Park, Daedalus, and delegated authority to the Director of Planning and Regeneration to award related contracts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved£410,000 for fees; contracts to Director of Planning and Regeneration
Money£410,000From Retained Business Rates; part of £2,200,000 link road
What happens nextStart Phase 1 immediatelyAdditional Feasibility and Concept Design
Who it affectsFaraday Business Park, DaedalusImproved internal connectivity and traffic capacity

What was decided

The Executive approved a budget of £410,000 for fees associated with pursuing Faraday Business Park infrastructure requirements. Report P27

Authority was delegated to the Director of Planning and Regeneration to award associated contracts, subject to the budget approval. Report P27

Why

The main access junction into the site (Spitfire Way/Broom Way) needs upgrades to maximise the development potential of Faraday Business Park, where development has exceeded original expectations. Report P16, P17

The business case is good, with projected land receipts from approximately 9.2 acres of non-airside land significantly above the link road project cost, and there is current commercial interest in the land. Report P19, P20

Waiting for the grant funding outcome would delay delivery, so starting the project now allows progress while the Hampshire County Council grant application is decided. Report P26, P27

What happens next

Officers will start the project through four phases: additional feasibility and concept design, developed design and planning, pre-construction, and construction. Report P21, P22, P23, P24

A project review will be undertaken with the Director of Planning and Regeneration at the end of each phase before proceeding. Report P27

If grant funding is not secured, the project can be paused, though a planning consent and some progress would have been achieved by then. Report P27

The money

  • £410,000 Budget for professional fees to be funded from Retained Business Rates Report P27
  • £2,200,000 Estimated total cost of the link road project connecting Spitfire Way and Meteor Way Report P18, P26
  • 50% Proposed match funding share from Retained Business Rates, to support the Hampshire County Council grant application Report P26

Options considered

  • Chosen: Approve £410,000 budget and start the project now. Avoids delay in delivery while grant outcome is awaited; enables critical delivery timescales attached to current land interest Report P26, P27
  • Rejected: Wait for grant funding confirmation before proceeding. Would delay delivery of the project Report P27

Implications

  • Financial: The £410,000 fees budget will be funded from Retained Business Rates and could form part of the 50% match funding if the Hampshire County Council grant is secured. Report P26, P27
  • Risk: If the grant application is unsuccessful, the project can be paused, but some fees and a planning consent would have been incurred and secured. Report P27
  • Climate: The link road is expected to ease congestion and emissions by creating internal connectivity, removing the need to exit and re-enter the estate, and includes pedestrian and cycle links to public transport. Report P29
  • Other: Daedalus is identified as an accelerated key project in the Corporate Strategy Review (October 2025), with new employment floorspace planned over the next six years. Report P5, P6

Who and where

  • Existing and potential commercial tenants at Faraday Business Park, Daedalus Report P6, P16, P19
  • Local people seeking skilled employment in aviation, aerospace and advanced manufacturing Report P7, P9
  • Road users and pedestrians/cyclists using the Broom Way junctions and Daedalus estate Report P17, P18, P29

Timeline

  • Now (March 2026): Start project with Phase 1: Additional Feasibility and Concept Design Report P21, P22
  • Summer 2026: Outcome of Hampshire County Council grant funding application from LEP Legacy Reserve Funds expected Report P26
  • As early as November 2027: Link road could be completed if started now Report P21

Plain English for the jargon

  • Daedalus: The Council's largest employment site, a 369-acre freehold site at Fareham allocated in the Local Plan 2037 for 127,900 sqm of space.
  • Faraday Business Park: An advanced business park on the eastern side of Daedalus, hosting a mix of target sector organisations.
  • Retained Business Rates (RBR): Business rates income retained locally by the Council, proposed as the source of funding for the fees budget and match funding.
  • LEP Legacy Reserve Funds: Funds administered via Hampshire County Council from the former Local Enterprise Partnership, the source of the grant application.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13(1)

Resolved

RESOLVED that the Executive: (a) approves a budget of £410,000 for fees associated with pursuing Faraday Business Park Infrastructure requirements; and (b) subject to the approval of recommendation (a) above, delegates authority to the Director of Planning and Regeneration to award associated contracts.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 2 March 2026 Portfolio: Policy and Resources

Subject: Infrastructure Improvements at Faraday Business Park, Daedalus Report of: Director of Planning and Regeneration Promote Economic Development; Corporate Priorities: Responsive, Inclusive and Innovative Council.

Purpose: To seek approval of a budget for professional fees associated with infrastructure requirements at Faraday Business Park, Daedalus and a delegation to award associated contracts

Executive summary: Daedalus is the Council’s largest employment site being allocated in the Fareham Local Plan (2037) to provide a total of 127,900 sqm of space. The 369-acre freehold site was purchased in 2015 from the Homes and Communities Agency. It is an important Corporate Priority project for the Council and was identified as an accelerated key project as part of the annual review of the Corporate Strategy undertaken in October 2025.

Faraday Business Park is one of the most advanced areas of Daedalus being located on its eastern side. Development has been undertaken and the extent of this is above that originally envisaged. The capacity of the main access into the site (junction of Spitfire Way/Broom Way) has been investigated and works are likely to be required to maximise the development potential of the site. One solution is a link road between Faraday Business Park and the Skills and Innovation area (See Appendix B). It would connect Spitfire Way and Meteor Way, dispersing traffic movements between the two junctions. Initial budget costings have been prepared and the anticipated cost is approximately £2,200,000.

The remaining land at Faraday Business Park is currently being marketed to potential occupiers. Non-Airside land extends to circa 9.2 acres, which has a projected land value significantly above the project cost of the link road. In addition, there is also non-airside land, the extent of which is difficult to pinpoint. as the boundaries could extend into the airfield. The Council does have initial interest from an occupier in a large section of the land at Faraday Business Park and there are critical timescales associated with the requirement. Taking account of the potential land receipts, the business case is strong and this is a project the Council should progress further, especially given current interest in the land. Notwithstanding this the longer the project is delayed the longer it could take to maximise the development potential of employment land at Faraday Business Park. The Council has recently made a grant application to Hampshire County Council in relation to the project from LEP Legacy Reserve Funds. If successful this would not cover the entire cost as the Council has offered match funding of 50% and it has been suggested that this will be funded from Retained Business Rates (RBR), subject to Executive approval. The outcome of the grant funding application will not be confirmed until the summer of 2026.

It is proposed that the Council should start the project now and it is therefore recommended that the Executive approve a budget for the associated professional fees (£410,000). This will enable the project to proceed without delay at least to a developed design and planning stage. If the Council waits until the grant funding is confirmed there will be a delay in delivery. This budget request will be funded from RBR. Eventually, if the project proceeds and a grant can be secured any expenditure is likely to form part of the match funding noted above. If funding cannot be secured, the project can be paused, but at least a planning consent should have been secured and progress has been made.

Recommendation: It is recommended that the Executive:

(a) approves a budget of £410,000 for fees associated with pursuing Faraday Business Park Infrastructure requirements; and

(b) subject to the approval of recommendation (a) above, delegates authority to the Director of Planning and Regeneration to award associated contracts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Example Route for Link Road (1)Appendix B 808 KB Download
PDF
Infrastructure Improvements at Faraday Business Park, DaedalusReport 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
SM
Councillor Simon MartinCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
LW
Councillor Lisa WhittleGuest, in attendance
PW
Councillor Paul WhittleGuest, in attendance
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
LU
Leigh UsherOfficer, expected
AW
Andrew WannellOfficer, expected

All 17 on the meeting page

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies