Redevelopment of Redoubt Court, Fort Fareham

Approved Executive 1 paper

AI summaryFareham Executive approved demolishing Redoubt Court to build 21 affordable homes at Fort Fareham, subject to planning consent and contractor appointment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to planning consent and the building becoming vacant
MoneyConfidentialCosts in Confidential Appendix A
What happens nextPlanning application Spring 2026Contractor appointment Autumn 2026
Who it affectsFort Fareham estate and residentsHouseholds on the housing waiting list

What was decided

The Executive approved the demolition of Redoubt Court once the remaining occupied building becomes vacant, subject to formal planning consent being granted. Report P1

The Executive approved the funding mechanisms for the redevelopment, as set out in Confidential Appendix A, to deliver a new affordable housing scheme on the wider site. Report P7, P8

Authority was delegated to the Director of Housing and Health, in consultation with the Executive Member for Housing, to appoint a contractor and take all steps needed to implement the proposals. Report P10

Why

Redoubt Court was identified as a key redevelopment opportunity in the Fareham Housing Regeneration Strategy and is allocated for housing in the Fareham Local Plan 2037. Report P1, P2

The scheme will deliver around 21 affordable homes at social rent, a net gain of 13, including 18 apartments with one to three bedrooms and three family homes, with ground floor flats built to wheelchair accessible standard. Report P3

Public consultation in January 2026 was broadly positive, with concerns about wildlife and parking addressed through extra parking spaces and design changes to protect greenspace. Report P5, P6

What happens next

A planning application will be submitted in Spring 2026, with a contractor appointed in Autumn 2026 subject to planning approval and procurement. Report P11, P12

Construction is expected to take up to 18 months, with the timeline remaining indicative. Report P12

Implications

  • Financial: Cost figures are held in Confidential Appendix A to keep the tender process competitive. Report P8
  • Legal: Demolition and the new development are both subject to formal planning consent.
  • Other: Concerns raised in consultation about local wildlife and parking pressure were addressed through additional parking and design changes to limit habitat loss. Report P5, P6
  • Climate: No environmental or carbon impacts have been identified at this stage, with further assessment to follow any planning consent. Report P14

Who and where

  • Current residents of Redoubt Court, awaiting rehousing once the building is vacated Report P1
  • Households on the council housing waiting list who may be offered the new social rent homes Report P3
  • Residents of the wider Fort Fareham estate, who will see changes to parking and adjoining green space Report P4, P5

Timeline

  • November 2022: Fort Fareham added to the Fareham Housing Regeneration Strategy Report P1
  • 15 January 2026: In-person consultation event held on the Fort Fareham estate Report P5
  • Spring 2026: Planning application to be submitted, subject to Executive approval Report P12
  • Autumn 2026: Contractor to be appointed, subject to planning approval and procurement Report P12
  • Up to 18 months: Anticipated length of the construction programme Report P12
  • 8 January to 29 January 2026: Public consultation on the redevelopment proposals Report P5

Plain English for the jargon

  • Social rent: Rents set below market levels, aimed at lower income households on the housing waiting list.
  • HA51: The housing allocation reference for the Redoubt Court site in the Fareham Local Plan 2037.
  • Net gain of 13 affordable homes: The 21 new homes minus the existing Redoubt Court properties they replace.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9(2)

Resolved

RESOLVED that the Executive: (a) approves the demolition of Redoubt Court, subject to formal planning consent being granted, once the remaining occupied building becomes vacant; (b) approves the funding mechanisms for the redevelopment of Redoubt Court and the wider site to deliver a new affordable housing scheme, as outlined in the Confidential Appendix A to the report; and (c) delegates authority to the Director of Housing and Health, following consultation with the Executive Member for Housing to appoint a contractor to deliver the homes in line with the Council’s Contract Procedures Rules, and to undertake all actions required to implement the proposals within the report.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Background

3. In November 2022, Fort Fareham was added to the Fareham Housing Regeneration Strategy. The appendix highlighted several council homes within the estate requiring attention, and a programme of works, including energy efficiency upgrades and property improvements are ongoing. Additionally, Redoubt Court was identified as a key redevelopment opportunity, and the site was confirmed as a housing allocation (HA51) within the Fareham Local Plan 2037.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Redevelopment of Redoubt Court, Fort FarehamReport 117 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
SM
Councillor Simon MartinCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
LW
Councillor Lisa WhittleGuest, in attendance
PW
Councillor Paul WhittleGuest, in attendance
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
LU
Leigh UsherOfficer, expected
AW
Andrew WannellOfficer, expected

All 17 on the meeting page

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies