Gateshead Newcastle Joint Bridges Committee noted this item on Thursday 10 December 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED – (i) That it be noted that expected expenditure for 2020/21 is £30,3450 with a budget provision of £39,900. (ii) that the programme of maintenance and repair works to be carried out in 2021/22 as detailed in the report be recommended to the appropriate committee or delegated decision making of each authority. (iii) that a budget provision of £45,500 for 2021/22 as detailed in the report be recommend to the appropriate committee or delegated decision making for each authority for inclusion in that committee’s budget for 2021/22.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. Purpose of the report 1.1 This report details the expenditure for 2019/2020, reviews the expenditure for 2020/2021, and recommends a budget for expenditure on the Joint Tyne bridges for 2021/2022.
2. Recommendations 2.1 Committee is recommended to:
i Note the expected expenditure for 2020/2021 is £30,350 compared with a budget provision of £39,900.
ii Recommend the programme of maintenance and repair works to be carried out in 2021/2022, as detailed in paragraph 6, to the appropriate committee or delegated decision making of each authority.
iii Recommend a budget provision of £45,500 for 2021/2022, as detailed in paragraph 6 and Appendix A of this report, to the appropriate committee or delegated decision making of each authority for inclusion in that committee’s budget for 2021/2022. 3. Introduction and background 3.1 The Tyne, Swing, Redheugh, Scotswood and Newburn Bridges are jointly owned and maintained by Newcastle and Gateshead Councils. The High Level Bridge is owned and maintained by Network Rail except for the surfacing and lighting. The maintenance responsibility for these bridges is split as follows with costs shared on a population basis.
Newcastle City Council – Lead Authority Tyne Bridge Swing Bridge Newburn Bridge High Level Bridge – surfacing and lighting only
Gateshead Council – Lead Authority Redheugh Bridge Scotswood Bridge
This report presents details of the revenue maintenance of these bridges.
4. Year End Expenditure in 2019/2020 4.1 The year-end expenditure in 2019/2020 was £37,828 compared with a budget provision of £39,900 (Tyne £10,000, Swing £10,000, Redheugh £15,200, Scotswood £3,700, Newburn £1,000).
5. Review of Expenditure in 2020/2021 5.1 At the meeting of 19 December 2019, the budget provision for 2020/2021 was set at £39,650. The current estimated outturn is £30,350. A review of the expenditure is given below and details are shown in Appendix A.
Tyne Bridge
5.2The estimated outturn for the Tyne Bridge is £9,700 compared with a budget figure of £10,000. Works to the Tyne Bridge include minor drainage repairs, bird control measures and graffiti removal.
Swing Bridge
5.3The estimated outturn for the Swing Bridge is £9,000 compared to a budget figure of £10,000. Works to the Swing Bridge were restricted to minor safety repairs to the surfacing and bridge deck.
Redheugh Bridge
5.4The estimated outturn for the Redheugh Bridge is £7,150 compared to a budget allocation of £14,950. Works to the Redheugh Bridge include regular maintenance of the bridge drainage system, programmed maintenance to replace internal lighting and replace a security door, reactive maintenance to repair the pedestrian guardrail from vehicle impact and parapet mesh repair. Other regular and reactive maintenance were undertaken as part of the capital bridge maintenance works in February 2020.
Scotswood Bridge
5.5The estimated outturn for the Scotswood Bridge is £4,500 compared to a budget allocation of £3,700. Works to the Scotswood Bridge include regular maintenance to the bridge drainage system and river outfalls programmed maintenance of bridge drainage system and expansion joints and reactive maintenance to impact damage to the steel parapets.
Newburn Bridge
5.6The estimated outturn for the Newburn Bridge is nil compared to a budget allocation of £1,000. No works are anticipated this year.
6. Proposed Budget Provision for 2021/2020
Tyne Bridge
6.1An allowance of £10,000 has been identified for minor structural repairs, routine maintenance and utility payments on the bridge.
Swing Bridge
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Gateshead Newcastle Joint Bridges Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
Joint Tyne Bridges Capital BudgetRESOLVED i. The Committee noted the progress made on the planned capital works programme funded by the Department for...
Joint Tyne Bridges Revenue BudgetRESOLVED i. The Committee noted the outturn expenditure for 2023/24 is £34,992 compared with a budget provision of £4...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.