Gateshead Newcastle Joint Bridges Committee, Monday 16 December 2024 at 1.30pm

Joint Tyne Bridges Revenue Budget

Noted Committee 1 paper

Gateshead Newcastle Joint Bridges Committee noted this item on Monday 16 December 2024. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

RESOLVED i. The Committee noted the outturn expenditure for 2023/24 is £34,992 compared with a budget provision of £44,250. ii. The Committee recommended the programme of maintenance and repair works to be carried out in 2025/26, as detailed in paragraph 6, to the appropriate committee or delegated decision making of each authority. iii. The Committee recommended a budget provision of £74,495 for 2025/26, as detailed in paragraph 6 and Appendix A of this report, to the appropriate committee or delegated decision making of each authority for inclusion in that committee’s budget for 2025/26.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Gateshead Newcastle Joint Bridges Committee

Agenda item 8

Newcastle & Gateshead Joint Bridges Committee 16 December 2024 Joint Tyne Bridges Revenue Budget

Report by: Engineering Services Manager, Gateshead / Assistant Director of Transport, Newcastle

Ward Implications: Monument / Benwell & Scotswood / Callerton & Throckley / Ryton, Crawcrook & Stella / Blaydon / Dunston & Teams / Bridges

For decision

1. Purpose of the report 1.1 This report updates the outturn revenue expenditure for 2023/24, reviews the revenue expenditure for 2024/25, and recommends a revenue budget for expenditure on the Joint Tyne Bridges for 2025/26.

2. Recommendations 2.1 Committee is recommended to:

i Note the outturn expenditure for 2023/24 is £34,992 compared with a budget provision of £44,250.

ii Recommend the programme of maintenance and repair works to be carried out in 2025/26, as detailed in paragraph 6, to the appropriate committee or delegated decision making of each authority.

iii Recommend a budget provision of £74,495 for 2025/26, as detailed in paragraph 6 and Appendix A of this report, to the appropriate committee or delegated decision making of each authority for inclusion in that committee’s budget for 2025/26.

1 Agenda item 8

3. Introduction and background 3.1 The Tyne, Swing, Redheugh, Scotswood, and Newburn Bridges are jointly owned and maintained by Newcastle and Gateshead Councils. The High Level Bridge is owned and maintained by Network Rail except for the surfacing and lighting. The maintenance responsibility for these bridges is split as follows with costs shared on a population basis.

Newcastle City Council - Highway Authority  Tyne Bridge  Swing Bridge  Newburn Bridge  High Level Bridge - surfacing and lighting only

Gateshead Council - Highway Authority  Redheugh Bridge  Scotswood Bridge 3.2 The results of the 2021 Census have been published and showed changes to the population in both Newcastle and Gateshead which sets the cost share on a 60:40 basis. 3.3 This report presents details of the revenue maintenance of these bridges.

4. Year End Expenditure in 2023/24

4.1The year-end expenditure in 2023/2024 was £34,992 compared with a budget provision of £44,250 (Tyne £15,200, Swing £12,000, Redheugh £13,050, Scotswood £3,000, Newburn £1,000).

5. Review of Expenditure in 2024/25

5.1At the meeting of 14 December 2023, the proposed budget provision for 2024/25 was £38,050. The current estimated outturn is £59,898. A review of the expenditure is given below, and details are shown in Appendix A.

Tyne Bridge

5.2The estimated outturn for the Tyne Bridge is £200, in line with the budget figure of £200. This covers utility charges.

Swing Bridge

5.3The estimated outturn for the Swing Bridge is £2,200, below the budget figure of £12,000. Expenditure was moved to Capital repairs. The revenue works to the Swing Bridge were restricted to minor safety repairs to the footways and signage.

2 Agenda item 8

Redheugh Bridge

5.4The estimated outturn for the Redheugh Bridge is £46,155 compared to a budget figure of £38,100. Works to the Redheugh Bridge include regular maintenance of the bridge drainage system and additional maintenance of the drainage to the internal cells, planned repairs to the coping units, reactive maintenance to repair the pedestrian guardrail from vehicle impact, removal of incipient concrete spalls to the Newcastle Approach Viaduct.

Scotswood Bridge

5.5The estimated outturn for the Scotswood Bridge is £10,255 compared to a budget allocation of £10,255.

Newburn Bridge

5.6The estimated outturn for the Newburn Bridge is £0 compared to a budget allocation of £1,000. No works have been carried out or expected to the bridge this financial year.

6. Proposed Budget Provision for 2025/26 Tyne Bridge

6.1No revenue works are planned for the Tyne Bridge in 2025/26, however an allowance of £200 has been included for utility payments.

Swing Bridge

6.2An allowance of £12,000 has been identified for minor maintenance repairs and routine maintenance on the bridge.

High Level Bridge

6.3There is no planned maintenance on the bridge.

Redheugh Bridge

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Joint Tyne Bridges Revenue BudgetReport 179 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 12 attended
JM
Councillor John McElroyCommittee Member, present
BC
Councillor Brenda ClellandCommittee Member, absent
JE
Councillor John Eagle Gateshead CouncilCommittee Member, present
AW
Councillor Amanda WintcherCommittee Member, present
PA
Councillor Pauline AllenCommittee Member, present
SF
Councillor Steve FairlieCommittee Member, absent
AH
Councillor Alexander HayCommittee Member, present
DJ
Councillor Dr Juna SathianCommittee Member, apologies
PM
Councillor PJ MorrisseyCommittee Member, absent
AS
Alistair SwanCouncil Staff, in attendance
RG
Rob GilbertCouncil Staff, in attendance
TW
Trevor WaggettCouncil Staff, in attendance

On this subject at Gateshead

Search all
  1. Joint Tyne Bridges Revenue BudgetThis decision
  2. Introduction to the Tyne & Wear Trading Standards Joint CommitteeNoted
  3. Joint Tyne Bridges Capital BudgetNoted
  4. Joint Tyne Bridges Capital BudgetNoted
  5. Joint Tyne Bridges Revenue BudgetNoted
  6. Gateshead Appointments to Northumberland, Tyne and Wear and North Durham Joint Health OSCDecided

More from Gateshead Gateshead Newcastle Joint Bridges Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 Appointment of Chair for the Municipal Year 2026/27RESOLVED that Councillor Keating, Gateshead Council, be appointed as Chair of the Joint Bridges Committee for the 202... Decided Open
8 Jul 2026 Appointment of Vice Chair for the Municipal Year 2026/27RESOLVED that Councillor Ferguson, Newcastle City Council Council, be appointed as Vice-Chair of the Joint Bridges Co... Decided Open
16 Dec 2024 Minutes of the previous meeting held of 14 December 2023RESOLVED The Committee: i. Requested a formal response on the status of the swing bridge from the Port of Tyne. Decided Open
16 Dec 2024 Joint Tyne Bridges Capital BudgetRESOLVED i. The Committee noted the progress made on the planned capital works programme funded by the Department for... Noted Open
16 Dec 2024 Tyne Bridge RestorationRESOLVED i. The Committee noted the contents of the report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies