Gateshead Newcastle Joint Bridges Committee noted this item on Monday 16 December 2024. Below is the council's own wording, with the papers it was decided on.
RESOLVED i. The Committee noted the progress made on the planned capital works programme funded by the Department for Transport’s Highway Maintenance Block (HMB) for 2024/25. ii. The Committee the programme of planned capital works to be carried out in 2025/26 to the appropriate committee or delegated decision processes of each authority. iii. The Committee recommended a budget provision of £2,029,000 for 2025/26 to the appropriate committee or delegated decision processes of each authority for inclusion in budgets for 2025/26.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
Report to Gateshead Newcastle Joint Bridges Committee
Purpose of the report
1.1This report outlines the progress made on the planned 2024/25 capital works programme, details any unplanned capital works which were required during the year and recommends a capital budget for expenditure on the Joint Tyne Bridges in 2025/26.
Recommendations
2.1Committee is recommended to:
i Note the progress made on the planned capital works programme funded by the Department for Transport’s Highway Maintenance Block (HMB) for 2024/25.
ii Recommend the programme of planned capital works to be carried out in 2025/26, as detailed in paragraphs 4 to 9, to the appropriate committee or delegated decision processes of each authority.
iii Recommend a budget provision of £2,029,000 for 2025/26, as detailed in paragraphs 4 to 9 of this report, to the appropriate committee or delegated decision processes of each authority for inclusion in budgets for 2025/26.
1 Agenda item 7
3. Introduction and background
3.1Capital works undertaken on the Newcastle and Gateshead Joint Bridges is funded from the Department for Transport’s (DfT) Highway Maintenance Block (HMB) allocation. The maintenance costs are shared on a population basis.
3.2In December 2023 a Capital budget allocation for 2024/25 was set at £475,000; £425,000 to Redheugh Bridge and £50,000 to Scotswood Bridge. An allocation for the Tyne Bridge Restoration works was not set as the Department for Transport (DfT) approval for the project had not been given at the time of the Committee.
3.3Subsequently in February 2024 when the DfT funding was approved the Local Authority contribution for 2024/25 was identified as £577,717.
3.4The allocation to the Tyne Bridge Restoration will be fully expended. The estimated expenditure on the other bridges is detailed in paragraphs 5 to 9.
3.5The planned works to be carried out in 2025/26 is detailed in paragraphs 5 to 9, together with the recommended budget allocations.
4. Tyne Bridge
4.1There were no proposals to carry out any capital works under this budget in 2024/25.
4.2Major Road Network programme funding was received from the Department for Transport in February 2024 and the main works commenced in April 2024.
4.3Progress on these works is covered in detail in a separate report to this Committee.
4.4The estimated local authority contribution for 2025/26 is £1,029,000.
5 Swing Bridge
5.1There were no proposals to carry out any capital works in 2024/25.
5.2There are no proposals to carry out any capital works in 2025/26.
6. High Level Bridge
6.1There were no proposals to carry out any capital works in 2024/25.
6.2There are no proposals to carry out any capital works in 2025/26.
2 Agenda item 7
7. Redheugh Bridge
7.1There were proposals to carry out a principal inspection of the Redheugh Bridge in 2023/24. These works are currently being procured with the intention to undertake the inspection in 2024/25. A budget provision of £100,000 has been allowed for in 2024/25 for the proposed works, however recent market engagement suggests lower costs.
7.2A special inspection was carried out in 2023/24 of Pier N8 of the Newcastle Approach Viaduct which is within the Network Rail/LNER car park. This inspection has identified essential concrete repairs are required and a design for this has been developed.
7.3Spalling is also present at Pier N2 of the Newcastle Approach Viaduct which is within a public car park. Newcastle’s have engaged their contractor to install palisade fencing around the pier.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Gateshead Newcastle Joint Bridges Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
Joint Tyne Bridges Revenue BudgetRESOLVED i. The Committee noted the outturn expenditure for 2023/24 is £34,992 compared with a budget provision of £4...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.