HOUSING, ENVIRONMENT AND HEALTHY COMMUNITIES OSC 13th May 2024
TITLE OF REPORT: Building Safety and Compliance
Purpose of the Report 1. To provide an overview on the current building safety and compliance position
Background 2. The Building Safety Act 2022 (The Act) came into law on 1st October 2023 and introduced new duties for the management of fire and structural safety in high rise residential buildings.
3. The Act applies to new and existing occupied buildings over 18 metres high, or containing 7 storeys or more, and with at least two residential units.
4. The Council is required to provide a building safety case for its high-rise blocks. The Building Safety Regulator can request this at any time over the next five years in various tranches.
5. The tranches are prioritised on the height of the building, the number of residents and various other factors that raise the risk profile. The categorization may change as the inspection process progresses.
6. The Council have in place schemes of work to complete risk assessments and servicing of equipment to demonstrate compliance with the key six areas of compliance – fire, water, asbestos, electric, gas, mechanical..
Building Safety Current Position
7. Redheugh and Eslington, Regent and St Cuthberts Court are in Tranche 1 for safety case reports.
8. Acomb, Bedale, Ripley, Willerby, Barford, Stretford, Bensham, Warwick, Newbolt and Tennyson are in Trance 2.
9. Beacon, Lough and Fell, Adelaide, Brisbane, Melbourne and Sidney are in Tranche 3.
10. Park, Peareth and Priory are in Tranche 4.
11. There are no confirmed dates for when the safety cases will be requested by the Building Safety Regulator.
12. All Gateshead Council high-rise blocks were registered with the Building Safety Regulator by the deadline of 31st October 2023 and key structural and fire safety building information provided. 1 13. Further information was provided to the National Register of Social Housing fire safety remediation survey for the Regulator of Social Housing in April 2024.
14. A planned programme of fire risk assessments in high rise blocks is up to date.
15. External wall surveys have been carried out and audited by an external specialist company.
16. Fire strategies and block evacuation processes are in place and externally audited.
17. Customer vulnerability information is in place and shared with the Tyne and Wear Fire and Rescue Service (TWFRS).
18. High rise block audits by the TWFRS are in a rolling programme.
19. Resident engagement strategy, resident multi-storey safety group, complaints procedure and mandatory occurrence process are all in place.
20. 8 of 24 building safety case reports have been completed including those for the 4 tranche one blocks.
21. A quarterly inspection programme of 1,524 communal fire doors is in place.
22. An annual inspection programme of 1,850 flat front doors is in place with a 72% access rate. All non-accesses are in a follow up process with a legal route in place if necessary.
23. The high-rise fire detection system, within dwellings, complies with regulation but is under review for upgrading to a higher standard as part of future planned work.
24. New compliance software is in the process of implementation with a target date of April 2024. This will provide a major part of the golden thread of information directly from the various compliance and risk assessment programmes.
Risks and mitigations
25. There are two high rise blocks with window panels that do not meet current standards. Both are in the process of decommissioning and have acceptable mitigation in place agreed with the TWFRS. 32 of 166 flats in Redheugh are currently occupied and 40 of 166 at Eslington.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing and Compliance Performance Monitoring: Quarter 4Report | 117 KB | DownloadRead as text |
Follow Housing, Environment and Healthy Communities Overview and Scrutiny Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Introduction to Housing, Environment and Healthy Communities OSCRESOLVED ... view the full minutes text for item CPL3 | Decided | Open |
| 29 Jun 2026 | Performance Management and Improvement FrameworkRESOLVED that: i. the contents of the annual report at appendix 1 be noted. ii. the additional information will be ma... | Noted | Open |
| 29 Jun 2026 | Work ProgrammeRESOLVED that: i) The proposed work programme items to date be noted; ii) Work be carried out between the Chair and o... | Noted | Open |
| 23 Mar 2026 | Regulatory Judgement Improvement PlanRESOLVED that: i. the Committee provided its views and comments on the content of the report. | Decided | Open |
| 19 Jan 2026 | Building Safety and ComplianceRESOLVED that: i. the Committee provided its views and comments on the content of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.