(i) Cabinet recommended to Council that all variations to the 2024/25 Capital Programme. (ii) Cabinet recommended to Council the financing of the revised programme. (iii) Cabinet confirms to Council that capital expenditure and financing requirements have been revised in line with the amended budget and none of the approved Prudential Indicators set for 2024/25 have been breached. For the following reasons: a) To ensure the optimum use of the Council’s capital resources in 2024/25. b) To accommodate changes to the Council’s in-year capital expenditure plans. c) To ensure performance has been assessed against the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report sets out the latest position on the 2024/25 Capital Programme and Prudential Indicators at the end of the first quarter to 30 June 2024. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators.
Background
2. The original budget for the capital programme for 2024/25, as agreed by Council on 22 February 2024, totalled £113.9m. The first quarter review now projects the year-end expenditure to be £108.0m, £79.9m General Fund and £28.1m HRA.
3. The proposed variance in the capital programme at the first quarter comprises of the following movements: £m Slippage of planned capital expenditure from 2023/24 4.297 Other movements 0.831 Re-profiling of capital expenditure to future years (11.076) Total Variance (5.948)
4. A total of £4.297m of slippage was identified in 2023/24 on several key schemes, which were carried forward into 2024/25 including:
• £1.709m Loan to Gateshead Energy Company • £0.706m West Askew Road • £0.511m UK Shared Prosperity Fund
5. Planned investment has been re-profiled to future financial years on several schemes, amounting to a reduction of £11.076m in 2024/25, the schemes which have slipped include the following:
• (£6.078m) Schools Basic Needs Funding – design and planning works at schools is ongoing with schemes due to commence over the medium term. • (£2.625m) Housing Development – anticipated delays in the procurement of a developer • (£0.690m) Extra Care Scheme – work is ongoing to determine the requirements of the service. • (£0.500m) Development Site Preparation works – to support larger housing developments planned in future years.
Proposal
6. The report identifies planned capital expenditure of £108.0m for the 2024/25 financial year. The expected resources required to fund the Capital Programme are as follows: £m Prudential Borrowing 48.383 Projected Capital Receipts 0.750 Capital Grants and Contributions 30.727 Major Repairs Reserve (HRA) 19.114 Capital Grants and Contributions (HRA) 0.759 Right to Buy Receipts (HRA) 8.217 Total Capital Programme 107.950
9. CIPFA’s Prudential Code advises the regular monitoring of performance against the prudential indicators which regulate borrowing and investment. Targets and limits for the prudential indicators for 2024/25 were agreed at Council on 22 February 2024 and borrowing and investment levels have remained within these limits. Performance against the indicators for 2024/25 is set out in Appendix 5.
Recommendations
7. It is recommended that
(i) Cabinet recommend to Council that all variations to the 2024/25 Capital Programme as detailed in Appendix 2 are agreed. (ii) Cabinet recommend to Council the financing of the revised programme set out in this report. (iii) Cabinet confirm to Council that capital expenditure and financing requirements have been revised in line with the amended budget and none of the approved Prudential Indicators set for 2024/25 have been breached.
for the following reason(s)
a) To ensure the optimum use of the Council’s capital resources in 2024/25. b) To accommodate changes to the Council’s in-year capital expenditure plans. c) To ensure performance has been assessed against the approved Prudential Limits.
CONTACT: Clare Tait extension: 3716 APPENDIX 1
Policy Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.