Gateshead Metropolitan Borough Council
Cabinet, Tuesday 15 July 2025 at 10.00am

Capital 1st Quarter Review 2025/26

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 15 July 2025. Below is the council's own wording, with the papers it was decided on.

ItemC38

Resolved

i) That Cabinet recommend to Council that all variations to the 2025/26 Capital Programme as detailed in Appendix 2 be agreed. ii) That Cabinet recommend to Council the financing of the revised programme as set out in the report. iii) That Cabinet confirm to Council that capital expenditure and financing requirements have been revised in line with the amended budget and that none of the approved Prudential Indicators set for 2025/26 have been breached. The above decision was made for the following reasons: a) To ensure the optimum use of the Council’s capital resources in 2025/26. b) To accommodate changes to the Council’s in-year capital expenditure plans. c) To ensure performance has been assessed against the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report sets out the latest position on the 2025/26 Capital Programme and Prudential Indicators at the end of the first quarter to 30 June 2025. The report assesses reasons for the variances from the approved programme and details the proposed financing of the Capital Programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the Capital Programme and the monitoring of performance against the statutory Prudential Indicators.

Background

2. The original budget for the capital programme for 2025/26, as agreed by Council on 18 February 2025, totalled £157.2m. The first quarter review now projects the year-end expenditure to be £145.5m, £96.6m General Fund and £48.9m HRA.

3. The proposed variance in the capital programme at the first quarter comprises of the following movements: £m Slippage of planned capital expenditure from 2024/25 4.998 Other movements 17.042 Re-profiling of capital expenditure to future years (33.738) Total Variance (11.698)

4. A total of £4.998m of slippage was identified in 2024/25 on several key schemes, which were carried forward into 2025/26 including:

• £0.704m Strategic Maintenance • £1.900m Loan to Gateshead Energy Company (GECo) for District Energy Extension Heat Networks Investment Project (HNIP) • £1.025m Communal Mechanical and Electrical Works HRA

5. Planned investment has been re-profiled to/from future financial years on several schemes, amounting to an overall reduction of £33.738m in 2025/26. The schemes which have been re-profiled include the following:

Reprofiling of Capital Expenditure into Future Years

• (£13.000m) Gateshead Quays • (£8.669m) Loan to GECo – Old Fold/Nest Housing Extension – scheme paused • (£2.883m) City Regional Sustainable Transport Settlement • (£1.600m) Prince Consort Road • (£1.500m) Depot Review • (£1.192m) Loan to GECo - Green Heat Network Fund • (£1.035m) The Angel • (£0.767m) Riverside Park • (£0.550m) Specialist Therapeutic Children’s Home • (£0.777m) School SEN High Needs Funding • (£1.677m) Regeneration and Demolition HRA

Reprofiling of Capital Expenditure into Current Year

• £9.306m Local Transport Plan – Integrated Transport – includes £7m Bus Service Improvement Plan (BSIP) to be spent by 31 March 2026 • £3.953m Transforming Cities – tranche 2 launched • £1.022m School Condition Fund • £0.720m Local Transport Plan – Planned Maintenance

Capital Expenditure added to the current year

• £1.128m Old Town Hall Quarter

Proposal

6. The report identifies planned capital expenditure of £145.5m for the 2025/26 financial year. The expected resources required to fund the Capital Programme are as follows:

£m Borrowing 50.066 Projected Capital Receipts 1.326 Capital Grants and Contributions 45.267 Major Repairs Reserve (HRA) 20.886 Capital Grants and Contributions (HRA) 0.420 Right to Buy Receipts (HRA) 27.568 Total Capital Programme 145.533

7. CIPFA’s Prudential Code advises the regular monitoring of performance against the prudential indicators which regulate borrowing and investment. Targets and limits for the prudential indicators for 2025/26 were agreed at Council on 18 February 2025 and borrowing and investment levels have remained within these limits. Performance against the indicators for 2025/26 is set out in Appendix 5. Recommendations

8. It is recommended that

(i) Cabinet recommend to Council that all variations to the 2025/26 Capital Programme as detailed in Appendix 2 are agreed. (ii) Cabinet recommend to Council the financing of the revised programme set out in this report. (iii) Cabinet confirm to Council that capital expenditure and financing requirements have been revised in line with the amended budget and none of the approved Prudential Indicators set for 2025/26 have been breached.

for the following reason(s)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital 1st Quarter Review 2025/26Report 459 KB DownloadRead as text

At this meeting

Whole meeting
C27MinutesOn the agenda C29Continuing our work with Citizen’s Advice GatesheadApproved C30Updated Private Sector Housing Housing and Planning Act 2016 Enforcement PolicyApproved C31Mandatory Licensing of Houses in Multiple Occupation PolicyApproved C32Veterans Capital Housing Funding bidApproved C33Gateshead Local Environment & Streetscene Approach, Priorities and Delivery Plan 2025 - 2028Approved C34Construction Services No Access and Decant PolicyApproved C35Allocation Policy UpdatesApproved C36Treasury Annual Report 2024/25Decided C37Capital Programme and Prudential Indicators 2024/25 – Year End OutturnNoted
C38Capital 1st Quarter Review 2025/26This decision
C39Housing Revenue Account Budget – First Quarter Review 2025/26Decided C40Revenue Outturn 2024/25Agreed C41Revenue Budget - First Quarter Review 2025/26Agreed C42Proposal to Refresh the Council’s Corporate ValuesAgreed C43Submission Draft MetroGreen Area Action Plan (Regulation 19) for ConsultationApproved C44Climate Emergency UpdateDecided C45Performance Management and Improvement Framework – Year End Performance ReportApproved C46Approval of Schemes, Estimates, Tenders and Consents during the Summer Recess 2024Approved C47Statement of Licensing Policy 2026 - 2031Approved C48Nomination of Local Authority Governors for Maintained SchoolsApproved C49Exclusion of the Press and PublicDecided C50Renewal of Leases for Baltic Flour Mill Visual Arts Trust and North Music Trust (Glasshouse)Private C51Warm Homes Social Housing FundPrivate C52Contract awards to Gateshead Energy Company for Town Centre heat network extensionPrivate

Who was there

10 of 17 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, in attendance
BF
Brian FaganOfficer, expected

All 17 on the meeting page

On this subject at Gateshead

Search all
  1. Capital 1st Quarter Review 2025/26This decision
  2. Capital Programme and Prudential Indicators - First Quarter Review 2026-27Approved
  3. Capital Programme and Prudential Indicators – First Quarter Review 2026-27Approved
  4. Capital Programme and Prudential Indicators – Third Quarter Review 2025/26Agreed
  5. Capital Programme and Prudential Indicators - Second Quarter ReviewAgreed
  6. Capital Programme and Prudential Indicators - Second Quarter ReviewAgreed

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies