CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gateshead Metropolitan Borough Council
Planning and Development Committee, Wednesday 1 October 2025 at 6.00pm

Enforcement Action

Noted Planning 1 paper

AI summaryGateshead Planning and Development Committee noted a progress report on 11 enforcement cases. Key updates include ongoing Crown Court proceedings for the Jack and Jo's Nursery case and demolition plans on hold for the former Kwik Save in Felling.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInformation on 11 enforcement cases was noted by the committee
MoneyNilNo financial implications reported
What happens nextCourt hearings and monitoringCases proceeding through courts and compliance checks
Who it affects20 wards across GatesheadAll 20 wards of the borough listed as affected

What was decided

The committee noted the information in the report on progress of enforcement action previously authorised. Report P3

Why

The report was provided to advise the committee of the progress of enforcement action previously authorised by the committee. Report P1

What happens next

A Case Management Hearing at Newcastle Crown Court is scheduled for 5 November 2025 in the prosecution of three defendants for non compliance with the Jack and Jo's Nursery enforcement notice. Report P86

A contractor has been appointed to clear fly tipped material from the former MGM Engineering Factory site in default, and a case file has been submitted to legal for prosecution for non compliance with a Community Protection Notice. Report P114

Officers will continue to monitor compliance with enforcement notices at 9 Claypath, Gateshead, the Borough Arms on Bensham Road, and the former Kwik Save site in Felling. Report P70, P141, P144

Options considered

  • Chosen: Note the report on enforcement action progress. Recommended by the Service Director, Climate Change, Compliance, Planning and Transport Report P3

Implications

  • Financial: No financial implications were identified. Report P5
  • Risk: No risk management implications were identified. Report P7
  • Staffing: No human resources implications were identified. Report P9
  • Equalities: No equality and diversity implications were identified. Report P11
  • Other: No crime and disorder implications were identified. Report P13
  • Climate: No sustainability implications were identified. Report P15
  • Legal: The Human Rights Act states a person is entitled to the peaceful enjoyment of his possessions, but this does not impair the right of the state to enforce laws to control the use of property and land in accordance with the general interest. Report P17

Who and where

  • All 20 wards of Gateshead Metropolitan Borough Council, including Birtley, Blaydon, Bridges, Chopwell and Rowlands Gill, and 16 others Report P19
  • Owners and operators of 11 sites under active enforcement action Report P21, P54, P70, P87, P94, P107, P114, P123, P131, P141, P144
  • Residents neighbouring the former Kwik Save site on Felling High Street, affected by anti social behaviour, arson and fly tipping Report P54
  • Local residents engaging with the Blaydon Quarry Liaison Group Report P48, P50

Timeline

  • 17 September 2025: Current status update across all 11 enforcement cases Report P21, P54, P70, P87, P94, P107, P114, P123, P131, P141, P144
  • 19 September 2025: Compliance deadline for the balcony enforcement notice at 9 Claypath, Gateshead Report P141
  • 23 October 2025: Compliance deadline for the enforcement notice at The Borough Arms, 82 Bensham Road Report P144
  • 5 November 2025: Further Case Management Hearing at Newcastle Crown Court for the Jack and Jo's Nursery prosecution Report P86
  • 26 April 2027: Trial date at Newcastle Crown Court for two defendants in the Jack and Jo's Nursery case Report P83

Plain English for the jargon

  • CPN: Community Protection Notice, served on a person causing ongoing nuisance or harm, requiring action to stop it
  • DOC: Discharge of Condition, a planning application to seek approval for details required by a planning condition
  • PINS: Planning Inspectorate, the government body that determines planning appeals
  • TPO: Tree Preservation Order, which protects specific trees from being cut down or damaged
  • TWFRS: Tyne and Wear Fire and Rescue Service
  • ASB: Anti social behaviour
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPD42

Resolved

i. That the information be noted.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Planning and Development Committee

Purpose of the report

1. To advise the Committee of the progress of enforcement action previously authorised by the Committee.

Background

2. The properties, which are the subject of enforcement action and their current status, are set out in Appendix 2.

Recommendation

3. It is recommended that the Committee note the report.

Contact: Elaine Rudman Ext: 3911 APPENDIX 1

Financial implications

Nil.

2. RISK MANAGEMENT IMPLICATIONS

Nil.

3. HUMAN RESOURCES IMPLICATIONS

Nil.

4. EQUALITY AND DIVERSITY IMPLICATIONS

Nil

5. CRIME AND DISORDER IMPLICATIONS

Nil.

6. SUSTAINABILITY IMPLICATIONS

Nil.

7. HUMAN RIGHTS IMPLICATIONS

The Human Rights Act states a person is entitled to the peaceful enjoyment of his possessions. However, this does not impair the right of the state to enforce such laws, as it deems necessary to control the use of property and land in accordance with the general interest.

8. WARD IMPLICATIONS

Birtley, Blaydon, Bridges, Chopwell and Rowlands Gill, Chowdene, Crawcrook & Greenside, Deckham, Dunston and Teams, Dunston Hill and Whickham East, Felling, High Fell, Lamesley, Lobley Hill and Bensham, Low Fell, Pelaw & Heworth, Ryton, Crookhill and Stella, Saltwell, Wardley & Leam Lane, Whickham North, Whickham South and Sunniside, Windy Nook and Whitehills, Winlaton and High Spen.

9. BACKGROUND INFORMATION

Nil. APPENDIX 2 Item Site Ward Alleged Breach of Date Approval Date Served Date Notice End of Case History Current Update Number Planning Control given for comes into Compliance Enforcement Force Period Action 1. Blaydon Quarry Crawcrook Breach of Planning 22nd May 24th May 28th June 28th Blaydon Quarry is in breach of several 17.09.2025 – Nothing to update Lead Road, and Conditions 2019 2019 2019 December planning conditions. this month. Consultants are Gateshead Greenside Condition 23 and 2019 – chasing outstanding information Condition 24 Condition 23 A Notice has been served in relation to required to be able to submit DOC condition 23 to require installation of a applications in relation to ecology, 28 October drainage system. The Council has designed drainage and landscaping. 2019 – an acceptable scheme to be installed in the Condition 24 interests of surface water drainage and to enable the safe and successful restoration of the site.

A site visit was undertaken on the 4th June 2019, where drainage works had commenced. Officers are working closely with the Operator of the quarry to ensure compliance.

A discharge of condition application has been submitted in relation to condition 23 for the Council to assess.

An appeal has been submitted in relation to the enforcement notice.

A Notice has been served in relation to condition 24 to require installation of the previously approved drainage system on the southern boundary, in the interests of surface water drainage and to enable the safe and successful restoration of the site.

A discharge of condition application has been submitted in relation to condition 24 for the Council to assess.

An appeal has been submitted in relation to the enforcement notice.

Wardell Armstrong on behalf of the Operator has withdrawn the Enforcement Appeal.

February 2023 - Development management have engaged a minerals and landfill specialist consultant to consider the current planning status of this development and determine an appropriate course of action should further enforcement activity be required.

04.05.2023 – Site meeting took place with with Item Site Ward Alleged Breach of Date Approval Date Served Date Notice End of Case History Current Update Number Planning Control given for comes into Compliance Enforcement Force Period Action owner, Environment Agency, Planning, Enforcement and consultant on 03.05.23.

Agreed on action that is required by owner to ensure compliance and required timescales.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enforcement ActionReport 200 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
JT
Councillor Judith TurnerChair, present
KW
Councillor Keith WoodVice-Chair, present
VA
Councillor Vicky AndersonCommittee Member, apologies
DB
Councillor Dot BurnettCommittee Member, present
LC
Councillor Lynne CaffreyCommittee Member, present
SD
Councillor Sonya DickieCommittee Member, present
PE
Councillor Paul ElliottCommittee Member, apologies
AG
Councillor Alex GeddesCommittee Member, apologies
TG
Councillor Tom GrahamCommittee Member, apologies
HK
Councillor Hugh KellyCommittee Member, present
KM
Councillor Kathleen McCartneyCommittee Member, present
EM
Councillor Eileen McMasterCommittee Member, present

All 21 on the meeting page

On this subject at Gateshead

Search all
  1. Enforcement ActionThis decision
  2. Enforcement ActionNoted
  3. Enforcement ActionNoted
  4. Enforcement ActionNoted
  5. Enforcement ActionNoted
  6. Enforcement ActionNoted

More from Gateshead Planning and Development Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Planning Applicationsi) That the full planning applications and outline applications specified in the appendix to these minutes be granted... Refused Open
9 Sep 2026 No.1 - Alexandra Guest House, 377 Alexandra Road, Gateshead, NE8 4HYThat permission be GRANTED, subject to the following conditions and the addition of an Operational and Management Pla... Approved Open
9 Sep 2026 No.2 - St Cuthberts Clearance Area Land Between Askew RoadThat planning permission is GRANTED subject to the following conditions and that the Service Director of Climate Chan... Approved Open
9 Sep 2026 No.3 - Discover Leisure PLC,Portobello Road, Birtley, DH3 2SNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open
9 Sep 2026 No.4 - 16 Langdale Road, Gateshead, NE9 5RNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies