Enforcement Action

Noted Planning 1 paper

AI summaryGateshead Planning and Development Committee noted an enforcement progress report covering 11 sites. Key cases include the ongoing prosecution of Jack and Jo's Nursery owners, restoration at Blaydon Quarry, and the closure of Daveys Breakfast takeaway.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new enforcement actions authorised
MoneyNot stated
What happens nextMonitoring and court cases continueTrial set for 26 April 2027
Who it affects11 enforcement sitesAcross multiple Gateshead wards

What was decided

The Committee noted the enforcement action progress report covering 11 sites. Report P3

No new enforcement decisions or authorisations were made at this meeting.

Why

The report is a routine update on the progress of enforcement action previously authorised by the Committee. Report P1, P2

The report sets out current status, ongoing works and recent updates on each case in Appendix 2. Report P2

What happens next

Officers will continue monitoring compliance, processing discharge of condition applications, and pursuing appeals and prosecutions where required. Report P54, P55, P79, P81, P124, P129

A jury trial is scheduled at Newcastle Crown Court on 26 April 2027 for Joanne and Moira Stanton in the Jack and Jo's Nursery café case. Report P85

The Council is preparing to carry out works in default at 89/91 and 93/95 Woodbine Street under section 219 of the Town and Country Planning Act 1990. Report P158

Options considered

  • Chosen: Note the report. Recommended by the Service Director as a routine progress update. Report P3

Implications

  • Legal: Several cases involve live court proceedings, including a jury trial at Newcastle Crown Court and prosecutions for non-compliance with Community Protection Notices. Report P85, P88, P133
  • Legal: Appeals to the Planning Inspectorate are pending for 3 Shield Avenue, The Borough Arms and the 101 Bewick Road front extension. Report P148, P149, P160
  • Financial: No financial implications identified in the report. Report P5
  • Risk: No risk management implications identified in the report. Report P7
  • Staffing: No human resources implications identified in the report. Report P9
  • Equalities: No equality and diversity implications identified in the report. Report P11

Who and where

  • Owners and operators of 11 enforcement sites across Gateshead Report P19, P21
  • Residents and businesses near the Blaydon Quarry, Felling, and former MGM Engineering Factory sites Report P47, P57, P68, P125
  • Ward councillors and the MP for Blaydon, who have been invited to liaison group meetings Report P45

Timeline

  • 12.03.2026: Compliance deadline for the 157 Bewick Road hard surface enforcement notice. Report P155
  • 28.07.2026: Compliance deadline for the 101 Bewick Road front extension enforcement notice. Report P159
  • End of Summer 2026: Expected completion of soil imports to Blaydon Quarry. Report P54
  • Spring 2026: Grass planting scheduled on the majority of the Blaydon Quarry site. Report P54
  • Autumn 2026: Grass planting scheduled to the northern edge of Blaydon Quarry. Report P54
  • 26 April 2027: Jury trial at Newcastle Crown Court for Joanne and Moira Stanton in the Jack and Jo's Nursery café case. Report P85

Plain English for the jargon

  • PINS: Planning Inspectorate, the body that decides planning appeals.
  • CPN: Community Protection Notice, served on a person to stop anti-social behaviour or site impacts.
  • DOC: Discharge of Condition application, used to seek approval for matters required by a planning condition.
  • s215 notice: Notice under section 215 of the Town and Country Planning Act 1990 requiring a landowner to tidy up land harming local amenity.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPD88

Resolved

i. That the information be noted.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Planning and Development Committee

Purpose of the report

1. To advise the Committee of the progress of enforcement action previously authorised by the Committee.

Background

2. The properties, which are the subject of enforcement action and their status, are set out in Appendix 2.

Recommendation

3. It is recommended that the Committee note the report.

Contact: Elaine Rudman Ext: 3911 APPENDIX 1

Financial implications

Nil.

2. RISK MANAGEMENT IMPLICATIONS

Nil.

3. HUMAN RESOURCES IMPLICATIONS

Nil.

4. EQUALITY AND DIVERSITY IMPLICATIONS

Nil

5. CRIME AND DISORDER IMPLICATIONS

Nil.

6. SUSTAINABILITY IMPLICATIONS

Nil.

7. HUMAN RIGHTS IMPLICATIONS

The Human Rights Act states a person is entitled to the peaceful enjoyment of his possessions. However, this does not impair the right of the state to enforce such laws, as it deems necessary to control the use of property and land in accordance with the general interest.

8. WARD IMPLICATIONS

Birtley, Blaydon, Bridges, Chopwell and Rowlands Gill, Chowdene, Crawcrook & Greenside, Deckham, Dunston and Teams, Dunston Hill and Whickham East, Felling, High Fell, Lamesley, Lobley Hill and Bensham, Low Fell, Pelaw & Heworth, Ryton, Crookhill and Stella, Saltwell, Wardley & Leam Lane, Whickham North, Whickham South and Sunniside, Windy Nook and Whitehills, Winlaton and High Spen.

9. BACKGROUND INFORMATION

Nil. APPENDIX 2 Item Site Ward Alleged Breach of Planning Date Approval Date Served Date Notice End of Case History Current Update Number Control given for comes into Compliance Enforcement Force Period Action 1. Blaydon Quarry Crawcrook Breach of Planning 22nd May 2019 24th May 28th June 2019 28th Blaydon Quarry is in breach of several 11.3.2026 – The landscaping, Lead Road, and Conditions 2019 December planning conditions. drainage and ecology Gateshead Greenside Condition 23 and Condition 2019 – conditions have now been 24 Condition 23 A Notice has been served in relation to discharged. Planning are condition 23 to require installation of a considering information 28 October drainage system. The Council has submitted in relation to 2019 – designed an acceptable scheme to be Condition 20 and 27 of Condition 24 installed in the interests of surface water DC/12/01266/MIWAS drainage and to enable the safe and (overtipping on Cell 1 and successful restoration of the site. working methods used to contour the land surrounding A site visit was undertaken on the 4th June the lagoon in the north east 2019, where drainage works had corner of the site.) commenced. Officers are working closely with the Operator of the quarry to ensure compliance.

A discharge of condition application has been submitted in relation to condition 23 for the Council to assess.

An appeal has been submitted in relation to the enforcement notice.

A Notice has been served in relation to condition 24 to require installation of the previously approved drainage system on the southern boundary, in the interests of surface water drainage and to enable the safe and successful restoration of the site.

A discharge of condition application has been submitted in relation to condition 24 for the Council to assess.

An appeal has been submitted in relation to the enforcement notice.

Wardell Armstrong on behalf of the Operator has withdrawn the Enforcement Appeal.

February 2023 - Development management have engaged a minerals and landfill specialist consultant to consider the current planning status of this development and determine an appropriate course of action should further enforcement activity be required. Item Site Ward Alleged Breach of Planning Date Approval Date Served Date Notice End of Case History Current Update Number Control given for comes into Compliance Enforcement Force Period Action

04.05.2023 – Site meeting took place with with owner, Environment Agency, Planning, Enforcement and consultant on 03.05.23.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enforcement ActionReport 208 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 19 attended
JT
Councillor Judith TurnerChair, present
KW
Councillor Keith WoodVice-Chair, present
VA
Councillor Vicky AndersonCommittee Member, present
DB
Councillor Dot BurnettCommittee Member, present
LC
Councillor Lynne CaffreyCommittee Member, apologies
SD
Councillor Sonya DickieCommittee Member, apologies
PE
Councillor Paul ElliottCommittee Member, present
AG
Councillor Alex GeddesCommittee Member, apologies
HK
Councillor Hugh KellyCommittee Member, present
KM
Councillor Kathleen McCartneyCommittee Member, present
EM
Councillor Eileen McMasterCommittee Member, apologies
JM
Councillor Jonathan MohammedCommittee Member, present

All 19 on the meeting page

On this subject at Gateshead

Search all
  1. Enforcement ActionThis decision
  2. Enforcement ActionNoted
  3. Enforcement ActionNoted
  4. Enforcement ActionNoted
  5. Enforcement ActionNoted
  6. Enforcement ActionNoted

More from Gateshead Planning and Development Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Planning Applicationsi) That the full planning applications and outline applications specified in the appendix to these minutes be granted... Refused Open
9 Sep 2026 No.1 - Alexandra Guest House, 377 Alexandra Road, Gateshead, NE8 4HYThat permission be GRANTED, subject to the following conditions and the addition of an Operational and Management Pla... Approved Open
9 Sep 2026 No.2 - St Cuthberts Clearance Area Land Between Askew RoadThat planning permission is GRANTED subject to the following conditions and that the Service Director of Climate Chan... Approved Open
9 Sep 2026 No.3 - Discover Leisure PLC,Portobello Road, Birtley, DH3 2SNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open
9 Sep 2026 No.4 - 16 Langdale Road, Gateshead, NE9 5RNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies