Planning and Development Committee, Wednesday 15 July 2026 at 6.00pm

No.4 - Gateshead Council Depot, The Court Yard, NE9 5AW

Approved Planning 1 paper

AI summaryGateshead Council Planning and Development Committee grants planning permission to convert Gateshead Council Depot at The Court Yard, NE9 5AW into residential units, subject to 23 conditions covering biodiversity, noise, heritage and construction management.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to 23 planning conditions
MoneyNo financial figures stated in papers
What happens nextDevelopment must start within 3 yearsBiodiversity Gain Plan required before commencement
Who it affectsGateshead Council Depot site, NE9 5AWConversion to residential units

What was decided

Permission was granted for the conversion of the Gateshead Council Depot into residential units, with the Service Director of Climate Change, Compliance, Planning and Transport authorised to amend conditions as necessary. Report P1

The permission is subject to a Biodiversity Gain Plan being approved before the development begins, under Paragraph 13 of Schedule 7A Town and Country Planning Act 1990. Report P2, P65, P66, P67

Development must begin no later than three years from the date of the permission, under section 91 of the Town and Country Planning Act 1990. Report P11, P12

Why

Conditions safeguard hedgehogs, the woodland area to the north, and ensure biodiversity net gain in line with NPPF and policies CS18, MSGP36 and MSGP37. Report P14, P16, P68, P70

Conditions on materials, boundary treatments and the retaining wall are needed to protect the appearance of the existing building, conservation area and heritage assets, in line with policies CS14, CS15, MSGP24 and MSGP25. Report P23, P25

Noise mitigation measures, obscure glazing, restricted construction hours and visibility splays are required to protect living conditions of future and nearby residents, in line with policies CS13, CS14, MSGP15, MSGP17 and MSGP18. Report P34, P37, P47, P50, P64

What happens next

A Biodiversity Gain Plan must be submitted and approved before any development begins, and the development must proceed in line with the BNG Assessment dated January 2026. Report P65, P69, P71

A Demolition and Construction Management Plan must be submitted and approved before any development, including demolition, starts on site. Report P38, P48

Boundary treatment details, visibility splay details, cycle parking details and soft landscaping details must be submitted and approved before any dwelling is occupied, with landscaping maintained for at least 30 years. Report P13, P51, P54, P72, P74

Options considered

  • Chosen: Grant planning permission subject to conditions. Recommended by officers as the application complies with local plan policies subject to conditions Report P1

Implications

  • Environment and climate: Hedgehog protection measures and biodiversity net gain of at least 30 years maintenance are required, with a Biodiversity Gain Plan a statutory pre-commencement requirement. Report P2, P13, P65, P67, P74
  • Legal: Permission engages section 91 of the Town and Country Planning Act 1990 (three year commencement) and Schedule 7A (biodiversity gain). Report P2, P12, P67
  • Equalities: Windows serving bathrooms, en-suites and WCs must be glazed with obscure glass to protect privacy of existing and future residents. Report P35, P37
  • Risk: Construction noise, dust, vibration and surface water run-off are controlled through a required Demolition and Construction Management Plan and restricted working hours. Report P33, P38, P46

Who and where

  • Future occupiers of the new residential units, including units 1, 4, 5 and 7 Report P24, P29, P55
  • Residents of neighbouring properties on Durham Road and surrounding streets Report P34, P47, P50
  • Hedgehogs and the woodland area to the north of the built development Report P13, P14
  • Conservation area and heritage assets including the existing depot building and signage structure Report P23, P25, P27, P30

Timeline

  • Application form received 15.10.2025: Application submitted to the council Report P18
  • BNG Assessment dated January 2026: Biodiversity Net Gain Assessment prepared Report P69, P72
  • Design and Access Statement dated April 2026, Rev C: Design and Access Statement submitted Report P8
  • Within 3 years of permission: Development must begin, otherwise permission expires Report P11, P12
  • At least 30 years after planting: Soft landscaping and habitat creation must be maintained Report P74
  • Noise Impact Assessment dated 23 April 2026: Noise Impact Assessment (LAE1365.1) prepared Report P59

Plain English for the jargon

  • Biodiversity Net Gain (BNG): A measurable improvement in biodiversity for a site after development, required by law under Schedule 7A of the Town and Country Planning Act 1990.
  • Biodiversity Gain Plan: A plan that must be approved by the local planning authority before development begins, showing how biodiversity net gain will be achieved and maintained.
  • LAeq: Equivalent continuous sound level, the average noise level over a stated period of time, used to set internal noise standards in dwellings.
  • LAmax: The maximum sound level recorded during a measurement period, used alongside LAeq for night-time noise standards.
  • Visibility splay: An unobstructed sight line at a junction or parking space needed for pedestrian and driver safety, here set at 2m x 2m.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPD113

Resolved

That permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Compliance, Planning and Transport be authorised to add, vary and amend the planning conditions as necessary. 1 Unless otherwise required by condition, the development shall be carried out in complete accordance with the approved plan(s) as detailed below - LOCATION PLAN/SITE PLAN UN-007 PL-01 REV C LOCATION PLAN/COLOURED SITE PLAN UN-007 PL-01-1 REV C LOCATION PLAN/B&W SITE PLAN UN-007 PL-01-2 REV B BOUNDARY AND TREATMENTS PLAN UN-007 PL-06 REV D REFUSE TRACKING PLAN UN-007 PL-09 REV D ELEVATIONS UN-007 PL-02 REV B PRPOSED PLANS UN-007 PL-03 REV A CONVERSION PROPOSED PLANS AND ELEVATIONS UN-007 PL-05 REV A NATIONAL SPACE STANDARDS UN-007 PL-10 REV A SITE CROSS SECTIONS S3Di_047 PL-06-1 Design and Access Statement APRIL 2026 REV C Any material change to the approved plans will require a formal planning application to vary this condition and any non-material change to the plans will require the submission of details and the agreement in writing by the Local Planning Authority prior to any non-material change being made. 2 The development to which this permission relates must be commenced not later than 3 years from the date of this permission. 3 Notwithstanding the approved plans, no new boundary treatment shall be installed until final details of boundary treatment demonstrating measures for hedgehog and protection of the woodland area to the north of the built development have been submitted to and approved in writing by the Local Planning Authority. 4 The details approved under condition 3 shall be implemented in full accordance with the approved details before any residential unit hereby approved is occupied. 5 All new external surfaces shall be constructed with the materials specified in the following documents: APPLICATION FORM RECEIVED 15.10.2025 ELEVATIONS UN-007 PL-02 REV B BOUNDARY AND TREATMENTS PLAN UN-007 PL-06 REV D External natural stone and slate shall be re-used/reclaimed from those on site, and where new materials are brought onto the site these would need to match those existing on site. Roof lights shall be conservation style. Notwithstanding the approved plans, the retaining wall running north to south at the eastern part of the site shall be retained in situ and remain at 2.5m high. Where it ... view the full minutes text for item PD113
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Planning and Development Committee

REPORT NO 4

Committee Report

Application No: DC/25/01070/FUL Case Officer Joanne Munton Date Application Valid 15 October 2025 Applicant [name removed]: Gateshead Council Depot The Court Yard Durham Road Gateshead NE9 5AW

Ward: Low Fell Proposal: Conversion and extension of existing building at western part of site to provide 2 dwellings, demolition of existing buildings at eastern part of site and erection of 6no. 2.5 storey dwellings, including associated parking, tree removal, replacement planting and removal of existing signage structure at south eastern part of site (additional information 17.11.2025, amended 25.11.2025, 27.04.2026 and 19.05.2026) (Description amended 26.05.2026) Recommendation: GRANT Application Type Full Application

1. The Application:

1. 1 DESCRIPTION OF SITE

1. 2 The site is located west of Durham Road in Low Fell and within the wider grounds of Whinney House (historically part of the estate land), the specific site itself being located south east of Whinney House.

1. 3 There is a collection of buildings on the application site broadly creating two U shapes facing each other and forming a courtyard in the centre, and whilst now vacant, was formerly used as the Gateshead Outdoor Activity Centre.

1. 4 The western block has a distinctive central tower and the northern and southern ends are higher than the central part. The eastern block comprises an L shaped stone building/pair of buildings and a more modern brick single storey building with four large double timber doors.

1. 5 Within the former estate grounds, Whinney House itself has been converted into flats, there are other estate buildings occupied as dwellings, and there is also more modern development within the grounds including a care home and a residential block of flats. To the west of the site is a modern gated cul de sac of dwellings at Mulberry Park and to the north of the site is the former Gatehouse/Lodge, which is a dwelling.

1. 6 The application site is accessed by the same drive from Durham Road that serves all of the above.

1. 7 Durham Road is to the east of the site, and there are mature trees and landscaping between the main road and the existing buildings, and these buildings and courtyard are at a lower level (approximately 2m) to that of the footpaths and carriageway at Durham Road.

1. 8 To the south of the site are two residential properties, accessed separately from Durham Road.

1. 9 There is also an existing signage structure on site towards the south east near to the boundary with Durham Road. This sign has been traditionally associated with the 'Progressive Players' based at the Little Theatre further north on Saltwell View.

1. 10 The site is within Saltwell Conservation Area and is identified as a curtilage heritage asset to Whinney House and is therefore treated as if listed grade II.

1. 11 DESCRIPTION OF APPLICATION

1. 12 The application proposes the conversion and extension of the existing building at western part of the site to provide 2no. dwellings. Unit 1 would have 2no. bedrooms and Unit 2 would have 4no. bedrooms, with the two storey extension to Unit 2 projecting to the south.

1. 13 The existing buildings at the eastern part of site are proposed to be demolished and replaced with and 6no. 2 storey dwellings (with 2 dwellings having rooms in the roof), including built development extending further north.

1. 14 Units 3 and 8 would have 2no. bedrooms 1. 15 Units 4 and 6 would have 3no. bedrooms 1. 16 Units 5 and 7 would have 4no. bedrooms (with rooms in the roof space)

1. 17 In total, the proposed scheme would deliver 8 dwellings:

1. 18 3x dwellings with 2no. bedrooms 1. 19 2x dwellings with 3no. bedrooms 1. 20 3x dwellings with 4no. bedrooms

1. 21 Materials for the new build elements are proposed to be:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
No.4: Gateshead Council Depot, The Court Yard, NE9 5AWReport 286 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 22 attended
RJ
Councillor Ronnie JacksonChair, present
NC
Councillor Neil CarpenterVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
AB
Councillor Arthur BoylinCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, apologies
LC
Councillor Lynne CaffreyCommittee Member, present
MH
Councillor Melissa HarkerCommittee Member, present
CH
Councillor Craig HeathcoteCommittee Member, present
ML
Councillor Michael LamportCommittee Member, present
KM
Councillor Kathleen McCartneyCommittee Member, present
RM
Councillor Roger MarajCommittee Member, in attendance
PM
Councillor Peter MaughanCommittee Member, present

All 22 on the meeting page

On this subject at Gateshead

Search all
  1. No.4 - Gateshead Council Depot, The Court Yard, NE9 5AWThis decision
  2. Surplus Declaration of the Saltwell Park Bottom Depot, Saltwell Road South, GatesheadDecided

More from Gateshead Planning and Development Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Planning Applicationsi) That the full planning applications and outline applications specified in the appendix to these minutes be granted... Refused Open
9 Sep 2026 No.1 - Alexandra Guest House, 377 Alexandra Road, Gateshead, NE8 4HYThat permission be GRANTED, subject to the following conditions and the addition of an Operational and Management Pla... Approved Open
9 Sep 2026 No.2 - St Cuthberts Clearance Area Land Between Askew RoadThat planning permission is GRANTED subject to the following conditions and that the Service Director of Climate Chan... Approved Open
9 Sep 2026 No.3 - Discover Leisure PLC,Portobello Road, Birtley, DH3 2SNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open
9 Sep 2026 No.4 - 16 Langdale Road, Gateshead, NE9 5RNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open