Planning Enforcement Appeals

Noted Planning 1 paper

AI summaryGateshead Planning and Development Committee noted an update on planning enforcement appeals, with no new appeals or decisions since the last meeting. Two outstanding appeals at 82 Bensham Road, the former Borough Arms, are proceeding via written representations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the enforcement appeals update report
MoneyNilNo financial implications identified
What happens nextRepresentations by 23 September 2025Deadline for written representations to Planning Inspectorate on the two outstanding appeals
Who it affectsNot stated

What was decided

The Committee noted the report on planning enforcement appeals. Report P5

Why

No new appeals had been received and no appeal decisions had been issued since the previous update to Committee, so the report was for information only. Report P2, P3

What happens next

Two outstanding appeals at 82 Bensham Road will continue through the written representations procedure, with the Planning Inspectorate to receive any representations no later than 23 September 2025. Report P26

Options considered

  • Chosen: Note the report. Recommended to Committee as the report was for information Report P5, P1

Implications

  • Legal: Two human rights issues are engaged: the right of an individual to a fair trial and the right to peaceful enjoyment of property. Report P19
  • Legal: The planning enforcement appeal regime is administered by the Planning Inspectorate and is outside the Council's control. Report P20
  • Other: Two appeals have been lodged against enforcement action at the same site, the former Borough Arms at 82 Bensham Road, Gateshead, NE8 1PS. Report P26
  • Financial: No financial implications arising from the report. Report P7
  • Risk: No risk management implications identified. Report P9
  • Equalities: No equality and diversity implications identified. Report P13
  • Climate: No sustainability implications identified. Report P17

Who and where

  • Residents of Lobley Hill and Bensham ward Report P22
  • Residents of Bridges ward Report P22
  • Residents of Whickham North ward Report P22
  • YGNH, complainant regarding 82 Bensham Road, Gateshead, NE8 1PS Report P26
  • Persimmon Homes (North East) Limited, party to appeal regarding land at and adjacent to 82 Bensham Road, Gateshead, NE8 1PS Report P26
  • The Planning Inspectorate, which is hearing the two outstanding appeals Report P20, P26

Timeline

  • August 2025: Planning Inspectorate confirmed start date of both appeals at 82 Bensham Road (former Borough Arms) Report P26
  • 23 September 2025: Deadline for any representations to be received by the Planning Inspectorate on the two outstanding appeals Report P26
  • 2026-07-15: Planning and Development Committee meeting at which the report was noted

Plain English for the jargon

  • Section 174(2) of the 1990 Act: Section 174(2) of the Town and Country Planning Act 1990, which sets out the statutory grounds on which a person may appeal against an enforcement notice. Grounds (a) and (f) relate to matters including the validity of the notice and the steps required to remedy the breach.
  • Written representations: A planning appeal procedure decided on the basis of written submissions rather than at a public hearing or inquiry.
  • Planning Inspectorate: The Government agency that administers the planning appeal process on behalf of the Secretary of State.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPD117

Resolved

i. That the information be noted.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Planning and Development Committee

Purpose of the report

1. To advise the Committee of new appeals against enforcement action received and to report the decisions of the Planning Inspectorate or magistrates received during the report period.

Background

2. There have been no appeals received since an update was last provided to committee.

3. There have been no appeal decisions received since the last Committee.

4. Details of outstanding appeals can be found in Appendix 2.

Recommendation

5. It is recommended that the Committee note the report.

Contact: Elaine Rudman Ext: 3911 APPENDIX 1

Financial implications

Nil

2. RISK MANAGEMENT IMPLICATIONS

Nil

3. HUMAN RESOURCES IMPLICATIONS

Nil

4. EQUALITY AND DIVERSITY IMPLICATIONS

Nil

5. CRIME AND DISORDER IMPLICATIONS

Nil

6. SUSTAINABILITY IMPLICATIONS

Nil

7. HUMAN RIGHTS IMPLICATIONS

The subject matter of the report touches upon two human rights issues: the right of an individual to a fair trial and the right to peaceful enjoyment of property

As far as the first issue is concerned the planning enforcement appeal regime is outside of the Council’s control being administered by the Planning Inspectorate.

8. WARD IMPLICATIONS

Lobley Hill and Bensham Bridges Whickham North,

9. BACKGROUND INFORMATION

Appeal decision APP/H4505/C/24/3353466 APPENDIX 2

Outstanding Enforcement Appeal Cases

YGNH A complaint was received in The appeal will proceed on 82 Bensham Road, relation to alleged grounds (a) and (f) as set GATESHEAD, NE8 1PS unauthorised development out at Section 174(2) of the Known locally as the at the site. Following a site 1990 Act. former Borough Arms visit a number of breaches of planning control were The planning inspectorate identified and subsequently has confirmed the start assessed by Development date of the appeal as 12 Management. It is August 2025. The appeal considered that that some is to be heard through the elements of the written representation’s unauthorised development procedure. cause less than substantial harm to a designated The appeal reference is heritage asset and that the APP/H4505/C/25/3369930. development is not in accordance with the Any representations are to National Planning Policy be received by the Framework and policies planning inspector no later CS15 and MSGP25 of the than 23 September 2025. Local Plan for Gateshead Guidance on making representations can be found in the following link Taking part in a planning, listed building or enforcement appeal - GOV.UK (www.gov.uk) Persimmon Homes A complaint was received in The appeal will proceed on (North East) Limited relation to alleged grounds (a) and (f) as set Land at and adjacent to unauthorised development out at Section 174(2) of the 82 Bensham Road, at the site. Following a site 1990 Act. Gateshead, NE8 1PS visit a number of breaches Known locally as the of planning control were The planning inspectorate former Borough Arms identified and subsequently has confirmed the start assessed by Development date of the appeal as 12 Management. It is August 2025. The appeal considered that that some is to be heard through the elements of the written representation’s unauthorised development procedure. cause less than substantial harm to a designated The appeal reference is heritage asset and that the APP/H4505/C/25/3370021. development is not in accordance with the Any representations are to National Planning Policy be received by the Framework and policies planning inspector no later CS15 and MSGP25 of the than 23 September 2025. Local Plan for Gateshead Guidance on making representations can be found in the following link Taking part in a planning, listed building or enforcement appeal - GOV.UK (www.gov.uk)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning Enforcement AppealsReport 100 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 22 attended
RJ
Councillor Ronnie JacksonChair, present
NC
Councillor Neil CarpenterVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
AB
Councillor Arthur BoylinCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, apologies
LC
Councillor Lynne CaffreyCommittee Member, present
MH
Councillor Melissa HarkerCommittee Member, present
CH
Councillor Craig HeathcoteCommittee Member, present
ML
Councillor Michael LamportCommittee Member, present
KM
Councillor Kathleen McCartneyCommittee Member, present
RM
Councillor Roger MarajCommittee Member, in attendance
PM
Councillor Peter MaughanCommittee Member, present

All 22 on the meeting page

On this subject at Gateshead

Search all
  1. Planning Enforcement AppealsThis decision
  2. Planning Enforcement AppealsNoted
  3. Planning Enforcement AppealsNoted
  4. Planning Enforcement AppealsNoted
  5. Planning Enforcement AppealsNoted
  6. Planning Enforcement AppealsNoted

More from Gateshead Planning and Development Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Planning Applicationsi) That the full planning applications and outline applications specified in the appendix to these minutes be granted... Refused Open
9 Sep 2026 No.1 - Alexandra Guest House, 377 Alexandra Road, Gateshead, NE8 4HYThat permission be GRANTED, subject to the following conditions and the addition of an Operational and Management Pla... Approved Open
9 Sep 2026 No.2 - St Cuthberts Clearance Area Land Between Askew RoadThat planning permission is GRANTED subject to the following conditions and that the Service Director of Climate Chan... Approved Open
9 Sep 2026 No.3 - Discover Leisure PLC,Portobello Road, Birtley, DH3 2SNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open
9 Sep 2026 No.4 - 16 Langdale Road, Gateshead, NE9 5RNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open