RESOLVED to: Grant Planning Permission subject to the conditions below and the applicant giving a unilateral undertaking under s106 of the Town and Country Planning Act 1990 to the Borough Council in relation to (1) a Traffic Regulation Order associated with speed limits on Arnold Lane, (2) details of wheel washing and means of access and routes of construction traffic, (3) details of proposed new setts and barn owl nest boxes, details of translocation of Open Mosaic Habitat and badgers to the Gedling Country Park, (4) details of mitigation measures to compensate for the loss of land at Carlton Le Willows Academy and Woodthorpe (St Marks) Scout Group, (5) details of a travel plan co-ordinator and travel plan monitoring in relation to the operational phase of ... view the full minutes text for item 243.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
Proposal: Construction of a 3.8km long road linking A612 Burton Road and B684 Mapperley Plains Road (Gedling Access Road).
Revised Recommendation
As a consequence of drafting the conditions recommended to be attached to the above application should members be minded to approve, it was considered that a number of items should be included within the recommended s106 agreement. These items relate to the requirement for a travel plan co-ordinator and travel plan monitoring and for post operation traffic monitoring and a mechanism for implementing any subsequent mitigation measures following traffic monitoring. Given the nature of these items it is considered that they would be best secured through a s106 agreement rather than through conditions.
The revised recommendation is:
Recommendation: Grant Planning Permission subject to the conditions set out below and subject to the satisfactory completion of a s106 agreement with the Borough Council and other interested parties in relation to; (1) a Traffic Regulation Order associated with speed limits on Arnold Lane, (2) details of wheel washing and means of access and routes of construction traffic, (3) details of proposed new setts and barn owl nest boxes, details of translocation of Open Mosaic Habitat and badgers to the Gedling Country Park, (4) details of mitigation measures to compensate for the loss of land at Carlton Le Willows Academy and Woodthorpe (St Marks) Scout Group, (5) details of a travel plan co-ordinator and travel plan monitoring in relation to the operational phase of the GAR, (6) details for monitoring of traffic conditions during the operational phase of the GAR and mechanisms for implementing mitigation measures and (7) details of a local labour agreement for the construction of the GAR.
Proposed Conditions
The conditions that are recommended to be attached to the planning application for the Gedling Access Road are set out below.
A time limit condition specifying when the first phase and second phase of the GAR shall be constructed by is considered necessary as a result of the Environmental Statement (ES) that has been submitted. Following the time limit condition it is proposed that there should be a condition setting out the plans and documents that are to be approved as part of this application. Given the form of the ES it is considered necessary to condition the manner in which the GAR shall be opened to the public. It is proposed that the 5-arm roundabout should be opened first and that the rest of the GAR should be opened in one entire phase (except for the roundabout and arms of the GAR proposed on Lambley Lane). An exception is made for Lambley Lane, because this part of the GAR will need to be brought into use in order to retain vehicular access through this part of the Borough.
Details of how pedestrian and traffic movement shall be managed during the construction and post construction prior to the opening of the phases of the GAR is also proposed to be conditioned. This will assist in ensuring that adequate measures are put in place so as to avoid any adverse socio-economic impacts that could be caused as a result of temporary alterations to the road network caused by the construction of the GAR.
A public transport strategy is also requested to cover both phases of the development and also to cover the three time periods of construction, post construction and prior to the opening of each phase and then post opening. This information is required in order to ensure that there is no disruption to public transport.
Highways have requested a condition to ensure that any proposed security lighting will not have any adverse impact on other road users.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.