Resolved
RESOLVED TO: · Request additional information regarding risk number 2 · Note the progress of actions identifies in the Corporate Risk Register.
Overview and Scrutiny Committee noted this item on Monday 20 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED TO: · Request additional information regarding risk number 2 · Note the progress of actions identifies in the Corporate Risk Register.
1.1It was agreed at the last Overview and Scrutiny Committee it would receive quarterly updates on the Corporate Risk Scorecard and specifically those issues that are identified by the Audit Committee to be of concern.
1.2The current Risk Management Strategy & Framework was last considered and approved by the Cabinet in October 2017. The purpose of the Strategy and Framework is to define how risks are managed by the Council. It provides guidance on the processes, procedures, roles and responsibilities for risk, and it sets out the context on how risks are to be managed. It defines the key role for the Audit Committee as providing independent assurance to the Council with regard to the effectiveness of the risk management framework and the associated control environment. This includes the monitoring of the framework and ensuring the implementation of all audit actions.
1.3The Corporate Risk Register is a key enabler of the Strategy and Framework, and provides assurance on the key risks identified as corporate risks. 1.4 Existing risks identified within both the Council’s corporate and operational service risk registers are subject to quarterly review by senior management and on an ongoing basis through the work of Internal Audit.
1.5This approach has meant that some of the risks included within the corporate risk register have been set at a relatively high score with the expectation that as mitigation measures are properly recorded or actions taken, then these risks should start to improve over the coming months. This is not to say that all risks will return to ‘green’, as mitigation measures can only go so far, and some risks may always be inherently ‘red’ or ‘amber’ as the score reflects the potential impact on the Council and the likelihood of that event occurring.
1.6The Corporate Risk Register and supporting comments as at the end of March 2020 are appended to this report, and this includes a summary of all control gaps currently identified on the Council’s Corporate Risk Register.
1.7Members are fully aware of the risks arising from the national outbreak of the coronavirus, Covid-19. The impacts of this, as at quarter 4, have been reflected in the risk register. Two reports were presented to Cabinet on 18 June 2020 detailing Gedling’s response to the pandemic, and proposing a Reset Strategy to include a review of the Gedling Plan to ensure that it remains fit for purpose and incorporates any new work streams arising from Covid-19 impacts.
1.8Members of the committee should note that all risks are unchanged from last quarter with the exception of three areas which have all been affected by the Covid 19 Pandemic.
2 FAILURE TO MAINTAIN FINANCIAL INTEGRITY Current Risk and Direction of Travel: RED – Deterioration from D4 (major impact/high likelihood to E4 (major impact/very high likelihood)
10 FAILURE TO MAINTAIN SERVICE STANDARDS, CUSTOMER SATISFACTION, AND/OR MEET CUSTOMER EXPECTATIONS Current Risk and Direction of Travel: AMBER – Deterioration (from a fully controlled risk B1 to C3 Significant Impact/Significant Likelihood)
12 FAILURE TO REACT TO AN ENVIRONMENTAL INCIDENT OR MALICIOUS ACT
Current Risk and Direction of Travel: AMBER – Deterioration from fully controlled to Serious Impact/Low Likelihood. Additional information regarding these risks is attached at Appendix 1 and 2. No issues of concern were identifies at the Audit Committee held on the 7th July.
4.1There are no financial implications arising out of this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 369 KB | Download |
PDF |
Corporate Risk Management Scorecard Quarter 4 2019/20Report | 161 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 27 July 2026.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 12 Oct 2026 | Update on Local Government Reorganisation (LGR).To note the update on Local Government Reorganisation. | Noted | Open |
| 12 Oct 2026 | Response to the Fly Tipping, Litter and Waste Management Recommendations.To note Cabinet’s response to the recommendations of the Fly Tipping, Litter and Waste Management Working Group. | Noted | Open |
| 12 Oct 2026 | Scrutiny Work Programme.To note the Scrutiny Work Programme. | Noted | Open |
| 9 Mar 2026 | To approve, as a correct record, the minutes of the meeting held on 12 January 2026.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.