Resolved
To note the Gedling Borough Five Year Housing Land Supply Assessment 2025, attached as Appendix A.
AI summaryGedling Planning Committee notes the 2025 housing land supply assessment, which shows the borough now has a 3.73 year supply, down from 6.19 years, because the new standard method raised the annual target to 638 homes.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
To note the Gedling Borough Five Year Housing Land Supply Assessment 2025, attached as Appendix A.
THAT: Planning Committee
Notes the Gedling Borough Five Year Housing Land Supply Assessment 2025, attached as Appendix A.
1.1This report sets out the latest five year housing land supply position for Gedling Borough Council as at 31st March 2025, which is attached at Appendix A. The National Planning Policy Framework 2021 requires that local planning authorities update their five year housing land supply assessments on an annual basis.
1.2The assessment includes the housing sites in the Local Planning Document which was adopted by Council on 18 July 2018. The five year period is 1 April 2025 to 31 March 2030. For clarity, this is the assessment against the housing requirement as calculated using the Government’s standard methodology (published 2025) as the Aligned Core Strategy was adopted in September 2014 and the policies are yet to be reviewed.
1.3A joint SHLAA methodology was first published in November 2020 by Broxtowe Borough Council, Erewash Borough Council, Gedling Borough Council, Nottingham City Council and Rushcliffe Borough Council. It is considered that a common approach is more robust and the methodology is intended to be more transparent and evidence based. The joint methodology comprises a common methodology document plus a separate appendix for each authority to justify the assumptions used for each SHLAA update (www.gedling.gov.uk/shlaa).
1.4The assessment shows that against the housing target as calculated using the standard methodology, Gedling Borough Council does not have a five year plus 5% buffer supply of land for housing. The Council has a 3.73 year supply, which equates to an undersupply of 846 homes. This is a significant decrease from the previous 2024 five year land supply assessment’s figure of 6.19 years’ supply. The main reason for this is due to the new standard method which results in a significant increase in the number of dwellings to be delivered per annum, now 638 (previously 460). The new standard method comprised one of the reasons for the Council’s decision to cease preparation of the Greater Nottingham Strategic Plan and to progress the Gedling Local Development Plan. It is important that the Council continues to allocate land for development through the preparation of its local plan, to ensure an ongoing supply of housing land.
2 Proposal
2.1It is proposed that Planning Committee notes the content of the Gedling Borough Five Year Housing Land Supply Assessment 2025 as set out in Appendix A which has been noted by Cabinet on 12th December 2025.
3.1Paragraph 78 of the National Planning Policy Framework 2024 states that local planning authorities should identify and update annually a supply of specific deliverable sites sufficient to provide a minimum of five years’ worth of housing against their housing requirement set out in adopted strategic policies, or against their local housing need where the strategic policies are more than five years old (unless these strategic policies have been reviewed and found not to require updating).
4.1None, this report monitors the supply of housing sites. An equalities impact assessment has already been undertaken on the Council’s policies (including housing allocations) through the assessment of the adopted version of the Local Plan.
5 Carbon Reduction/Environmental Sustainability Implications
5.1None, this report monitors the supply of housing sites. Consideration of carbon reduction/environmental sustainability implications has already been undertaken on the Council’s policies (including housing allocations) through the preparation of the adopted version of the Local Plan. 6 Appendices
6.1Appendix A - Gedling Borough Five Year Housing Land Supply Assessment 2025.
7.1None.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Five Year Housing Land Supply Assessment 2025Report | 156 KB | DownloadRead as text |
PDF |
Five Year Housing Supply 2025.docxReport | 1.2 MB | Download |
Follow Planning Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 9 September 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 14 Oct 2026 | Application no. 2026/0501 - Richard Herrod Centre, Foxhill Road Central, Carlton, NottinghamshireTo Grant Planning Permission: Subject to the conditions listed for the reasons set out in the report. Conditions The ... | Approved | Open |
| 14 Oct 2026 | Appeal Summary Ref: 6014560 - 31 Mansfield Road, Daybrook, NottinghamshireTo note the information. | Noted | Open |
| 14 Oct 2026 | Appeal Summary Ref: 6013777 - 6 Pateley Road, Woodthorpe, NottinghamshireTo note the information. | Noted | Open |
| 14 Oct 2026 | Future planning applicationsTo note the information. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.