Authority Monitoring Report April 2024 – March 2025

Noted Planning 2 papers

AI summaryGedling Planning Committee noted the Authority Monitoring Report for April 2024 to March 2025, which tracks housing, Green Belt, climate and heritage policies and sets the timetable for the new Gedling Local Development Plan.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCovering 1 April 2024 to 31 March 2025
Money£250,859.41Open space s106 off-site contributions potentially due
What happens nextAdoption Spring 2028Of the new Gedling Local Development Plan
Who it affectsBorough residents and developersSubject to ongoing local plan monitoring

What was decided

The committee noted the Gedling Borough Council Authority Monitoring Report for April 2024 to March 2025, attached as Appendix A.

The report records the council's progress on Local Plan preparation, duty to co-operate activity and implementation of planning policies over the monitoring year. Report 1.3, 1.4, 5.1

Why

The Authority Monitoring Report is required under Regulation 34 of the Town and Country Planning (Local Planning) (England) Regulations 2012 and must be published at least annually. Report 1.2, 1.3

It also supports the evidence base for the replacement Gedling Local Development Plan, which the council is now preparing after withdrawing from the joint Greater Nottingham Strategic Plan. Report 2.4, P33, P35

What happens next

Regulation 19 consultation on the Gedling Local Development Plan is scheduled for March 2026, with publication of the Submission Document in December 2026. Report P35

Independent Examination hearings (if required) are planned for January 2027, receipt of the Inspector's Report for December 2027 and adoption in Spring 2028. Report P36

The council will continue joint working through the Greater Nottingham Planning Partnership, including an updated Green Belt Assessment Framework consulted on in September 2025. Report P42

The money

  • £250,859.41 Total off-site open space s106 contributions potentially due in 2024/25, subject to approval of open space schemes Report P138
  • £49,469.36 Capital maintenance contribution for open space at Land off Marion Avenue, Hucknall (RPI linked) Report P142
  • £20,891.60 Open space scheme contribution for Land off Marion Avenue, Hucknall (RPI linked) Report P142
  • £60,037.20 Capital maintenance contribution for open space at Land East, Killisick Lane, Arnold (RPI linked) Report P142
  • £27,360.00 Open space scheme contribution for Land East, Killisick Lane, Arnold (RPI linked) Report P142
  • £63,840.00 Capital maintenance contribution for open space at Land Rear of Coppice Farmhouse, Mapperley Plains (RPI linked) Report P142
  • £29,261.25 Open space scheme contribution for Land Rear of Coppice Farmhouse, Mapperley Plains (RPI linked) Report P142

Implications

  • Legal: The AMR is a statutory requirement under Regulation 34 of the 2012 Regulations; the council must publish it at least annually. Report 1.2, 1.3
  • Climate: Per capita CO2 emissions in the borough fell from 4.9 to 3.4 tonnes between 2011 and 2022; the Air Quality Management Area along the A60 Mansfield Road was revoked in November 2024. Report P79, P100
  • Other: 73% of the borough (8,794 hectares) remains Green Belt after the 2018 Local Planning Document released 215 hectares; 13 permissions for disproportionate Green Belt extensions were granted on 'very special circumstances' grounds. Report P106, P107, P108
  • Other: Zero planning permissions were granted against Environment Agency, Coal Authority, Health and Safety Executive or council Scientific Officer advice during the monitoring period. Report P83, P96, P101
  • Risk: Population rose to 120,179 by mid-2024 (up 3.3% since 2011), with a 20% increase in residents aged 65 and over, increasing pressure on services. Report 4.3, P49
  • Equalities: The three most deprived wards are Netherfield, Daybrook and Cavendish; the borough's overall deprivation score improved from 15.29 in 2010 to 14.89 in 2019. Report 4.4, P51

Who and where

  • Residents of Gedling Borough, particularly older residents (20% increase since 2011) and the most deprived wards (Netherfield, Daybrook, Cavendish) Report 4.3, 4.4, P49, P51
  • Developers and applicants for renewable energy, housing, employment and waste management schemes Report P68, P69, P70, P71, P72, P90, P91
  • Neighbourhood planning areas of Burton Joyce, Calverton, Linby and Papplewick Report 2.7, P26, P27, P28, P29
  • Statutory consultees including the Environment Agency, Natural England, Historic England and the Highways Authority Report 3.3, P43

Timeline

  • 1 April 2024 to 31 March 2025: Monitoring period covered by the Authority Monitoring Report Report P4
  • September 2025: Updated Green Belt Assessment Framework consulted on by Greater Nottingham authorities Report P42
  • 21 July to 1 September 2025: Regulation 18 Issues and Options consultation on the Gedling Local Development Plan Report P37
  • March 2026: Regulation 19 consultation on Gedling Local Development Plan Report P35
  • December 2026: Publication of Submission Document for Gedling Local Development Plan Report P35
  • January 2027: Independent Examination hearings (if required) Report P36
  • December 2027: Receipt of Inspector's Report Report P36
  • Spring 2028: Adoption of Gedling Local Development Plan Report P36

Plain English for the jargon

  • AMR: Authority Monitoring Report, an annual report on local plan progress that local planning authorities must publish.
  • ACS: Aligned Core Strategy, the Part 1 Local Plan jointly prepared with neighbouring councils and adopted in September 2014.
  • LPD: Local Planning Document, the Part 2 Local Plan adopted in July 2018 setting out site allocations and development management policies.
  • SPD: Supplementary Planning Document, guidance supporting Local Plan policies and a material consideration in planning decisions.
  • s106: Section 106 agreement, a legal planning obligation between a developer and a local authority to mitigate the impact of development.
  • LWS: Local Wildlife Site, a locally designated site of nature conservation value.
  • AQMA: Air Quality Management Area, an area designated where air quality objectives are not being met.
  • SSSI: Site of Special Scientific Interest, a nationally designated conservation site.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item41

Resolved

To note the Gedling Borough Council Authority Monitoring Report April 2024 - March 2025 attached as Appendix A.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Planning Committee

Authority Monitoring Report

April 2024 – March 2025

Published December 2025 Contents 1. Introduction .......................................................................................................... 2 2. Development Plan Documents ............................................................................ 3 Local Plan ............................................................................................................... 3 Supplementary Planning Documents and Guidance .............................................. 3 Neighbourhood Planning ........................................................................................ 4 Statement of Community Involvement .................................................................... 5 Local Development Scheme ................................................................................... 5 3. Duty to Co-operate ............................................................................................... 6 Local Planning Authorities ...................................................................................... 6 Statutory Consultees .............................................................................................. 7 4. Demographics of Gedling Borough .................................................................... 8 5. Monitoring Local Plan Policies ......................................................................... 10 Overview and Interpretation .................................................................................. 10 Climate Change, Flood Risk and Water Management .......................................... 10 Environmental Protection ...................................................................................... 18 Green Belt ............................................................................................................ 20 Natural Environment ............................................................................................. 22 Open Space and Recreational Facilities ............................................................... 24 Historic Environment............................................................................................. 29 Design .................................................................................................................. 31 Homes .................................................................................................................. 33 Employment .......................................................................................................... 50 Retail and Community Facilities ........................................................................... 57 Transport .............................................................................................................. 65 Infrastructure and Developer Contributions .......................................................... 68 Appendix 1 – Monitoring Indicators ..................................................................... 71

1 1. Introduction 1.1. The Authority Monitoring Report is based upon the monitoring period 1 April 2024 to 31 March 2025.

1.2The Authority Monitoring Report is required under Regulation 34 of The Town and Country Planning (Local Planning) (England) Regulations 2012. Regulation 34 can be viewed on the following website https://www.legislation.gov.uk/uksi/2012/767/regulation/34/made.

1.3The National Planning Practice Guidance states that local planning authorities must publish information at least annually that shows progress with Local Plan preparation, reports any activity relating to the duty to cooperate and shows how the implementation of policies in the Local Plan is progressing.

1.4All of the monitoring indicators included in this report and their origins are set out in Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AMR 2024-2025: FINAL.docxReport 1.7 MB DownloadRead as text
PDF
Authority Monitoring Report April 2024: March 2025Report 160 KB Download

At this meeting

Whole meeting

Who was there

16 of 23 attended
RA
Councillor Roy AllanChair, present
PW
Councillor Paul WilkinsonVice-Chair, present
PA
Councillor Pauline AllanCommittee Member, present
JA
Councillor Jane AllenCommittee Member, present
SB
Councillor Stuart BestwickCommittee Member, present
DE
Councillor David EllisCommittee Member, present
AE
Councillor Andrew EllwoodCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
JN
Councillor Julie NajukCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, present
CP
Councillor Catherine PopeCommittee Member, present
GP
Councillor Grahame PopeCommittee Member, present

All 23 on the meeting page

On this subject at Gedling

Search all
  1. Authority Monitoring Report April 2024 – March 2025This decision
  2. Authority Monitoring Report April 2024 - March 2025Decided
  3. Authority Monitoring Report April 2023 - March 2024Noted
  4. Authority Monitoring Report April 2023 - March 2024Noted
  5. Authority Monitoring ReportNoted
  6. Authority Monitoring Report April 2022-March 2023Noted

More from Gedling Planning Committee

All decisions
MeetingDecisionOutcome
14 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 9 September 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
14 Oct 2026 Application no. 2026/0501 - Richard Herrod Centre, Foxhill Road Central, Carlton, NottinghamshireTo Grant Planning Permission: Subject to the conditions listed for the reasons set out in the report. Conditions The ... Approved Open
14 Oct 2026 Appeal Summary Ref: 6014560 - 31 Mansfield Road, Daybrook, NottinghamshireTo note the information. Noted Open
14 Oct 2026 Appeal Summary Ref: 6013777 - 6 Pateley Road, Woodthorpe, NottinghamshireTo note the information. Noted Open