AI summaryGedling Cabinet approved the Carlton Active leisure centre to move into pre-construction design (RIBA 3 and 4), and agreed to close the Richard Herrod Centre from 1 May 2026 to enable the rebuild.
Written from the decision and the officer reportPDF Pro
OutcomeNotedRIBA 2 noted, project to proceed to RIBA 3 and 4
Money£29,998,353 + VATRIBA 2 capital cost estimate for the new build
What happens nextRIBA 3 and 4 pre-constructionRIBA 3 from 23 February 2026, start on site 7 December 2026
Who it affectsCarlton residents and leisure usersRichard Herrod closes 1 May 2026; Carlton Forum to be withdrawn
What was decided
Cabinet noted the RIBA 2 design, cost plan and business case, and approved progression through the UK Leisure Framework into RIBA Stage 3 (Spatial Coordination) and Stage 4 (Technical Design), subject to budget approval. Report P9, P76
Cabinet agreed the Richard Herrod Centre will close from 1st May 2026, to enable demolition and redevelopment as the Carlton Active Centre. Report P33, P106
Cabinet agreed to withdraw from the Carlton Forum Leisure Centre joint use agreement with Nottingham County Council and Redhilll Academy Trust, and authorised the Chief Executive to serve notice in consultation with the Leader. Report P32, P41
Why
The existing facilities are ageing: Richard Herrod is council-owned with the highest leisure subsidy, and Carlton Forum is over 50 years old and on land not owned by the council, so a new-build on the Richard Herrod site was judged the most cost-effective option. Report P32, P33, P35
An indoor bowls hall (3, 4 or 6 rinks) was considered but rejected because of high build cost, site area constraints, and the need to protect the swimming pool and gym, which have the strongest user demand. Report P68, P69
The Max Associates business case (Option 3, Adv Play only) shows a potential usable surplus of around £200k after deducting the 3G pitch and sinking fund, giving indicative PWLB borrowing capacity of c.£9.78m over 25 years or c.£13.35m over 50 years. Report P82
What happens next
RIBA Stage 3 design work begins 23 February 2026 and is scheduled to complete in June 2026, with the planning application window running 7 May to August 2026 and RIBA Stage 4 completing 25 September 2026. Report P9, P106
Contract award is programmed for 9 November 2026 after internal governance between 2 and 6 November 2026, with a 4-week mobilisation and start on site on 7 December 2026. Report P9, P106, P107
Authority was delegated to the Chief Executive, in consultation with the Leader, to seek all necessary planning and statutory approvals; each stage's equalities impact assessment must be reported to Cabinet, and a further report is to come back on rehousing the indoor bowls club within the borough. Report P34
The money
£29,998,353 + VAT Total RIBA 2 capital cost estimate for the new Carlton Active centre Report P9, P76
£26,830,308.10 Construction total within the RIBA 2 cost plan Report P76
£790,000 Furniture, Fixtures and Equipment (FF&E) cost through Alliance Leisure Report P77, P84
£991,600 Delivery fees in the RIBA 2 cost plan Report P78
£1,341,515 Client-held contingency in the RIBA 2 cost plan Report P78
£783,264.42 Fee to take the project to RIBA Stage 3 Report P9
£908,374.56 Fee to take the project to RIBA Stage 4 Report P9
£1,691,638.98 Combined RIBA 3 and 4 fees Report P9
c.£200k Indicative usable surplus from the Max business case (Option 3) after deducting 3G pitch and sinking fund Report P82
Options considered
Chosen: Option 3 in the Max Associates business case: Adventure Play only, no indoor bowls (the chosen scheme). Strongest surplus position (£253,812 total surplus, c.£200k after pitch deductions) while retaining the gym and pool that have the highest user demand Report P82
Rejected: Option 1: Excluding both indoor bowls and adventure play. Lower surplus than Option 3 (£172,974) and removes the adventure play offer Report P82
Rejected: Option 2: Including indoor bowls and adventure play. Surplus of only £128,486 and indoor bowls costs and site footprint were judged unaffordable Report P69, P82
Rejected: Option 4: Including indoor bowls and adventure play (variant). Surplus of £218,177 still leaves indoor bowls unviable on this site and budget Report P69, P82
Rejected: Including an indoor bowls hall of 3, 4 or 6 rinks at the Richard Herrod site. High specialist build cost, would exceed developable area or force removal of pool or gym Report P68, P69
Implications
Financial: RIBA 2 cost is £29,998,353 + VAT, including a 6% allowance for construction inflation to completion from December 2026, and a client contingency of £1,341,515. Report P76, P78, P79
Financial: The 2024/25 combined Carlton Forum and Richard Herrod subsidy was £540,322; the Max business case shows the new scheme could deliver a usable surplus of around £200k a year from Year 5. Report P82
Legal: The Chief Executive is authorised to withdraw from the Carlton Forum joint use agreement with Nottingham County Council and Redhilll Academy Trust, and to take the scheme through planning, building control and building regulations. Report P32
Equalities: Each equalities impact assessment produced at each RIBA stage must be brought back to Cabinet, alongside a report on rehousing the indoor bowls club within the borough. Report P34
Risk: Key project risks include asbestos, ground conditions, drainage, planning and highways, and ecology (including potential bat roosts requiring emergence surveys between May and September). Report P9, P72, P73
Risk: RIBA 2 redesign or value engineering is likely if the budget is reduced further, with a possible full scheme redesign if there is a substantial budget cut. Report P9, P100, P101
Climate: Social value commitments include an energy-efficient build, waste reduction, sustainable travel, biodiversity focus, local supply chains and a low-carbon design aligned with the Leisure Transform and Procurement strategies. Report P123, P124, P125
Other: Richard Herrod Centre will close on 1st May 2026 ahead of demolition as part of enabling works, with proposed start of those works on 21st September 2026. Report P33, P36, P106
Who and where
Users of Richard Herrod Centre, who will lose access from 1 May 2026 pending redevelopment Report P33, P34
The indoor bowls club at Richard Herrod, to be rehomed within the borough following closure Report P34
Users of Carlton Forum Leisure Centre, which the council will withdraw from after the new centre opens Report P32, P41
Gedling Southbank FC and Mencap Valley Care Home, whose sites and operations are adjacent to the redevelopment Report P40, P115
Nottingham County Council and Redhilll Academy Trust, joint use partners at Carlton Forum who will receive notice of withdrawal Report P32
Local residents in Carlton, who are within the demographic catchment for the new gym, studios, pools and Innerva wellness equipment Report P92, P93
Timeline
28th January 2026: RIBA Stage 2 report finalised Report P1, P4, P7
19th February 2026: Cabinet approval of RIBA 2 and progression to pre-construction Report P106
23rd February 2026: RIBA Stage 3 commences Report P106
1st May 2026: Richard Herrod Centre closes to enable redevelopment Report P106
7th May 2026, August 2026: Planning application period Report P9, P106
21st May 2026: RIBA Stage 4 commences Report P106
June 2026: RIBA Stage 3 completes Report P106
21st September 2026: Proposed enabling works (including demolition) commence Report P106
25th September 2026: Contractor proposals submitted and RIBA Stage 4 completes Report P9, P106
2nd November 2026, 6th November 2026: Internal governance and approvals Report P107
9th November 2026: Main contract execution Report P9, P107
7th December 2026: Start on site for main construction Report P9, P76, P107
Plain English for the jargon
RIBA Stage 2: Concept Design, the second of the Royal Institute of British Architects' work stages, where design concepts and a cost plan are developed.
RIBA Stage 3 (Spatial Coordination): The third RIBA work stage, where the design is developed in detail and coordinated across disciplines before planning submission.
RIBA Stage 4 (Technical Design): The fourth RIBA work stage, where the design is finalised for tender and construction.
GIFA: Gross Internal Floor Area, the total floor area measured to the internal face of the perimeter walls.
FF&E: Furniture, Fixtures and Equipment, the movable items needed to fit out a building for use.
PWLB: Public Works Loan Board, a UK government body that lends money to local authorities for capital projects.
UK Leisure Framework: A publicly compliant procurement framework allowing direct appointment of Alliance Leisure Services as development partner for leisure schemes.
3G pitch: A third-generation artificial grass sports pitch, requiring a sinking fund for future resurfacing.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item82
Resolved
That: 1) Cabinet noted and agreed the outputs of the RIBA Stage 2 design work for the Carlton Active Leisure, Health and Wellbeing Centre, including the emerging design proposals, business case position and indicative RIBA Stage 2 cost plan, recognising that these remain subject to further development and refinement and having regard to the evidence set out within the report in respect of indoor bowls provision. 2) Subject to budget approval, Cabinet approved progression of the project into pre-construction, specifically RIBA Stage 3 (Spatial Coordination) and RIBA Stage 4 (Technical Design), to be delivered through the UK Leisure Framework. 3) Cabinet agreed the closure of the Richard Herrod Centre with effect from 1st May 2026, to enable the redevelopment of the site as the Carlton Active Centre, noting that the closure date aligns with the agreed programme for pre-construction and redevelopment. 4) Cabinet agreed to withdraw from the Carlton Forum Leisure Centre joint use agreement and authorised the serving of notice by the Chief Executive, in the consultation with the Leader of the Council, at the appropriate time in accordance with the terms of the agreement, in order to enable an orderly transition of leisure provision in Carlton. 5. Cabinet agrees to delegate authority to the Chief Executive, in the consultation with the Leader of the Council, to seek all necessary approvals relating to final design and the progression of the scheme through the planning and statutory approvals process, including planning applications, building control and building regulations matters, where such decisions are required to facilitate the approved progression of the project. 5) Each equalities impact assessment at each RIBA stage be disseminated to cabinet. 6) A report be brought to cabinet regarding the rehousing of the bowls club within the borough.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
Carlton Active Gedling Borough Council 28th January 2026
RIBA 2 Report. Gedling Borough Council | RIBA 2 Report 2
Document history. Version Control
Version Date Description
1.023/01/2026 Draft 2.0 26/01/2026 Hadron review 3.0 28/01/2026 Final Issue
Authorisation
ALS Business Development Manager Date ALS Executive Approval Date Gareth Liversedge 28/01/2026 Will Gardner 28/01/2026
Disclaimer Copyright This document and its contents have been prepared and are intended solely for the The copyright of this document is vested in Alliance Leisure Services Ltd. This document Client’s information and use in relation to Carlton Active within Gedling Borough may not be reproduced in whole or in part without their express written permission Council. Alliance Leisure Services Ltd assumes no responsibility to any other party in respect of or arising out of or in connection with this document and/or its contents. Gedling Borough Council | RIBA 2 Report 3
Executive summary. Gedling Borough Council (GBC) has commissioned Alliance Team Programme Leisure (ALS) to develop the design and associated costings for the proposed new-build Carlton Active facility. ALS has selected an experienced team to support the The planning period for the scheme is anticipated to run project: from 7 May 2026 through to August 2026. Completion of Brief RIBA Stage 4 is scheduled for 25 September 2026, Hadron (Project Management) following which the scheme will be presented for Gedling The scope currently includes; Universal (Principal Contractor) Borough Council approval between 2 and 6 November GT3 (Lead Designer) 2026. Subject to approval, contract award is programmed 8 lane main pool for 9 November 2026. Greenwood Projects (Principal Designer – CDM) Teaching pool Health Suite (30m2) Safer Sphere (Principal Designer – BSA) A four-week mobilisation period will follow contract award, with the start on site anticipated on 7 December Community Room – suitable for a range of sporting and 2026. Budget non-sporting activities, community hire and youth services (146m²), together with a community room The project is currently estimated at £29,998,353 + VAT. A detailed breakdown of the programme is provided in store (46m²) Appendix B. Café linked to reception A number of site and technical surveys have been Adventure Play area At RIBA Stage 0, the estimated value of the new-build undertaken, details of which are outlined within the facility was identified as between £32.5m and £39.3m. Assisted Exercise Suite report. Following further discussions at the project inception Gym – c. 130 stations (631m2) meeting, the project budget was reduced to circa £30m. 2 x group Exercise Studios (199m2 & 125m2) Key risks include asbestos, ground conditions, drainage, Subsequent discussions have indicated that further budget Spin Studio (65m2) Planning and Highways, and ecology. A detailed risk reductions may be required. Various office and admin spaces; and register is included within the report. Dedicated changing spaces. Value engineering may be required at RIBA Stage 2 should • The fee to take this to RIBA 3: £783,264.42 the available budget be reduced further, in order to ensure the scheme remains aligned with the Council’s • The fee to take this to RIBA 4: £908,374.56 confirmed budget. However, in the event of a substantial budget reduction, this would necessitate a redesign of the • Total fees combined are £1,691,638.98 RIBA Stage 2 scheme. Further detail on the implications of The programme length for undertaking RIBA 3 & 4 this is provided within the report. estimated at 10 months. Gedling Borough Council | RIBA 2 Report 4
Contents. 1 Introduction
Appendices. 2 Project Brief
3 The Development Proposal
4 RIBA 2 Planning and Surveys A RIBA plan of works 5 Capital Investment Summary B Contractors Proposals 6 FF&E C FF&E Schedule 7 Project management D Innerva Business Plan 8 Cost implications and design development
9 Principal Designers (CDM & BSA)
10 Social Value
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.