Options to expend s106 affordable housing contributions

Approved Executive 2 papers

AI summaryGedling Cabinet approves partnership with Registered Providers to spend £1.94m of S106 affordable housing contributions on new units in the Borough.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBuild or acquire affordable units in the Borough
Money£1,940,706 in S106 contributions heldIncluding £560,567 to commit by January 2027
What happens nextNominate a preferred Registered ProviderThrough a formal tender or application process
Who it affectsAll wards in the BoroughHouseholds in need of affordable housing

What was decided

Cabinet approved working in partnership with approved Registered Providers of social housing to build or acquire affordable units within the Borough. Report P8, 2.1

The Council will require 100 per cent nomination rights to the new affordable homes. Report 2.2, P20

Why

Demand for social housing continues to grow and the Council has a legal duty to house homeless people and those in urgent housing need. Report 1.6

S106 commuted sums unspent within their time limits (typically 10 years) must be repaid to the developer, creating a financial risk to the Council. Report 10.1, 1.3, 3.1

The partnership option avoids extra management and maintenance costs to the Council, with the Registered Provider taking on regulatory liability. Report 4.1, P18

What happens next

Run a formal selection process (tender or application) to nominate a preferred Registered Provider partner. Report P16, 2.1

Negotiate nomination rights for initial and any subsequent allocations of the affordable units. Report P20, 2.2

Commit the £560,567 of contributions that must be spent by January 2027 to avoid repayment to developers. Report P41, 10.1

The money

  • £1,940,706 Total S106 affordable housing contributions held as of 31 March 2025, which are time limited Report 4.3
  • £560,567 S106 contributions that need to be committed by January 2027 Report P41

Options considered

  • Chosen: Work in partnership with a Registered Provider of social housing (Option 1). Guarantees effective spending, value for money and strategic alignment; no extra management or maintenance costs; reduces delays in using the commuted sums Report P15, 1.6, 4.1, P32
  • Rejected: Council owned affordable housing properties (Option 2). Council lacks capacity and expertise to manage and maintain units; no suitable Nottinghamshire authority identified to take on management; would require registration with the Regulator of Social Housing; total cost not currently known Report P32, 4.2, P24, P25, P39
  • Rejected: Do nothing. Risk that unspent S106 contributions would need to be repaid to developers, a financial risk to the Council Report 3.1

Implications

  • Financial: Holding £1,940,706 in time-limited S106 contributions, of which £560,567 must be committed by January 2027 or risk repayment to developers. Report 4.3, P41, 1.3
  • Legal: Section 106 of the Town and Country Planning Act 1990 requires funding to be used per the agreement terms or returned to the developer. Report 5.1
  • Risk: Under the partnership option, the Registered Provider is liable for regulatory standards, not the Council; the Council keeps an oversight role. Report P18, P19
  • Equalities: An Equality Impact Assessment is at Appendix 1 of the report. Report 6.1, 8.1
  • Climate: A Whole Life Cycle Assessment is required for any properties bought; condition surveys will address emissions per property. Report 7.1

Who and where

  • All wards in Gedling Borough Report P1
  • Households in need of affordable housing, including homeless people and those in urgent housing need Report 1.6
  • Over 20 Registered Providers currently operating within the Borough Report P15

Timeline

  • 31 March 2025: Date of S106 affordable housing contributions total of £1,940,706 Report 4.3
  • 19 February 2026: Cabinet decision approving the partnership approach
  • January 2027: Deadline by which £560,567 of contributions must be committed Report P41
  • Within 10 years of receipt (typical): Time bar after which unspent S106 commuted sums, plus accrued interest, must be repaid to the developer Report 10.1

Plain English for the jargon

  • Section 106 (S106): Legal agreements under the Town and Country Planning Act 1990 that let councils require developers to provide affordable homes or pay a commuted sum to offset the impact of a development.
  • Commuted Sum: A financial payment from a developer instead of building affordable homes on-site, used to fund affordable housing elsewhere in the area.
  • Registered Provider (RP): A social housing landlord registered with the Regulator of Social Housing that delivers and manages affordable housing.
  • Nomination rights: The right for a council to choose who is allocated the affordable homes, usually from its housing waiting list.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item83

Resolved

That: 1) Cabinet approved that the Council works in partnership with relevant Registered Providers of social housing to either build or acquire affordable units within the Borough.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Cabinet

Wards affected

All Wards

Purpose

To consider options available to the Council to best utilise Section 106 commuted sum monies with the aim of delivering urgently needed, good quality affordable housing in the Borough

Key Decision

This a key decision.

Recommendation(s)

THAT Cabinet:

1) Approves that the Council works in partnership with relevant Registered Providers of social housing to either build or acquire affordable units within the Borough.

Background

1.1The National Planning Policy Framework (NPPF) outlines the governments planning policies for England including provision of Affordable Housing. At a local level, Policy LPD 36 of the Councils Local Planning Document (2018) sets out the quantum of Affordable Housing required in a relevant area within the Borough. The Councils Affordable Housing Supplementary Planning Document (December 2009) provides detailed guidance on how affordable housing should be delivered. There is a requirement for developers to provide a variety of housing types, sizes and tenures, to provide a choice of market affordable needs and meet local demand.

1.2Section 106 (S106) affordable housing requirements are legal obligations in planning agreements where developers provide affordable homes (social rent, affordable rent, shared ownership) or pay a fee (Commuted Sum) to offset development impacts ensuring homes are for local, lower-income people and remain affordable long-term. These site-specific agreements mandate the number, type, and delivery of affordable units.

1.3Affordable housing commuted sums are financial payments from developers instead of building affordable homes on-site, used to fund affordable housing or related infrastructure elsewhere, often when on-site provision is unviable or inappropriate due to site constraints, location, or existing housing mix. These sums are calculated based on the cost of providing units, site viability, local needs, and policy, agreed via a Section 106 agreement to ensure funds are used for affordable housing provision in the community. Where any Affordable Housing Contribution is not spent in accordance with the obligations of those Section 106 Agreements, there is a risk that the financial contribution would need to be repaid.

1.4A financial contribution (Commuted Sum) of broadly equivalent value can be justified where the agreed approach contributes to the objective of creating mixed and balanced communities. The Councils approach should be sufficiently flexible to take account of changing market conditions over time.

1.5The Council has explored various options that are available to deliver additional, good quality affordable housing in the Borough by using S106 commuted sum monies. An option appraisal for S106 affordable homes scheme involves evaluating various delivery models and funding options to determine the most effective and financially viable approach for meeting local housing needs.

1.6The demand for social housing continues to grow. To help address the need, 2 options have been identified to utilise the commuted sum contributions with option 1 considered to be the preferred option: - Option1. Work with a Registered Provider of Social Housing

The funds can be transferred to a Council approved registered housing provider to build or acquire affordable units. There are currently over 20 Registered Providers (RP’s) operating within the Borough, each specialised in delivering and managing affordable housing schemes. Working with a RP will guarantee the effective spending of the funding whilst ensuring value for money and strategic alignment.

The Council can nominate a “preferred partner” to work with, but it usually involves a strategic decision through a formal selection method (like a tender or application process).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact AssessmentAppendix 1 437 KB Download
PDF
Options to expend s106 affordable housing contributionsReport 186 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
JC
Councillor John ClarkeChair, present
JH
Councillor Jenny HollingsworthVice-Chair, apologies
DE
Councillor David EllisCommittee Member, present
KF
Councillor Kathryn FoxCommittee Member, present
VM
Councillor Viv McCrossenCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, present
HW
Councillor Henry WheelerCommittee Member, present
MH
Mike HillOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
TA
Tina AdamsOfficer, in attendance
ST
Sarah TromanOfficer, in attendance

All 18 on the meeting page

More from Gedling Cabinet

All decisions
MeetingDecisionOutcome
16 Jul 2026 To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
16 Jul 2026 Forward Plan1) To note the report. Noted Open
16 Jul 2026 Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... Noted Open
16 Jul 2026 Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... Agreed Open
16 Jul 2026 Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies