Capital Programme and Capital Investment Strategy 2026/27 to 2030/31
AgreedExecutive4 papers
AI summaryGedling Cabinet agrees Capital Investment Strategy and three year Capital Programme totalling £19.5m, with referral to Full Council on 4 March 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedReferred to Full Council for final approval on 4 March 2026
MoneyNot stated
What happens nextFull Council approvalFinal approval scheduled for 4 March 2026
Who it affectsAll wards in GedlingCovered by the Council wide Capital Programme
What was decided
Cabinet agreed the estimated capital financing available for 2026/27 through to 2030/31, the Capital Investment Strategy, the Capital Programme for 2026/27 to 2028/29, the indicative programme for 2029/30 and 2030/31, and the Flexible Use of Capital Receipts Strategy, all referred to Full Council for approval on 4 March 2026. Report P11, P12, P13, P14, P15
Why
The Council is required to have a Capital Investment Strategy and Capital Programme under the prudential framework set out in the Local Government Finance Act 2003 and the CIPFA Prudential Code. Report 1.1, 1.2, 1.3, 1.4
The programme supports delivery of the Gedling Plan priorities, with limited capacity for additional service developments not funded by specific grants or invest to save schemes. Report 2.1, 2.2, P92, P103
What happens next
Full Council will consider approval of the Capital Investment Strategy, Capital Programme and Flexible Use of Capital Receipts Strategy on 4 March 2026. Report P7, P12, P13, P15
Cabinet will be updated through regular budget monitoring reports during 2026/27, with the vehicle replacement programme subject to in year review. Report P51, P72
The money
10,194,000 Total Capital Programme 2026/27 Report P39, P91
4,696,000 Total Capital Programme 2027/28 Report P39, P91
4,562,000 Total Capital Programme 2028/29 Report P39, P91
5,189,700 Indicative Capital Programme 2029/30 Report P39, P91
4,944,200 Indicative Capital Programme 2030/31 Report P39, P91
£2.12m Carlton Active RIBA 3 and 4 design and demolition costs Report P64, P67
£20,000,000 Plan for Neighbourhoods grant over 10 years, with Council as Accountable Body Report P69
£6,326,700 Prudential borrowing required to finance 2026/27 to 2028/29 programme Report P88
£3,429,900 Further estimated borrowing for 2029/30 to 2030/31 indicative programme Report P88
£10,837,400 Expected large capital receipt, partly earmarked for Carlton Active Report P76
2,969,000 Schemes re profiled from 2025/26 into 2026/27 Report P42, P43
344,400 New resource development bids and grant funded schemes Report P56, P57
Options considered
Chosen: Approve Capital Programme, Strategy and Flexible Use of Capital Receipts Strategy. Required to support delivery of the Gedling Plan and comply with the prudential framework Report P12, P13, P15, P103
Rejected: Identify additional service development schemes. Resources are limited and there is no capacity for schemes not funded by specific grants or invest to save arrangements Report P92
Implications
Financial: The Council will act as Accountable Body for around £20m of Plan for Neighbourhoods grant over 10 years, with capital elements of about £14,936,000 passing through the Council's capital programme. Report P69, P70
Financial: A large capital receipt of around £10,837,400 is expected, with part earmarked for the Carlton Active project pending a viable business case. Report P76
Financial: Borrowing of £6,326,700 is required to finance the 2026/27 to 2028/29 programme, with a further £3,429,900 estimated for 2029/30 to 2030/31, assessed as affordable and sustainable against Prudential Indicators. Report P88, P89
Risk: Local Government Reorganisation is expected with Vesting Day on 1 April 2028, which may affect capital investments post vesting and require a new capital programme to align with the dissolution of Gedling Borough Council. Report 3.1
Risk: If the Carlton Active scheme does not proceed, pre construction costs incurred to date will become abortive costs. Report P65
Climate: Several 2026/27 schemes focus on energy efficiency and environmental objectives, supporting the Council's Carbon Management Strategy. Report P96
Residents and users of council leisure facilities, particularly in Carlton through the Active project Report P60, P61, P62
Recipients of Disabled Facilities Grants Report P85, P86
Town Centre stakeholders in Greater Carlton through the Plan for Neighbourhoods Board Report P69, P70
Timeline
2026/27: Capital Programme year 1 totalling £10,194,000 Report P39
2027/28: Capital Programme year 2 totalling £4,696,000 Report P39
2028/29: Capital Programme year 3 totalling £4,562,000 Report P39
2029/30: Indicative programme of £5,189,700 Report P39
2030/31: Indicative programme of £4,944,200 Report P39
4 March 2026: Full Council meeting to consider final approval of the strategy, programme and Flexible Use of Capital Receipts Strategy Report P7, P12, P13, P15
1 April 2028: Expected Vesting Day for Local Government Reorganisation Report 3.1
Plain English for the jargon
CIPFA Prudential Code: Statutory code setting the framework for local authority capital finance, including indicators for affordability and prudence.
MRP: Minimum Revenue Provision, the duty to make prudent provision for repaying borrowing from revenue.
RIBA stages 3 and 4: Royal Institute of British Architects design stages covering spatial coordination, technical design and cost certainty.
CIL: Community Infrastructure Levy, a developer contribution that the Council can use to fund infrastructure.
LGR: Local Government Reorganisation, the restructuring of councils expected to create a new Unitary Council by 1 April 2028.
Plan for Neighbourhoods: Government programme providing long term grant to town boards, with the Council acting as Accountable Body for Greater Carlton.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item87
Resolved
That: 1) Cabinet agreed the estimated capital financing available for 2026/27 through to 2030/31. 2) Agreed the Capital Investment Strategy 2026/27 through to 2030/31 detailed at Appendix 1 and refer it to Full Council for approval on 4 March 2026. 3) Agreed the Capital Programme for 2026/27 through to 2028/29 detailed at Appendix 2 and refer it to Full Council for approval on 4 March 2026. 4) Noted the indicative Capital Programme for 2029/30 and 2030/31. 5) Agreed the Flexible Use of Capital Receipt Strategy in Appendix 3 and refer to Full Council for approval on 4 March 2026.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
a) The proposed Capital Investment Strategy for 2026/27 to 2030/31.
b) The proposed Capital Programme for 2026/27 through to 2028/29 for approval, and the indicative Capital Programme for 2029/30 and 2030/31, in light of the Council’s priorities and the resources available; and
c) The Flexible Use of Capital Receipts Strategy 2026/27.
The Capital Investment Strategy, the Capital Programme and the Flexible Use of Capital Receipts Strategy determined by Cabinet at this meeting will be referred to Full Council on 4 March 2026 for final approval. The detailed capital programme proposals are shown in Appendix 2 to this report.
Key Decision
This is a Key Decision.
Recommendations
Members are recommended to:
1. Agree the estimated capital financing available for 2026/27 through to 2030/31.
2. Agree the Capital Investment Strategy 2026/27 through to 2030/31 detailed at Appendix 1 and refer it to Full Council for approval on 4 March 2026.
3. Agree the Capital Programme for 2026/27 through to 2028/29 detailed at Appendix 2 and refer it to Full Council for approval on 4 March 2026.
4. Note the indicative Capital Programme for 2029/30 and 2030/31.
5. Agree the Flexible Use of Capital Receipt Strategy in Appendix 3 and refer to Full Council for approval on 4 March 2026.
Background
1.1The prudential framework for Local Authority Capital Investment was introduced through the Local Government Finance Act 2003.
1.2This prudential framework incorporates four statutory codes. These are:
• The Prudential Code prepared by CIPFA. • The Treasury Management Code prepared by CIPFA. • The Statutory Guidance on Local Authority Investments prepared by the Department for Levelling Up, Housing and Communities (DLUHC). • The Statutory Guidance on Minimum Revenue Provision (MRP) prepared by DLUHC.
1.3The Capital Investment Strategy 2026/27, an appendix to this report complies with the Prudential Code CIPFA issued in 2021.
1.4The Prudential Code underpins the systems of capital finance and planning and is the primary document which provides the framework for the development of the capital strategy and the capital programme which are proposed in this report. The key issues addressed by the code relate to how Councils will ensure prudence, in respect of longer term planning, the MRP, understanding of risk and the ability to raise council tax.
1.5The Prudential Code sets out the following key objectives, to ensure that:
• Local strategic planning, asset management planning and proper option appraisal are supported.
• The capital investment plans of local authorities are affordable, prudent and sustainable. Affordability has regard to the implications of capital expenditure for Council Tax, whilst prudence and sustainability have regard to the long-term implications for external borrowing considering the actual impact, and potential impact on overall fiscal sustainability.
• Treasury management and other investment decisions are taken in accordance with good professional practice and in the full understanding of risks involved.
• The authority is accountable, by providing a clear and transparent framework.
1.6To provide a clear and transparent framework authorities are required by the Code to formulate a Capital Strategy which sets out the long-term context in which capital expenditure and investment decisions are made and gives due consideration to both risk and reward and their impact on priority outcomes. Whilst the Code does not define ‘long term’ the Council’s current capital investment strategy proposed at Appendix 1 covers the five-year period of the medium term financial plan (MTFP), 2026/27 through to 2030/31, to ensure that longer term forecasts for capital expenditure, disposals and borrowing are fully considered in the revenue budget and demonstrated to be prudent and affordable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.