Gravesham Borough Council
Report to: Joint Transportation Board
Date: 21 March 2007
Reporting officers: Divisional Manager & Director (Regeneration & Regulation)
Subject: A2 Pepperhill to Cobham Widening Scheme
Purpose and summary of report: This report is to advise members of progress with A2 widening scheme.
Recommendations: The report is for information only.
1. Introduction
1.1The A2 Pepperhill to Cobham widening scheme was last reported to this Board at a special meeting held on 18 October last year. This report gives an update on progress with the works, the works programme and ongoing consultations between SKANSKA (the consortium delivering the project for the Highways Agency), and County and Gravesham Borough Council officers. The main A2 works will be completed early Spring 2009 with landscaping of the redundant carriageways completed late 2009.
2. Background/Discussion
2.1The Scheme will provide for widening the A2 from 3 to 4 lanes in each direction between Pepperhill and Cobham junctions. The road will be moved south to hug the CTRL alignment as far as possible between Pepperhill and Marling Cross and the redundant section of road will be landscaped, with a combined dedicated footpath and cycle path, and equestrian route along the line of the old southern footway.
2.2The scheme started in September 2006 with works at Pepperhill and Tollgate.
2.3Downs Road was closed to the public shortly after the commencement of the off- line works and will remain closed for the duration of the works.
2.4The Tollgate Hotel, which is significantly affected by the scheme has been acquired by the Highways Agency and is being used as the site offices and public information centre for the scheme. The turnpike filling station and two cottages on the line of the scheme have been demolished and work started on constructing a drainage lagoon and a new bridge to carry the A2 over A227.
2.5In January this year, works commenced to construct additional vehicle crossovers through the central reservation of the existing A2 which has necessitated the implementation of narrow lanes between Marling Cross and Thong Lane with a 50 mph speed limit. The narrow lanes are expected to be required for a further 6 months.
2.6Statutory undertakers diversion works have also commenced on Hever Court Road which have necessitated the temporary closure of the Singlewell slip road behind the Manor Hotel and temporary traffic lights for shuttle working on Hever Court Road.
3. Programmed works
Hever Court Road
3.1The main statutory undertakers diversion works in Hever Court Road are programmed to commence on 8 May this year, to be completed at the end of July. During this period Hever Court Road will be made one-way eastbound between Miskin Way and the bridge over the A2.
3.2In August, Hever Court Road will be required to be closed for a few weeks to enable earthworks for the new road layout to be carried out. The road can then be opened up again one-way over the same length as identified above.
3.3In January 2008 closure of the road will be required for a major gas main diversion until August 2008. Discussions regarding advance notification of these closures and for the Marling Cross bridge closure, warning/information signing and diversion routes is ongoing.
Marling Cross overbridge
3.4Closure of this bridge has been deferred from May this year until 21 September to enable works at the Tollgate junction to be completed so as not to impede diverted traffic. However the closure period has been extended from 9 months to just over 14 months, with the link not being re-established until early December 2008. It is proposed to maintain a temporary pedestrian route for the majority of the closure period by the use of temporary steps.
Thong Lane Bridge
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A2 Pepperhill to Cobham Widening SchemeReport | 45 KB | DownloadRead as text |
Follow Gravesham Joint Transportation Board at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2021 | Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. | Noted | Open |
| 10 Mar 2021 | Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. | Noted | Open |
| 10 Mar 2021 | Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... | Agreed | Open |
| 14 Mar 2018 | Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: ยท The Gravesham D... | Noted | Open |
| 14 Mar 2018 | Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.