Resolved that in the context of a number of options for how the A2 Sandwich land might be used in the future over and above the base case, the Borough Council:- (1) seeks with the partners a thorough exploration of the coach park and ride and outdoor activity park concepts, with wider public consultation when appropriate; (2) reserves its position on the other options until that work is done, but remains committed to maintenance of the green belt boundary in this area.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Director (Regeneration and Regulation)
Subject: A2 Sandwich Land
Purpose and summary of report: To set a direction for the exploration of options on possible future uses in the A2 Sandwich Lands given that that there are a number of proposals from a number of sources. Recommendations: In the context of a number of options for how the A2 Sandwich land might be used in the future over and above the base case, the Borough Council; 1) seeks with partners a thorough exploration of the coach Park and Ride and Outdoor Activity Park concepts, with wider public consultation when appropriate; 2) reserves its position on the other options until that work is done, but remains committed to maintenance of the Green Belt boundary in this area.
1. Introduction
1.1The A2 Phase 2 Pepper Hill to Cobham widening road scheme that is currently under construction will result in the trunk road past Gravesend and Northfleet moving southwards adjacent to the Channel Tunnel Rail Link. There is a ‘base’ scheme of what happens to the old A2 (discussed further below). A number of planning issues that arise from the A2 scheme have been raised in the Local Development Framework (LDF) consultation process, for example the future uses of various parcels of land including the redundant carriageway.
1.2As a result of this process a number of ideas have been suggested about what might happen in the A2 corridor. The purpose of this report is to outline these and suggest a general direction. The LDF process will provide the forum for sorting out the planning issues, but there are other considerations, such as the degree of direct involvement by the Borough Council. Final details of the landscaping for the base scheme on A2 need to be agreed soon, and some of the decisions about this may need to be influenced by future options.
2. A2 Sandwich Lands
2.1The A2 is being widened to 4 lanes and moved south towards the Channel Tunnel Rail Link on the south side of Gravesend/Northfleet. This leaves behind the old A2 carriageways between just east of Pepper Hill junction and just short of Marling Cross junction, a distance of about 3.5 km. In addition there is a strip of land between the old and new A2 which is about 2.5km long (see map). The old A2 has to remain “highway” in legal terms so that the services can remain in margins of the highway. The old A2 will be landscaped and a joint footway/cycleway provided from Pepper Hill through to Marling Cross (and then extended along the north side of the A2 to the Cobham junction). This will also provide the access for the utilities to maintain their plant, and therefore has to make provision for large lorries (albeit very infrequently). All other road vehicles will be banned. There is also provision for an equestrian route along the A2 southern footway, linking Downs Road with the enhanced bridges at Ifield Court and Church Road to match those over the Rail Link into the rural area.
2.2At the eastern, Singlewell, end there is provision for a replacement Linear Park for that which has been lost to the new A2 and the Channel Tunnel Rail Link Infrastructure Maintenance Depot. The land will all be handed over from Highways Agency to Kent County Council, with a 5 year maintenance period. The HA will remain responsible for the revetment at Tollgate (by the BP petrol station) and the existing bridge over the A227 Wrotham Road. Material is being prepared for a KCC/GBC consultation on the future of Downs Road. The question here being should it be permanently closed to traffic but open for walking, cycling and equestrians, or re-opened to all traffic. The results of this will be reported to the Joint Transportation Board in due course.
2.3This leaves in the corridor three areas of land for future consideration, as well as the old A2 itself within the constraints noted above:
• Land east of the Tollgate Motel
• Tollgate Motel
• Land between Tollgate and Downs Road
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.