Resolved
Resolved that the Council's policy approach for affordable housing on the Heritage Quarter site be to seek 10 per cent on-site provision with a 20 per cent commuted sum.
Cabinet decided this item on Monday 19 November 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the Council's policy approach for affordable housing on the Heritage Quarter site be to seek 10 per cent on-site provision with a 20 per cent commuted sum.
1.1This is a major development site consisting of approximately 600 units of one and two bedroom flats. The council’s normal affordable housing policy is to seek 30% on-site provision which would equate to 180 units.
1.2At the Cabinet meeting held on 13 February 2006, Members decided that the policy approach for this site specifically should be 20% on-site provision with a 10% commuted sum.
1.3The reason for this approach was to meet the need identified in the Housing Needs Survey by using the commuted sum to provide larger family sized units off-site rather than further flatted accommodation on-site.
1.4It remains the case for the reasons set out below, that there is still an acute shortage of 2/4 bedroom family homes with a relative surfeit of flatted accommodation. In light of this the council may well need to reconsider its specific policy on on-site/off-site provision for the Heritage Quarter development.
2. Affordable Housing
2.0The location of the Heritage Quarter proposals and the size and accommodation type has been considered when looking at on-site provision of affordable housing. The development of one and two bedroom flats provided in Gravesham or with planning permission is 370 units since 2005.
2.2There are currently 213 applicants on the waiting list with points waiting for 3 and 4 bedroom family accommodation. On the transfer list the numbers are similar where there are 221 applicants who are living in overcrowded conditions waiting for larger accommodation. The demand for large family homes is increasing with 434 homes needed to satisfy the current demand.
2.3The turnover of family homes is small in comparison to smaller units. For example, during the last financial year there were 21 x 4 bed homes available for re-let in council stock versus 132 x 1 bed units that became available for re-let.
2.4The council has a severe shortage of family type accommodation in the social rented sector. Evidence shows the level of affordable flats that have been developed or with planning permission in place since 2005 supporting the council’s case in accepting a higher commuted sum of 20% with on-site provision of 10% equating to 60 units. This will enable the council to provide family accommodation for social rent elsewhere in the borough.
3. Affect on the Scheme
3.1In February 2006 King Sturge, our consultants, advised that the effect of reducing the on-site provision of affordable housing from 30% to 20% was to generate a sum of some £550,000 to be spent on affordable housing off-site. Because the Total Cost Indicators and grant rate are similar to the rates of two years ago, we can reasonably expect to receive a figure slightly in excess of £1,000,000 to spend off-site.
3.2As to the profitability of the scheme, King Sturge wrote to the council back in November 2005 on how the reduction of the number of affordable units provided on-site would affect the overall profitability of the scheme. A copy of that letter has been annexed to this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
The Heritage QuarterReport | 21 KB | DownloadRead as text |
Follow Cabinet at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... | Refused | Open |
| 28 Sep 2026 | Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. | Agreed | Open |
| 28 Sep 2026 | Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... | Noted | Open |
| 28 Sep 2026 | Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... | Decided | Open |
| 28 Sep 2026 | LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.