Resolved that a three year contract be let to Kings Environmental Research Group, including the provision of a website, from 1 April 2008 and that the necessary budget provision be made on the basis that the cost is likely to be fully offset by fee income.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Subject: Contract for inspection and regulation of prescribed polluting processes Purpose and summary of report: To outline to Members the way in which this statutory duty is currently contracted out by Gravesham BC in a cost neutral way, and to request authority for the Head of Regulatory Services to put in place a similar contract for 3 years commencing 01 April 2008. Recommendations: (1) Members to agree that a 3 year contract for this function be let by the Head of Regulatory Services, to Company A (Option 1) which includes the provision of a website as from 1 April 2008, in accordance with contract procedural rules. (2) Members to agree the necessary budgetary provision for 2008/09, 2009/10 and 2010/11 on the basis that any contract cost is likely to be fully offset by fee income under the regime.
1. Introduction
1.1The Environmental Protection Act 1990, the Pollution Prevention and Control Act 1999 and regulations thereunder, require that certain prescribed processes are authorised by the local authority or Environment Agency so as to control pollution, particularly air pollution.
1.2Medium and low risk polluting processes (referred to as Part A2 and Part B processes) fall to the local authority for inspection and regulation. Other more complex processes fall to the Environment Agency.
1.3There is a statutory fee payable for the initial processing of each application and an annual subsistence fee thereafter. The scale of fees is set by the Secretary of State and is dependent on the complexity of the prescribed process.
1.4These processes must all be inspected on a regular risk-rated basis as laid down in mandatory guidance.
1.5The number of processes currently permitted and regularly inspected or awaiting permitting within Gravesham is 42. The list of processes in the Public Register is attached for information as an appendix to this report. 1.6 Processing applications, carrying out the regular inspections thereafter, and investigating any complaints against the premises is a technically complex process requiring a high degree of knowledge and skill.
2. Current Arrangements
2.1Initially the technical part of this function was contracted out to specialist contractors and the administrative part of the function retained in-house.
2.2Since 1 April 2003, following a Best Value Review of regulatory services, this function has been contracted out in its entirety to a specialist contractor, the contracts initially let for a 12 month duration. The current contract is for a period of 3 years, this extended period representing a Gershon efficiency saving as compared with annual contracts.
2.3The contract is currently let to Kings Environmental Research Group. The agreed contract price is set at 95% of the statutory fee payable by the process operators.
2.4The annual fee income for 2006/07 totalled £18,065.45 for which VAT is not payable, and our payment to the contractors was £17,162.18 excluding VAT. Figures for 2007/08 will not be available until the end of March 2008.
2.5Contract liaison and monitoring are carried out by a designated lead Senior Environmental Health Officer (SEHO) who has maintained an appropriate level of technical competence.
3 Proposed way forward
3.1A new contract for the inspection and regulation of the prescribed processes needs to be in place by 01 April 2008 to ensure continuity of cover.
3.2The advantages of entering into a three contract are:
• savings in Regulatory Services staff time in contract preparation, liaison, management and monitoring when considered in the long term
• no complex annual handover of premises files and other documentation from one contractor to the next
• continuity of inspecting staff, to the advantage of process operators
• no annual ‘lead-in’ time as contractors are first presented with the Gravesham premises/processes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.