Resolved that the use of the Safer Streets Initiative capital budget (2007/08 and 2008/09) to undertake the project as set out in section 3 of the report be approved and officers be requested to arrange for implementation at the earliest opportunity and before the electricity supplies are required to serve the 2008/09 Christmas lighting displays.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Director (Regeneration and Regulation)
Subject: Town centre electricity supplies.
Purpose and summary of report: To advise Members of the needs, costs and possible phasing for providing electricity supplies to the town centre Christmas lighting scheme, events and information activity.
Recommendations: That Members approve the use of the Safer Streets Initiative capital budget (2007/8 and 2008/9) to undertake the project as set out at section 3 and request that officers arrange for implementation at the earliest opportunity and certainly before the supplies are required to serve the 2008/9 Christmas lighting displays.
1. Introduction
1.1The provision of electrical supply within the town centre for Christmas lighting, events and information activity is provided from a number of sources.
1.2A series of high level wall-mounted socket boxes were provide approximately 10 years ago, following the success of town centre events such as the International Market, Children’s Day and Christmas events, until which time power was provided from lamp columns. However, the lighting circuits were insufficient to power major town centre events.
1.3These socket boxes were recently electrically tested and, apart form one, were found to be satisfactory. However, they are reaching a point where they need to be replaced. Similarly, the feeder supply to these boxes is somewhat variable and not in the control of the Council.
2. Discussion
2.1Although using the high level socket boxes reduces the need to deal with the health and safety issues surrounding trailing leads if using equipment at ground level, accessing the boxes is difficult and requires specialist equipment. It is therefore a costly operation if connection and disconnection is frequently required, as with a street market.
2.2It would be beneficial and cheaper in the long term, to have high level sockets for the Christmas lighting and ground level supply points for town centre events and other activity.
2.3Without dedicated feeder supplies to the high level socket boxes it is difficult to identify and remedy faults.
2.4The new three year Christmas lighting contract will provide the opportunity to rationalise power supply points.
3. Proposals
3.1The existing high level socket boxes were used to power lighting displays this Christmas.
3.2The installation contractor for the Christmas lighting will remove all redundant wiring and cabling from the town centre as part of the contract.
3.3It is recommended that priority is given to providing dedicated supplies to the 11 high level socket boxes required for the Christmas lighting. This will involve the installation of feeder pillars with mains connections at ground level and feeder cables up to the socket boxes. The condition of each socket box should be reassessed and, if necessary, replaced. In addition, the possibility of fitting socket boxes with digital timers is being investigated both to establish if such items are available and to understand the additional cost implications.
3.4To provide easily accessible power supply points at ground level it is recommended that retractable supply units are sunk into footway areas in appropriate locations.
3.5It has been assessed that 10 retractable supply units would be required in the long term to meet all the potential needs of town centre events. This could be phased over a number of years, but initially 2 units should be considered as priorities to serve next year’s town centre events programme. If funding is agreed for the two initial supplies it is suggested that officers, in consultation with appropriate Members, consider their most appropriate location in terms of existing and planned activities.
3.6A drawing of the type of retractable supply unit proposed is appended to the report.
4. Financial Issues
4.1Set out below are the estimated costs of the above:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.