CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gravesham Borough Council
Gravesham Joint Transportation Board, Wednesday 25 March 2009 at 7.00pm

Highway and Transportation Schemes Progress Report 2008/09

Noted Committee 1 paper

Gravesham Joint Transportation Board noted this item on Wednesday 25 March 2009. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

Resolved the report be noted.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Gravesham Joint Transportation Board

Gravesham Borough Council

Report to: Joint Transportation Board

Date: 25th March 2009

Reporting officer: Head of Countywide Improvements

Subject: Highway and Transportation Schemes Progress Report – 2008/9 Purpose and summary of report: This report advises members of the progress of highway and transportation schemes in Gravesham.

Recommendations: For information and comment.

1. Background.

1.1Following the acceptance of the proposed schemes for the 2008/9 Urban and Rural Packages, and Highway Improvement schemes, this report shows the progress on these schemes to date.

1.2Appendix 1 shows each scheme within the Kent Thameside (Gravesham) packages; Gravesham Rural package and Crash remedial Schemes. Progress to date and anticipated progress prior to the next Joint Board is detailed. Also detailed are those schemes from the 2007/08 financial year that were still to be completed in the last report.

1.3For Members’ information on the progress on these schemes

BACKGROUND DOCUMENTS: The background papers pertaining to this report are held on the Kent Highways Services files.

All requests to inspect the above documents MUST be directed in the first instance to the Committee Section of the Democratic Services Department

Contact Officers: See last column in Appendix 1 (tel 08458 247 800). Highway and Transportation Scheme Progress Report – 2008/9: APPENDIX 1

1. Kent Thameside (Gravesham) Urban Package 2008/09

Kent

Forecast Out-turn KHS Location Description of Works Current Progress Anticipated Actions for next 3 Highway

allocation

2008 – 09 2008 - 09 Original Ref months Services (Prior to next JTB) Contact 08458 247800 Sites for permanent traffic monitoring equipment, (count A226 Rochester 08-ITS- UTMC – Traffic loops), identified and David Road / Stonebridge N/a £50k £50k GR-01 congestion information installation expected to be Batchelor Rd – Gravesend completed by end of march 2009.

Agreement between KCC & GBC has been signed, and work on installing equipment 08-ITS- Off-vehicle ticketing & Installation & commissioning David Fastrack – Route B has commenced on Thames £390k £80k GR-02 CCTV to be completed. George Way with a view to completion before the end of the financial year.

Outline design has been Hall Road / 08-ITS- Cycle route & pedestrian progressed and discussions Outline design to be Peter Coldharbour Road rd £20k £10k GR-03 improvements. regarding purchase of 3 party completed Slaughter – Northfleet land continuing.

Pedestrian crossing & 08-ITS- Hall Rd / A2 Slip cycle improvements & GR-04 Works completed Monitoring £60k £70k Julian Cook roads. - Northfleet removal of old traffic signals equipment. Formal Pedestrian Darnley Road / 08-ITS- crossing facilities to be Works completed September Dashwood Road. N/a £90k £95k Julian Cook GR-05 added to existing traffic 2008 Gravesend signals 1. Kent Thameside (Gravesham) Urban Package 2008/09 (continued)

Kent

Forecast Out- Anticipated Actions for next 3

Allocation Highway

2008 – 09 2008 - 09 Original KHS Location Description of Works Current Progress months Services

turn Ref (Prior to next JTB) Contact 08458 247800

Old Rd West Crash Remedial 08-ITS- (B261) / Wrotham Measure - Junction Works completed N/a £5k £5k Geoff Dance GR-09 Rd (A227) - improvements – signing Gravesend & lining

Pedestrian crossing 08-ITS- Various locations – Simon improvements – various Works completed N/a £25k £25k GR-07 Gravesend Allsopp locations

08-ITS- Thames Way – GR- Extension of cycle-route. Works completed Monitoring £47k £30k Julian Cook Northfleet 010

Pedestrian crossing improvements – 08-ITS- B260 – Longfield Simon provision of dropped Works completed N/a £50k £50k GR-06 Road – Meopham. Allsopp kerbs at various locations

08-ITS- Wrotham Rd – Andy Extension of cycle route Works completed Monitoring £30k £50k GR-08 Istead Rise Padgham

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway and Transportation Schemes Progress Report 2008/09Report 44 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 22 attended
CC
County Councillor Michael SnellingChair, present
WD
Cllr William DykeVice-Chair, present
CC
Cllr Colin CallerCommittee Member, present
GG
Cllr Greta GoatleyCommittee Member, present
SL
Cllr Sara LangdaleCommittee Member, present
RS
Cllr Richard SmithCommittee Member, apologies
CC
County Councillor Jane CribbonCommittee Member, present
CC
County Councillor Leslie ChristieCommittee Member, present
CC
County Councillor Maureen NewellCommittee Member, present
CC
County Councillor Ray ParkerCommittee Member, present
KA
Kent Association of Parish CouncilsNon-elected, non-voting, expected
CP
Cobham Parish CouncilNon-elected, non-voting, expected

All 22 on the meeting page

On this subject at Gravesham

Search all
  1. Highway and Transportation Schemes Progress Report 2008/09This decision
  2. Kent Highways and Transportation (KH&T) Structure 2011Noted
  3. Highway and Transportation Schemes Progress ReportNoted
  4. Highway and Transportation Schemes Progress ReportNoted
  5. Highway and Transportation Schemes Progress ReportNoted
  6. Highway and Transportation Schemes Progress Report 2009/10Noted

More from Gravesham Gravesham Joint Transportation Board

All decisions
MeetingDecisionOutcome
10 Mar 2021 Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. Noted Open
10 Mar 2021 Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. Noted Open
10 Mar 2021 Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... Agreed Open
14 Mar 2018 Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham D... Noted Open
14 Mar 2018 Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... Agreed Open