Resolved
Resolved that the report be noted.
Gravesham Joint Transportation Board noted this item on Wednesday 17 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the report be noted.
2.1The Scheme Prioritisation System has been developed to enable the assessment of every scheme proposed and to compare with other schemes to see how they contribute to national, regional and local transport targets. The score achieved by a scheme shows the contribution it makes to these targets with the highest scoring schemes contributing most to the targets. The system acts as a guide for officers and Members in deciding which schemes should be funded and constructed.
2.2The Scheme Prioritisation System is based around the four shared transport priorities recommended by the Local Government Association in 2005 of tackling congestion, improving accessibility, increasing road safety and improving air quality. Each scheme is attributed a score based on how it meets with these targets. The Scheme Prioritisation System puts more emphasis on road safety schemes and gives the Joint Transportation Boards the opportunity to allocate its top eight priority schemes bonus points.
2.3A more detailed report on the Scheme Prioritisation System that went to the County Council’s Highways Advisory Board on the 5th May 2009 is included in Appendix B. 2.4 The County Council will be inviting Members of this Board to attend a seminar on the Scheme Prioritisation System in the summer. This will provide further guidance and advice to JTBs as to how to allocate its bonus points.
3. 2010 / 11 Programme
3.1Appendix A lists the Gravesham schemes assessed using the Scheme Prioritisation System and also shows the provisional scores which will be subject to change when this Board allocates its bonus points.
BACKGROUND PAPERS: Report to Highways Advisory Board dated 5th May 2009 included as Appendix B below.
All requests to inspect the above documents MUST be directed in the first instance to the Committee Section of the Democratic Services Department
CONTACT OFFICER: Peter Slaughter 01622 798431
2 APPENDIX A Schemes assessed for bids in 2010/11
Estimated Provisional Ref Nr Scheme Title Ward Cost (£k) Score 1 A226 East Milton Rd Pedestrian Crossing Improvements Gravesham Central 46 53
2 Northfleet Station pedestrian link to Ebbsfleet - design Northfleet North 50 70
3 Leander Drive Safety Improvements Riverview 86.25 50
4 Coldharbour Rd uncontrolled crossing + footway improvements Coldharbour 46 56
5 Colyer Rd and Vale Rd crossings Northfleet south 92 50
6 Mulberry Rd traffic calming Painters Ash 172.5 48
7 Lorry route signing in Gravesend Various 34.51 13
8 Pedestrian crossing and dropped crossing improvements Various 57.5 25
9 Gravesend UTMC Central 290 66
Shorne, Cobham and 10 Sole Street footway – phase 1 17.25 51 Luddesdown Shorne, Cobham and 11 Sole Street footway – phase 2 86.25 51 Luddesdown
12 Dering Way cycle path Riverside 80.5 54
13 Minor cycling improvements Central 5 71
14 St Marks Avenue – proposed one-way system Northfleet North 58 9
15 New footway connection at The Parade, Meopham Meopham North 6 23
16 Pedestrian crossing on London Rd in Northfleet Northfleet North 46 33
17 Windmill Street footway widening Pelham 29 21 APPENDIX B
To be included here
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Integrated Transport Programme 2010-11 Appendix OneAppendix | 93 KB | Download |
PDF |
Integrated Transport Programme 2010/11Report | 22 KB | DownloadRead as text |
Follow Gravesham Joint Transportation Board at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2021 | Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. | Noted | Open |
| 10 Mar 2021 | Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. | Noted | Open |
| 10 Mar 2021 | Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... | Agreed | Open |
| 14 Mar 2018 | Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham D... | Noted | Open |
| 14 Mar 2018 | Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.