Harden Road, Northfleet - Update on Development Project

Decided Executive 1 paper

Cabinet decided this item on Monday 8 March 2010. Below is the council's own wording, with the papers it was decided on.

Item124

Resolved

The Cabinet authorised the Director (Business) in consultation with the Director (Housing & Environment), Assistant Director (Business & Law) and Lead Member for Housing to award a contract for the Harden Road scheme following a tender process that is compliant with the council’s Procurement Rules.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Last Amended 23.2.2010

Gravesham Borough Council

Report to: Cabinet

Date: 8 March 2010

Reporting officer: Director (Business)

Subject: Update on Development Project at Harden Road, Northfleet.

Purpose and summary of report: To update members on the Harden Road development project and to request authorisation to enter into a contract to deliver the proposed new council homes at Harden Road, Northfleet. Recommendations That Members authorise the Director (Business) in consultation with the Director (Housing & Environment), Assistant Director (Business & Law) and Lead Member for Housing to award a contract for the Harden Road scheme following a tender process that is compliant with the council’s Procurement Rules.

1. Introduction 1.1 Members have previously received reports on the proposal to deliver new council owned homes on a council-owned site at Harden Road with funding from the Homes and Communities Agency (HCA) to be match funded with prudential borrowing undertaken by the council.

1.2Following a bid to the HCA in October 2009, it was announced in mid January 2010 that the council had been successful in its bid and had been allocated £345,000 which amounts to approximately 50% of the total scheme costs.

1.3Members have previously agreed that up to £400,000 be made available through prudential borrowing in order to match fund the level of grant received from the HCA, with the annual costs of repaying the borrowing met by the rental income from the new homes.

2. Progress on Scheme

2.1The HCA has imposed a very tight timescale on the implementation of this scheme, requiring development to commence in June 2010. If this date is not achieved, the entire HCA funding may be forfeited. In order to comply with these timescales, the following timetable will have to be achieved:-

2.1.1 Tender period 1 March 2010 with tenders being returned by noon on 12 April 2010.

-1- Last Amended 23.2.2010

2.1.2 Tender analysis by end April 2010

2.1.3 Appointment of contractor week 1 of May 2010

2.1.4 Start on site by June 2010

2.2In order to keep to this tight timescale the actions listed below will be undertaken.

2.2.1 One of the council’s partner associations (Russet Homes) will be appointed to act as Development Agent. Russet Homes will provide advice and assistance on managing the HCA grant funding and will project manage the scheme from start on site to completion and handover to the council. A Development Agency agreement between Russet Homes and the council has been drawn up by solicitors acting for the council (Thomson, Snell and Passmore).

2.2.2 An Employer’s Agent will be appointed as recommended in HCA guidance for Local Authorities bidding for funding through the LA New Build route. The Employer’s Agent will act as an independent consultant whose scope of works will include preparing a schedule of Employers Requirements, providing contractual advice, obtaining and evaluating tenders and preparing contract documents and controlling post contract costs (this list is not exhaustive). The Employer’s Agent will also arrange for all necessary site surveys to be carried out prior to tenders being invited. Subsequently a ‘letter of appointment’ detailing the Scope of Works has been drawn up between Potter Raper Partnership and the council by Thomson, Snell and Passmore.

2.2.3 Potter Raper will provide a list of recommended and approved contractors to the council for consideration and approval. Tenders will then be invited with a submission date of end April.

2.2.4 Russet Homes in consultation with Potter Raper will then make a recommendation to the council of a preferred contractor. The final decision on the selection of contractor for the works will remain with the council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Harden Road, Northfleet: Update on Development ProjectReport 37 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 19 attended
HD
Hardip DhaliwalOfficer, expected
MS
Cllr Michael SnellingChair, present
DT
Cllr David TurnerVice-Chair, present
JC
Cllr John CubittCommittee Member, present
LH
Cllr Laura HryniewiczCommittee Member, absent
AP
Cllr Anthony PritchardCommittee Member, present
AW
Cllr Adrian WarburtonCommittee Member, present
LC
Cllr Lee CroxtonGuest, in attendance
AW
Cllr Andrea WebbGuest, in attendance
NC
Nick ChannonOfficer, present
GT
Glyn ThomsonOfficer, present
MH
Mike HayleyOfficer, present

All 19 on the meeting page

On this subject at Gravesham

Search all
  1. Harden Road, Northfleet - Update on Development ProjectThis decision
  2. Harden Road Project and Funding Options - UpdateAgreed
  3. Local Authority Bidding for New Build and Update on Harden Road Project (Delivery of 5 Council - Owned Affordable Housing Units)Agreed
  4. GR/2009/0614 - Site of Former Scout Hut accessed between 11 and 13 Harden Road, Northfleet, Kent.Decided
  5. GR/2009/0614 - Site of Former Scout Hut accessed between 11 and 13 Harden Road, Northfleet, Kent.Deferred

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies