The Cabinet authorised the Director (Business) in consultation with the Director (Housing & Environment), Assistant Director (Business & Law) and Lead Member for Housing to award a contract for the Harden Road scheme following a tender process that is compliant with the council’s Procurement Rules.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Subject: Update on Development Project at Harden Road, Northfleet.
Purpose and summary of report: To update members on the Harden Road development project and to request authorisation to enter into a contract to deliver the proposed new council homes at Harden Road, Northfleet. Recommendations That Members authorise the Director (Business) in consultation with the Director (Housing & Environment), Assistant Director (Business & Law) and Lead Member for Housing to award a contract for the Harden Road scheme following a tender process that is compliant with the council’s Procurement Rules.
1. Introduction 1.1 Members have previously received reports on the proposal to deliver new council owned homes on a council-owned site at Harden Road with funding from the Homes and Communities Agency (HCA) to be match funded with prudential borrowing undertaken by the council.
1.2Following a bid to the HCA in October 2009, it was announced in mid January 2010 that the council had been successful in its bid and had been allocated £345,000 which amounts to approximately 50% of the total scheme costs.
1.3Members have previously agreed that up to £400,000 be made available through prudential borrowing in order to match fund the level of grant received from the HCA, with the annual costs of repaying the borrowing met by the rental income from the new homes.
2. Progress on Scheme
2.1The HCA has imposed a very tight timescale on the implementation of this scheme, requiring development to commence in June 2010. If this date is not achieved, the entire HCA funding may be forfeited. In order to comply with these timescales, the following timetable will have to be achieved:-
2.1.1 Tender period 1 March 2010 with tenders being returned by noon on 12 April 2010.
-1- Last Amended 23.2.2010
2.1.2 Tender analysis by end April 2010
2.1.3 Appointment of contractor week 1 of May 2010
2.1.4 Start on site by June 2010
2.2In order to keep to this tight timescale the actions listed below will be undertaken.
2.2.1 One of the council’s partner associations (Russet Homes) will be appointed to act as Development Agent. Russet Homes will provide advice and assistance on managing the HCA grant funding and will project manage the scheme from start on site to completion and handover to the council. A Development Agency agreement between Russet Homes and the council has been drawn up by solicitors acting for the council (Thomson, Snell and Passmore).
2.2.2 An Employer’s Agent will be appointed as recommended in HCA guidance for Local Authorities bidding for funding through the LA New Build route. The Employer’s Agent will act as an independent consultant whose scope of works will include preparing a schedule of Employers Requirements, providing contractual advice, obtaining and evaluating tenders and preparing contract documents and controlling post contract costs (this list is not exhaustive). The Employer’s Agent will also arrange for all necessary site surveys to be carried out prior to tenders being invited. Subsequently a ‘letter of appointment’ detailing the Scope of Works has been drawn up between Potter Raper Partnership and the council by Thomson, Snell and Passmore.
2.2.3 Potter Raper will provide a list of recommended and approved contractors to the council for consideration and approval. Tenders will then be invited with a submission date of end April.
2.2.4 Russet Homes in consultation with Potter Raper will then make a recommendation to the council of a preferred contractor. The final decision on the selection of contractor for the works will remain with the council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.