CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gravesham Borough Council
Cabinet, Monday 15 November 2010 at 7.00pm

Mail Room Inserting Equipment

Approved Executive 2 papers

Cabinet approved this item on Monday 15 November 2010. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

The Cabinet approved Option Two as outlined within Section 4 of the report, with this being funded through the following financial mechanisms; Use of the Spend to Save reserve to meet the £33,330 purchase cost of the new insertion machine, with this being an addition to the authority’s General Fund Capital Programme for 2010-11. Recycling of the resulting savings from the procurement of the new insertion equipment (at £8,170 ( Yr1 ) and £10,970 (Yrs 2 to 5) per annum) back to the Spend to Save reserve, until the initial capital outlay has been repaid, with all further savings being received by the authority’s General Fund.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
20101116135737349Report 113 KB Download
PDF
Mail Room Inserting EquipmentReport 86 KB Download

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies