Resolved
It was agreed that the Local Development Scheme be approved and published on the Council’s website.
Cabinet agreed this item on Monday 7 October 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the Local Development Scheme be approved and published on the Council’s website.
1.1The Planning and Compulsory Purchase Act 2004 (as amended) places a statutory duty on the Council to maintain an up-to-date Local Development Scheme. The revised Local Development Scheme attached to this report (Appendix 2) would fulfil this requirement.
1.2The Borough’s Local Plan Core Strategy was adopted by the Council on 30 September 2014. Following the adoption of the Core Strategy officers turned their attention to identifying whether or not a partial review of the Core Strategy was needed, as well as progressing work on the Site Allocations and Development Management Policies Document. The latter document being the second part of the Council’s Local Plan, which would allocate additional sites for development, designates sites / land for specific uses and would set out the detailed Development Management policies.
1.3Delays to the work programme due to a number of factors e.g. delays in evidence gathering, insufficient officer resources because of resources being directed to other Council priorities e.g. Lower Thames Crossing or leaving, has meant that the overall timetable has slipped. A revised programme addressing these delays and taking into account current resources is set out in the revised Local Development Scheme.
1.4The Local Development Scheme is used to monitor the Council’s progress in producing planning policy documents as part of the Authority’s Monitoring Report.
2. Local Development Scheme
2.1All local planning authorities are required to produce a Local Development Scheme. The Local Development Scheme outlines a public timetable for the preparation and adoption of Local Plan documents the Council intends to prepare. This revised Local Development Scheme would supersede the Local Development Scheme adopted in July 2017, and covers the period 2018-2021.
2.2A Local Development Scheme is required to set out:
The development plan documents that are to be developed
The subject matter and geographical coverage of the documents being developed
Whether any of the documents being developed are being prepared jointly with other local planning authorities
The timetable for the preparation of the document(s)
2.3Regulations require that the Council specify a date that the Local Development Scheme will come into effect, and it is proposed that the effective date for the new Local Development Scheme is 8 October 2019.
2.4The Government requires Local Plans to be kept up to date and reviewed on a 5 yearly basis. During the preparation of the Local Plan Core Strategy, there were a number of legislative and policy changes that necessitated changes to the Local Plan Core Strategy during its preparation and during examination, such as the Localism Act 2011, which introduced Neighbourhood Planning and paved the way for the revocation of Regional Spatial Strategies and their replacement with a ‘duty to co-operate’ on strategic planning matters.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
20191007 Appendix 2: Local Development Scheme 2019Appendix | 174 KB | Download |
PDF |
Local Plan: Local Development SchemeReport | 95 KB | DownloadRead as text |
Follow Cabinet at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... | Refused | Open |
| 28 Sep 2026 | Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. | Agreed | Open |
| 28 Sep 2026 | Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... | Noted | Open |
| 28 Sep 2026 | Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... | Decided | Open |
| 28 Sep 2026 | LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.