that authority be delegated to the Director (Planning and Development) in consultation with the Leader of the Executive and the Section 151 Officer, to award a build contract to the successful contractor following a selection process via the South East Consortium (SEC) for the demolition of 36 bedsits and the construction of 48 new Council homes consisting of 32 x 1 bed flats for over 55s and 16 general needs flats for rent.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Director (Planning and Development)
Subject: Development on Land at Valley Drive, Gravesend
Purpose and summary of report: To seek authority to award a build contract for the development of 48 new Council homes on land at Valley Drive, Gravesend. Recommendations: 1. That authority be delegated to the Director (Planning and Development) in consultation with the Leader of the Executive and the Section 151 Officer, to award a build contract to the successful contractor following a selection process via the South East Consortium (SEC) for the demolition of 36 bedsits and the construction of 48 new Council homes consisting of 32 x 1 bed flats for over 55s and 16 general needs flats for rent.
1. Valley Drive
1.1A planning application for the above development was submitted by the Council and presented to Regulatory Board in May 2019. The application (reference2019/0155) was recommended for permission subject to conditions and a Unilateral Undertaking in respect of financial obligations to Kent County Council and the NHS. Full permission was subsequently granted on 17 September 2019.
2. Tender Process
2.1Potter Raper Limited is appointed as the Council’s Employers Agent. PRP has prepared tender documents based on the drawings submitted to the LPA and the Council’s agreed Employer’s Requirements, and has submitted these to the South East Consortium (SEC) Framework to which the Council has membership.
2.2Potter Raper Limited provided an estimate for the works which was confirmed as being in excess of the Key Decision threshold of £100,000.
2.3Tender documents were received back from the SEC on 8th November. Potter Raper Limited in consultation with officers from the Housing Strategy and Development team have evaluated the tenders and have provided a tender report for the Design and Build of Blocks A and B at Valley Drive.
2.4Following post-tender evaluation, Potter Raper Limited has recommended Westridge Construction Limited be awarded the Design and Build Contract for the scheme. Details of the anticipated costs can be found at Appendix 2 which is in the private part of this agenda.
2.5Right to Buy (RTB) receipts can only be used on any net increase of homes. Therefore, due to the demolition of 36 bedsits on site, RTB receipts can only be used on the net increase of 12 units.
2.6The Council will need to fund delivery of the remaining 36 homes from borrowing. This element will form part of the authority’s overall borrowing requirement in 2020/21 and 2021/22. Officers will review all options available at such time and will make the necessary steps to securing funding, in accordance with the Council’s Treasury Management Strategy Statement and in consultation with the Council’s Section 151 Officer.
3. Viability
3.1Officers from the Finance Department and Housing Strategy and Development team are currently assessing the scheme and considering different tenures and rent levels.
3.2Current policy for the Council’s new build homes is to charge either Affordable Rent (inclusive of service charges) or the Local Housing Allowance (LHA) rate for each property, whichever is the lower.
3.3Charging Affordable Rent based at LHA rates currently gives a payback period of between 25-26 years
3.4Investigation into charging social rent plus service charge for the 32 homes for people over 55 will be carried out as the intention is to promote these new homes to existing Council residents who are currently under occupying in an attempt to encourage them to ‘re-size’ to a more appropriate home and in doing so, free up larger family homes. Areas to consider include resident perception and the amount of service charge that is Housing Benefit attributable.
3.5Details of viability based on varying rent levels will be subject to further discussions with the Lead Member for Housing.
4. Funding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.